FIRSTENERGY CORP.
 
34-1843785
   
(An Ohio Corporation)
   
   
76 South Main Street
   
   
Akron, OH  44308
   
   
Telephone (800)736-3402
   
         
         
000-53742
 
FIRSTENERGY SOLUTIONS CORP.
 
31-1560186
   
(An Ohio Corporation)
   
   
76 South Main Street
   
   
Akron, OH  44308
   
   
Telephone (800)736-3402
   










 












Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2.):

[ ] Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
[ ] Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
[ ] Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
[ ] Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
 
 
 
 
 

 
 

Item 2.06  Material Impairments

On August 12, 2010, officers of FirstEnergy Generation Corp., a wholly owned subsidiary of FirstEnergy Solutions Corp., announced plans to make operational changes at the following smaller coal-fired generating units, which have a combined generating capacity of approximately 1,620 megawatts, in response to the continued slow economy and lower demand for electricity, as well as uncertainty related to proposed new federal environmental regulations:

·  
Bay Shore Plant units 2-4 in Oregon, Ohio;
 
·  
Eastlake Plant units 1-4 in Eastlake, Ohio;
 
·  
Lake Shore Plant in Cleveland, Ohio; and
 
·  
Ashtabula Plant in Ashtabula, Ohio.
 
Management determined as of that date that an impairment charge of up to $287 million could result, which could reduce FirstEnergy Corp.’s third quarter 2010 earnings by up to $0.59 per share of common stock.  It is expected that no future cash expenditures would result in connection with any resulting impairment charge.

FirstEnergy Solutions Corp. is a wholly owned subsidiary of FirstEnergy Corp.

On August 12, 2010 FirstEnergy Corp. issued a press release announcing these plans, a copy of which is attached hereto as Exhibit 99.1 and incorporated by reference herein.


Item 9.01  Financial Statements and Exhibits

(d)  
Exhibits

Exhibit No.                                                      Description

99.1  
          Press release dated August 12, 2010

 
 
 
2

 
 

 

Forward-Looking Statements: This Form 8-K includes forward-looking statements based on information currently available to management. Such statements are subject to certain risks and uncertainties. These statements include declarations regarding management’s intents, beliefs and current expectations. These statements typically contain, but are not limited to, the terms “anticipate,” “potential,” “expect,” “believe,” “estimate” and similar words. Forward-looking statements involve estimates, assumptions, known and unknown risks, uncertainties and other factors that may cause actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Actual results may differ materially due to the speed and nature of increased competition in the electric utility industry and legislative and regulatory changes affecting how generation rates will be determined following the expiration of existing rate plans in Pennsylvania, the impact of the regulatory process on the pending matters in Ohio, Pennsylvania and New Jersey, business and regulatory impacts from American Transmission Systems, Incorporated’s realignment into PJM Interconnection, L.L.C., economic or weather conditions affecting future sales and margins, changes in markets for energy services, changing energy and commodity market prices and availability, replacement power costs being higher than anticipated or inadequately hedged, the continued ability of FirstEnergy’s regulated utilities to collect transition and other charges or to recover increased transmission costs, operating and maintenance costs being higher than anticipated, other legislative and regulatory changes, revised environmental requirements, including possible greenhouse gas emission regulations, the potential impacts of the proposed rules promulgated by EPA on July 6, 2010 in response to the U.S. Court of Appeals’ July 11, 2008 decision requiring revisions to the Clean Air Interstate Rules and the scope of any laws, rules or regulations that may ultimately take their place, the uncertainty of the timing and amounts of the capital expenditures needed to, among other things, implement the Air Quality Compliance Plan (including that such amounts could be higher than anticipated or that certain generating units may need to be shut down) or levels of emission reductions related to the Consent Decree resolving the New Source Review litigation or other similar potential regulatory initiatives or actions, adverse regulatory or legal decisions and outcomes (including, but not limited to, the revocation of necessary licenses or operating permits and oversight) by the Nuclear Regulatory Commission, Metropolitan Edison Company’s and Pennsylvania Electric Company’s transmission service charge filings with the Pennsylvania Public Utility Commission, the continuing availability of generating units and their ability to operate at or near full capacity, the ability to comply with applicable state and federal reliability standards, the ability to accomplish or realize anticipated benefits from strategic goals (including employee workforce initiatives), the ability to improve electric commodity margins and to experience growth in the distribution business, the changing market conditions that could affect the value of assets held in FirstEnergy’s nuclear decommissioning trusts, pension trusts and other trust funds, and cause it to make additional contributions sooner, or in an amount that is larger than currently anticipated, the ability to access the public securities and other capital and credit markets in accordance with FirstEnergy’s financing plan and the cost of such capital, changes in general economic conditions affecting the company, the state of the capital and credit markets affecting the company, interest rates and any actions taken by credit rating agencies that could negatively affect FirstEnergy’s access to financing or its costs or increase its requirements to post additional collateral to support outstanding commodity positions, letters of credit and other financial guarantees, the continuing decline of the national and regional economy and its impact on the company’s major industrial and commercial customers, issues concerning the soundness of financial institutions and counterparties with which FirstEnergy does business, the expected timing and likelihood of completion of the proposed merger with Allegheny Energy, Inc., including the timing, receipt and terms and conditions of any required governmental and regulatory approvals of the proposed merger that could reduce anticipated benefits or cause the parties to abandon the merger, the diversion of management’s time and attention from our ongoing business during this time period, the ability to maintain relationships with customers, employees or suppliers as well as the ability to successfully integrate the businesses and realize cost savings and any other synergies and the risk that the credit ratings of the combined company or its subsidiaries may be different from what the companies expect and the risks and other factors discussed from time to time in the registrants’ Securities and Exchange Commission filings, and other similar factors. The foregoing review of factors should not be construed as exhaustive. New factors emerge from time to time, and it is not possible for management to predict all such factors, nor assess the impact of any such factor on the registrants’ business or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking statements. The registrants expressly disclaim any current intention to update any forward-looking statements contained herein as a result of new information, future events, or otherwise.
 
 
SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the Registrants have duly caused this report to be signed on their behalf by the undersigned thereunto authorized.



August 13, 2010

 
 
 FIRSTENERGY CORP.
 
 Registrant
   
   FIRSTENERGY SOLUTIONS CORP.
   Registrant
   
 By:  
 
/s/ Harvey L. Wagner
 
Harvey L. Wagner
Vice President, Controller and
Chief Accounting Officer
 
 
 

 



 


 
 
3