Skip to main content

South Star Battery Metals Announces 2023 Positive Drilling Program Results for the BamaStar Graphite Project in Coosa County Alabama and NI43-101 Preliminary Economic Assessment Study Update

VANCOUVER, BC / ACCESSWIRE / November 8, 2023 / South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF), is pleased to announce that its 2023 drilling campaign has been completed on its BamaStar Graphite Project in Coosa County, Alabama. The program was designed to test continuity and limits of mineralization in support of the upcoming NI43-101 Preliminary Economic Assessment (PEA), scheduled for completion at the end of Q1 2024. 15 holes totaling approximately 1,900 meters were successfully completed, and all holes at BamaStar have intercepted significant intervals of graphite mineralization.

During the drilling, several potentially promising zones were intersected as can be seen in the below photograph (Figure 1).

Figure 1: Hole CMD 23-022 Core with Graphite Mineralization with Approximately 3.5% Grade (Cg)

Initial notable assay results have confirmed the prospectivity of several significant intersections as seen in Table 1 below based on a 1% cutoff grade.

Hole ID

Hole Depth

From

To

Interval

Grade Cg

CMD23013

107.0m

0m

8m

8m

2.54%

CMD23014

125.0m

0m

23m

23m

2.17%

CMD23015

140.6m

9m

62.3m

53.3m

2.51%

CMD23016

95.0m

0m

60.9

60.9m

2.30%

CMD23016

N/A

70.8m

79m

8.1m

2.88%

CMD23017

128.0m

3.5m

36.5m

33m

3.07%

CMD23017

N/A

73.8

119.6m

45.8m

2.34%

CMD23018

95.0m

0m

63m

63m

2.42%

CMD23019

155.0m

88m

144.7

56.7m

2.77%

CMD23020

149.0m

3.5m

9,4m

5.9m

1.84%

CMD23020

N/A

70.2m

78.5m

8.3m

1.40%

CMD23021

74m

0m

34.7m

34.7m

2.39%

CMD23021

N/A

52.8m

67.7m

14.9m

2.40%

CMD23022

83m

0m

36m

36m

3.71%

CMD23022

N/A

44.03

75.5

31.5

1.92%

CMD23023

86m

0m

18.5m

18.5m

2.23%

CMD23023

N/A

24.0

35

11m

2.30%

CMD23024

173m

5m

14m

9m

3.34%

CMD23024

N/A

26.3m

64.5m

38.2m

2.25%

CMD23024

N/A

99.7m

152m

52.3m

1.61%

CMD23025

182m

0m

30.4m

30.4m

2.27%

CMD23025

N/A

35m

45.4m

10.4m

1.86%

CMD23025

N/A

144.5m

182m

37.5m

2.08%

CMD23026

146m

0m

20m

20m

2.78%

CMD23026

N/A

96.5m

146m

49.5m

1.54%

CMD23027

146m

2m

23.2m

21.2m

2.33%

CMD23027

N/A

44.6m

54.5m

9.9m

3.27%

CMD23027

N/A

75.5m

111.5m

36m

1.32%

Table 1: 2023 Campaign Significant Intersections in the fifteen holes (1885m) drilled at the BamaStar project.

Richard Pearce, CEO of South Star said, "Our 2023 drilling campaign was extremely successful, and every hole has significant intervals with graphite mineralization. We tested controls and limits at depth, across the ore body, as well as along strike. We discovered a significant deeper mineralized package below what we had previously drilled, and there are several holes that ended in mineralization. We are open at depth and in both directions along strike. These results will be incorporated into an updated resource definition as part of our upcoming PEA scheduled for March 2024, and this deliverable should complete our 75% earn-in requirements on the properties. We are also on schedule to complete our Feasibility Study for Santa Cruz Mine incorporating Phase 3 (50,000 tpa of concentrates) by end of 2024. Our goals are to have two mines producing a total of 100,000 tpa of concentrates, and 60,000-70,000 tpa of vertically integrated graphite production including active anode materials and other critical graphite products in the US in 2027."

About South Star Battery Metals Corp

South Star Battery Metals Corp. is a Canadian battery metals project developer focused on the selective acquisition and development of near-term production projects in the Americas. South Star's Santa Cruz Graphite Project, located in Southern Bahia, Brazil is the first of a series of industrial and battery metals projects that will be put into production. Brazil is the second-largest graphite-producing region in the world with more than 80 years of continuous mining. Santa Cruz has at-surface mineralization in friable materials, and successful large-scale pilot-plant testing (> 30t) has been completed. The results of the testing show that approximately 65% of Cg concentrate is +80 mesh with good recoveries and 95%-99% Cg. With excellent infrastructure and logistics, South Star is fully funded for Phase 1, and the 12-month construction and commissioning are underway. Santa Cruz will be the first new graphite production in the Americas since 1996 with Phase 1 commercial production projected in Q4 2023. Phase 2 production (25,000 tpa) is partially funded and planned for 2026, while Phase 3 (50,000 tpa) is scheduled for 2028.

South Star's second project in the development pipeline is strategically located in Alabama in the center of a developing electric vehicle, aerospace, and defense hub in the southeastern United States. The BamaStar Project is a historic mine active during World Wars I & II. A NI43-101 technical report with the maiden resource estimate has been filed on SEDAR. Trenching, phase 1 drilling, sampling, analysis, and preliminary metallurgical testing have been completed. The testing indicates a traditional crush/grind/flotation concentration circuit that achieved grades of approximately 94-97% Cg with approximately 86% recoveries. South Star is executing on its plan to create a multi-asset, diversified battery metals company with near-term operations in strategic jurisdictions. South Star trades on the TSX Venture Exchange under the symbol STS, and on the OTCQB under the symbol STSBF.

South Star is committed to a corporate culture, project execution plan and safe operations that embrace the highest standards of ESG principles based on transparency, stakeholder engagement, ongoing education, and stewardship. To learn more, please visit the Company website at http://www.southstarbatterymetals.com.

This news release has been reviewed and approved by Richard Pearce, P.E., a "Qualified Person" under National Instrument 43-101 and President and CEO of South Star Battery Metals Corp.

On behalf of the Board,

MR. RICHARD PEARCE
Chief Executive Officer

For additional information, please contact:

South Star Investor Relations
Email: invest@southstarbatterymetals.com
+1 (604) 706-0212

Twitter: https://twitter.com/southstarbm
Facebook: https://www.facebook.com/southstarbatterymetals
LinkedIn: https://www.linkedin.com/company/southstarbatterymetals/
YouTube: South Star Battery Metals - YouTube

CAUTIONARY STATEMENT

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Forward-Looking Information

This press release contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements". Forward-looking statements in this press release include, but are not limited to, statements regarding, moving Santa Cruz into production and scaling operations as well as advancing the Alabama project; and the Company's plans and expectations.

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

SOURCE: South Star Battery Metals Corp.



View source version on accesswire.com:
https://www.accesswire.com/800948/south-star-battery-metals-announces-2023-positive-drilling-program-results-for-the-bamastar-graphite-project-in-coosa-county-alabama-and-ni43-101-preliminary-economic-assessment-study-update

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.