2014.3.31-10Q
Table of Contents


UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, DC 20549
FORM 10-Q
x
QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the quarterly period ended March 31, 2014

 

Commission
 
Registrant, State of Incorporation,
 
I.R.S. Employer
File Number
 
Address and Telephone Number
 
Identification No.
1-8809
 
SCANA Corporation (a South Carolina corporation)
 
57-0784499
1-3375
 
South Carolina Electric & Gas Company (a South Carolina corporation)
 
57-0248695
 
 
100 SCANA Parkway, Cayce, South Carolina 29033
 
 
 
 
(803) 217-9000
 
 

Indicate by check mark whether the registrant: (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days. SCANA Corporation Yes x No ¨  South Carolina Electric & Gas Company Yes x No ¨
 
Indicate by check mark whether the registrant has submitted electronically and posted on its corporate Web site, if any, every Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S-T during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files). SCANA Corporation Yes x No ¨  South Carolina Electric & Gas Company Yes x No ¨
 
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, or a smaller reporting company.  See definitions of “large accelerated filer,” “accelerated filer” and “smaller reporting company” in Rule 12b-2 of the Exchange Act.
SCANA Corporation
Large accelerated filer  x
Accelerated filer  ¨
Non-accelerated filer  ¨
 
Smaller reporting company  ¨
 
 
South Carolina Electric & Gas Company
Large accelerated filer  ¨
Accelerated filer  ¨
Non-accelerated filer  x
 
Smaller reporting company  ¨
 
 

Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act).
SCANA Corporation Yes ¨ No x  South Carolina Electric & Gas Company Yes ¨ No x
 
Indicate the number of shares outstanding of each of the issuer’s classes of common stock, as of the latest practicable date.
 
Description of
Shares Outstanding
Registrant
Common Stock
at April 30, 2014
SCANA Corporation
Without Par Value
141,591,499
South Carolina Electric & Gas Company
Without Par Value
        40,296,147 (a)
 (a) Held beneficially and of record by SCANA Corporation.
 
This combined Form 10-Q is separately filed by SCANA Corporation and South Carolina Electric & Gas Company.  Information contained herein relating to any individual company is filed by such company on its own behalf.  Each company makes no representation as to information relating to the other company.
 
South Carolina Electric & Gas Company meets the conditions set forth in General Instruction H(1)(a) and (b) of Form 10-Q and therefore is filing this Form with the reduced disclosure format allowed under General Instruction H(2).


Table of Contents

TABLE OF CONTENTS 
MARCH 31, 2014

 
Page
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

2

Table of Contents

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
 
Statements included in this Quarterly Report on Form 10-Q which are not statements of historical fact are intended to be, and are hereby identified as, “forward-looking statements” for purposes of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended.  Forward-looking statements include, but are not limited to, statements concerning key earnings drivers, customer growth, environmental regulations and expenditures, leverage ratio, projections for pension fund contributions, financing activities, access to sources of capital, impacts of the adoption of new accounting rules and estimated construction and other expenditures.  In some cases, forward-looking statements can be identified by terminology such as “may,” “will,” “could,” “should,” “expects,” “forecasts,” “plans,” “anticipates,” “believes,” “estimates,” “projects,” “predicts,” “potential” or “continue” or the negative of these terms or other similar terminology.  Readers are cautioned that any such forward-looking statements are not guarantees of future performance and involve a number of risks and uncertainties, and that actual results could differ materially from those indicated by such forward-looking statements.  Important factors that could cause actual results to differ materially from those indicated by such forward-looking statements include, but are not limited to, the following:
  
(1)
the information is of a preliminary nature and may be subject to further and/or continuing review and adjustment;
(2)
regulatory actions, particularly changes in rate regulation, regulations governing electric grid reliability and pipeline integrity, environmental regulations, and actions affecting the construction of new nuclear units;
(3)
current and future litigation;
(4)
changes in the economy, especially in areas served by subsidiaries of SCANA;
(5)
the impact of competition from other energy suppliers, including competition from alternate fuels in industrial markets;
(6)
the impact of conservation and demand side management efforts and/or technological advances on customer usage;
(7)
the loss of sales to distributed generation, such as solar photovoltaic systems;
(8)
growth opportunities for SCANA’s regulated and diversified subsidiaries;
(9)
the results of short- and long-term financing efforts, including prospects for obtaining access to capital markets and other sources of liquidity;
(10)
the effects of weather, especially in areas where the generation and transmission facilities of SCANA and its subsidiaries (the Company) are located and in areas served by SCANA’s subsidiaries;
(11)
changes in SCANA’s or its subsidiaries’ accounting rules and accounting policies;
(12)
payment and performance by counterparties and customers as contracted and when due;
(13)
the results of efforts to license, site, construct and finance facilities for electric generation and transmission;
(14)
maintaining creditworthy joint owners for SCE&G’s new nuclear generation project;
(15)
the ability of suppliers, both domestic and international, to timely provide the labor, secure processes, components, parts, tools, equipment and other supplies needed, at agreed upon prices, for our construction program, operations and maintenance;
(16)
the results of efforts to ensure the physical and cyber security of key assets and processes;
(17)
the availability of fuels such as coal, natural gas and enriched uranium used to produce electricity; the availability of purchased power and natural gas for distribution; the level and volatility of future market prices for such fuels and purchased power; and the ability to recover the costs for such fuels and purchased power;
(18)
the availability of skilled and experienced human resources to properly manage, operate, and grow the Company’s businesses;
(19)
labor disputes;
(20)
performance of SCANA’s pension plan assets;
(21)
changes in taxes;
(22)
inflation or deflation;
(23)
compliance with regulations;
(24)
natural disasters and man-made mishaps that directly affect our operations or the regulations governing them; and
(25)
the other risks and uncertainties described from time to time in the periodic reports filed by SCANA or SCE&G with the SEC.
       
SCANA and SCE&G disclaim any obligation to update any forward-looking statements.

3

Table of Contents

DEFINITIONS
 
The following abbreviations used in the text have the meanings set forth below unless the context requires otherwise: 
TERM
MEANING
AFC
Allowance for Funds Used During Construction
ANI
American Nuclear Insurers
AOCI
Accumulated Other Comprehensive Income
ARO
Asset Retirement Obligation
BLRA
Base Load Review Act
CA
The designation for a specific pre-fabricated construction module, such as module CA20
CAA
Clean Air Act, as amended
CAIR
Clean Air Interstate Rule
CCR
Coal Combustion Residuals
CEO
Chief Executive Officer
CFO
Chief Financial Officer
CERCLA
Comprehensive Environmental Response, Compensation and Liability Act
CGT
Carolina Gas Transmission Corporation
COL
Combined Construction and Operating License
Company
SCANA, together with its consolidated subsidiaries
Consolidated SCE&G
SCE&G and its consolidated affiliates
Consortium
A consortium consisting of Westinghouse Electric Company LLC and Stone and Webster, Inc., a subsidiary of Chicago Bridge & Iron Company N.V.
Court of Appeals
United States Court of Appeals for the District of Columbia
CSAPR
Cross-State Air Pollution Rule
CUT
Customer Usage Tracker
CWA
Clean Water Act
DHEC
South Carolina Department of Health and Environmental Control
DOE
United States Department of Energy
DSM Programs
Demand reduction and energy efficiency programs
ELG Rule
New federal effluent limitation guidelines for steam electric generating units
Energy Marketing
The divisions of SEMI, excluding SCANA Energy
EPA
United States Environmental Protection Agency
EPC Contract
Engineering, Procurement and Construction Agreement dated May 23, 2008
eWNA
Pilot Electric WNA
FERC
United States Federal Energy Regulatory Commission
Fuel Company
South Carolina Fuel Company, Inc.
GENCO
South Carolina Generating Company, Inc.
GHG
Greenhouse Gas
GWh
Gigawatt hour
IRP
Integrated Resource Plan
IRS
Internal Revenue Service
JEDA
South Carolina Jobs-Economic Development Authority
Level 1
A fair value measurement using unadjusted quoted prices in active markets for identical assets or liabilities
Level 2
A fair value measurement using observable inputs other than those for Level 1, including quoted prices for similar (not identical) assets or liabilities or inputs that are derived from observable market data by correlation or other means
Level 3
A fair value measurement using unobservable inputs, including situations where there is little, if any, market activity for the asset or liability
LOC
Lines of Credit
MGP
Manufactured Gas Plant

4

Table of Contents

MMBTU
Million British Thermal Units
MW
Megawatt
NASDAQ
The NASDAQ Stock Market, Inc.
NCUC
North Carolina Utilities Commission
NEIL
Nuclear Electric Insurance Limited
New Units
Nuclear Units 2 and 3 under construction at Summer Station
NPDES
National Permit Discharge Elimination System
NRC
United States Nuclear Regulatory Commission
NSPS
New Source Performance Standards
Nuclear Waste Act
Nuclear Waste Policy Act of 1982
NYMEX
New York Mercantile Exchange
OCI
Other Comprehensive Income
ORS
South Carolina Office of Regulatory Staff
PGA
Purchased Gas Adjustment
Price-Anderson
Price-Anderson Indemnification Act
PRP
Potentially Responsible Party
PSNC Energy
Public Service Company of North Carolina, Incorporated
Retail Gas Marketing
SCANA Energy
RSA
Natural Gas Rate Stabilization Act
Santee Cooper
South Carolina Public Service Authority
SCANA
SCANA Corporation, the parent company
SCANA Energy
A division of SEMI which markets natural gas in Georgia
SCE&G
South Carolina Electric & Gas Company
SCEUC
South Carolina Energy Users Committee
SCPSC
Public Service Commission of South Carolina
SEC
United States Securities and Exchange Commission
SEMI
SCANA Energy Marketing, Inc.
Summer Station
V. C. Summer Nuclear Station
U. S. Supreme Court
Supreme Court of the United States
VIE
Variable Interest Entity
WNA
Weather Normalization Adjustment


5

Table of Contents












SCANA CORPORATION
FINANCIAL SECTION

6

Table of Contents

PART I.  FINANCIAL INFORMATION

ITEM 1. F INANCIAL STATEMENTS
SCANA CORPORATION
CONDENSED CONSOLIDATED BALANCE SHEETS
(Unaudited) 
Millions of dollars
 
March 31,
2014
 
December 31,
2013
Assets
 
 
 
 
Utility Plant In Service
 
$
12,291

 
$
12,213

Accumulated Depreciation and Amortization
 
(4,050
)
 
(4,011
)
Construction Work in Progress
 
2,856

 
2,724

Plant to be Retired, Net
 
176

 
177

Nuclear Fuel, Net of Accumulated Amortization
 
298

 
310

Goodwill, net of writedown of $230    
 
230

 
230

Utility Plant, Net
 
11,801

 
11,643

Nonutility Property and Investments:
 
 
 
 
     Nonutility property, net of accumulated depreciation of $150 and $150  
 
315

 
317

Assets held in trust, net-nuclear decommissioning
 
104

 
101

Other investments
 
89

 
86

Nonutility Property and Investments, Net
 
508

 
504

Current Assets:
 
 
 
 
Cash and cash equivalents
 
110

 
136

     Receivables, net of allowance for uncollectible accounts of $8 and $6
 
846

 
802

Inventories (at average cost):
 

 
 
Fuel and gas supply
 
146

 
232

Materials and supplies
 
134

 
131

Prepayments and other
 
108

 
120

     Total Current Assets
 
1,344

 
1,421

Deferred Debits and Other Assets:
 
 
 
 
Regulatory assets
 
1,467

 
1,360

Pension asset
 
49

 
47

Other
 
173

 
189

Total Deferred Debits and Other Assets
 
1,689

 
1,596

Total
 
$
15,342

 
$
15,164


See Notes to Condensed Consolidated Financial Statements.

7

Table of Contents

Millions of dollars
 
March 31,
2014
 
December 31,
2013
Capitalization and Liabilities
 
 

 
 

Common Stock - no par value (shares outstanding: March 31, 2014 - 141.3 million; December 31, 2013 - 140.7 million)
 
$
2,307

 
$
2,280

Retained Earnings
 
2,563

 
2,444

Accumulated Other Comprehensive Loss
 
(61
)
 
(60
)
Total Common Equity
 
4,809

 
4,664

Long-Term Debt, net
 
5,388

 
5,395

Total Capitalization
 
10,197

 
10,059

Current Liabilities:
 
 

 
 

Short-term borrowings
 
560

 
376

Current portion of long-term debt
 
53

 
54

Accounts payable
 
390

 
425

Customer deposits and customer prepayments
 
116

 
88

Taxes accrued
 
63

 
206

Interest accrued
 
75

 
82

Dividends declared
 
72

 
69

Derivative financial instruments
 
47

 
8

Other
 
132

 
134

Total Current Liabilities
 
1,508

 
1,442

Deferred Credits and Other Liabilities:
 
 

 
 

Deferred income taxes, net
 
1,710

 
1,703

Deferred investment tax credits
 
31

 
32

Asset retirement obligations
 
583

 
576

Postretirement benefits
 
228

 
227

Regulatory liabilities
 
882

 
966

Other
 
203

 
159

Total Deferred Credits and Other Liabilities
 
3,637

 
3,663

Commitments and Contingencies (Note 9)
 

 

Total
 
$
15,342

 
$
15,164

 
See Notes to Condensed Consolidated Financial Statements.

8

Table of Contents

SCANA CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF INCOME
(Unaudited)
 
 
 
Three Months Ended
 
 
March 31,
Millions of dollars, except per share amounts
 
2014
 
2013
Operating Revenues:
 
 

 
 

Electric
 
$
678

 
$
583

Gas - regulated
 
458

 
382

Gas - nonregulated
 
454

 
346

Total Operating Revenues
 
1,590

 
1,311

Operating Expenses:
 
 

 
 
Fuel used in electric generation
 
212

 
186

Purchased power
 
25

 
7

Gas purchased for resale
 
670

 
501

Other operation and maintenance
 
180

 
176

Depreciation and amortization
 
95

 
93

Other taxes
 
58

 
55

Total Operating Expenses
 
1,240

 
1,018

Operating Income
 
350

 
293

Other Income (Expense):
 
 

 
 
Other income
 
15

 
13

Other expense
 
(14
)
 
(12
)
Interest charges, net of allowance for borrowed funds used during construction of $3 and $2 
 
(76
)
 
(75
)
Allowance for equity funds used during construction
 
7

 
4

Total Other Expense
 
(68
)
 
(70
)
Income Before Income Tax Expense
 
282

 
223

Income Tax Expense
 
89

 
72

Net Income
 
$
193

 
$
151

Per Common Share Data
 
 
 
 
Basic Earnings Per Share of Common Stock
 
$
1.37

 
$
1.13

Diluted Earnings Per Share of Common Stock
 
$
1.37

 
$
1.11

Weighted Average Common Shares Outstanding (millions)
 
 

 
 
Basic
 
141.1

 
134.4

Diluted
 
141.1

 
136.1

Dividends Declared Per Share of Common Stock
 
$
0.5250

 
$
0.5075

 
See Notes to Condensed Consolidated Financial Statements.

9

Table of Contents

SCANA CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(Unaudited) 
 
 
Three Months Ended March 31,
Millions of dollars
 
2014
 
2013
Net Income
 
$
193

 
$
151

Other Comprehensive Income (Loss), net of tax:
 
 
 
 
Unrealized Gains (Losses) on Cash Flow Hedging Activities:
 
 
 
 
Unrealized gains on cash flow hedging activities arising during period, net of tax of $1 and $2
 
1

 
3

(Gains) losses on cash flow hedging activities reclassified to net income, net of tax of $(1) and $2
 
(2
)
 
4

Net unrealized gains (losses) on cash flow hedging activities
 
(1
)
 
7

      Other Comprehensive Income (Loss)
 
(1
)
 
7

Total Comprehensive Income
 
$
192

 
$
158

 
See Notes to Condensed Consolidated Financial Statements.

10

Table of Contents

SCANA CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(Unaudited) 
 
 
Three Months Ended March 31,
Millions of dollars
 
2014
 
2013
Cash Flows From Operating Activities:
 
 

 
 

Net income
 
$
193

 
$
151

Adjustments to reconcile net income to net cash provided from operating activities:
 
 

 
 

Earnings from equity method investments, net of distributions
 
1

 

Deferred income taxes, net
 
7

 
17

Depreciation and amortization
 
99

 
97

Amortization of nuclear fuel
 
15

 
13

Allowance for equity funds used during construction
 
(7
)
 
(4
)
Carrying cost recovery
 
(2
)
 

Changes in certain assets and liabilities:
 

 
 

Receivables
 
(56
)
 
(22
)
Inventories
 
70

 
37

Prepayments and other
 
(5
)
 
21

Regulatory liabilities
 
(94
)
 
26

Accounts payable
 
29

 
5

Taxes accrued
 
(143
)
 
(101
)
Interest accrued
 
(7
)
 
(6
)
Pension and other post retirement benefits
 
(2
)
 

Regulatory assets
 
(108
)
 
12

Other assets
 
28

 
(16
)
Other liabilities
 
120

 
(37
)
Net Cash Provided From Operating Activities
 
138

 
193

Cash Flows From Investing Activities:
 
 

 
 

Property additions and construction expenditures
 
(289
)
 
(291
)
Proceeds from investments (including derivative collateral posted)
 
16

 
100

Purchase of investments (including derivative collateral posted)
 
(22
)
 
(84
)
Net Cash Used For Investing Activities
 
(295
)
 
(275
)
Cash Flows From Financing Activities:
 
 

 
 

Proceeds from issuance of common stock
 
22

 
221

Proceeds from issuance of long-term debt
 

 
57

Repayment of long-term debt
 
(9
)
 
(66
)
Dividends
 
(66
)
 
(66
)
Short-term borrowings, net
 
184

 
(93
)
Net Cash Provided From Financing Activities
 
131

 
53

Net Decrease In Cash and Cash Equivalents
 
(26
)
 
(29
)
Cash and Cash Equivalents, January 1
 
136

 
72

Cash and Cash Equivalents, March 31
 
$
110

 
$
43

Supplemental Cash Flow Information:
 
 

 
 

Cash paid for– Interest (net of capitalized interest of $3 and $2)
 
$
80

 
$
77

– Income taxes
 
100

 
1

Noncash Investing and Financing Activities:
 
 

 
 

Accrued construction expenditures
 
77

 
88

Capital leases
 
1

 
3

Nuclear fuel purchase
 

 
97

Issuance of common stock for dividend reinvestment plans
 
5

 


 See Notes to Condensed Consolidated Financial Statements.


11

Table of Contents

SCANA CORPORATION
NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
For the Three Months Ended March 31, 2014 and 2013
(Unaudited)
 
The following notes should be read in conjunction with the Notes to Consolidated Financial Statements appearing in SCANA’s Annual Report on Form 10-K for the year ended December 31, 2013. These are interim financial statements and, due to the seasonality of the Company’s business and matters that may occur during the rest of the year, the amounts reported in the Condensed Consolidated Statements of Income are not necessarily indicative of amounts expected for the full year.  In the opinion of management, the information furnished herein reflects all adjustments, all of a normal recurring nature, which are necessary for a fair statement of the results for the interim periods reported.
1.
SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES
 
Use of Estimates
 
The preparation of financial statements in conformity with generally accepted accounting principles requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and liabilities at the date of the financial statements and the reported amount of revenues and expenses during the reporting period. Actual results could differ from those estimates.
 
Plant to be Retired

As previously disclosed, in 2012 SCE&G identified six coal-fired units that it intends to retire by 2018, subject to future developments in environmental regulations, among other matters. These units had an aggregate generating capacity (summer 2012) of 730 MW. Three of these units had been retired by December 31, 2013, and their net carrying value is recorded in regulatory assets (see Note 2). The net carrying value of the remaining units is identified as Plant to be Retired, Net in the condensed consolidated financial statements. SCE&G plans to request recovery of and a return on the net carrying value of these remaining units in future rate proceedings in connection with their retirement, and expects that such deferred amounts will be recovered through rates. In the meantime, these units remain in use and in rate base, and SCE&G depreciates them using composite straight-line rates approved by the SCPSC.

Earnings Per Share
 
The Company computes basic earnings per share by dividing net income by the weighted average number of common shares outstanding for the period.  The Company computes diluted earnings per share using this same formula after giving effect to securities considered to be dilutive potential common stock utilizing the treasury stock method.  The Company has issued no securities that would have an antidilutive effect on earnings per share.
 
Reconciliations of the weighted average number of common shares for basic and diluted earnings per share computation purposes are as follows:     
 
 
 
March 31,
 
Millions
 
 
2014
 
2013
 
Weighted Average Shares Outstanding - Basic
 
 
141.1

 
134.4

 
Effect of dilutive equity forward shares
 
 

 
1.7

 
Weighted Average Shares - Diluted
 
 
141.1

 
136.1

 
 
Asset Management and Supply Service Agreements
 
PSNC Energy utilizes asset management and supply service agreements with counterparties for certain natural gas storage facilities.  Such counterparties held 26% and 48% of PSNC Energy’s natural gas inventory at March 31, 2014
and December 31, 2013, respectively, with a carrying value of $4.2 million and $22.8 million, respectively, through either capacity release or agency relationships.  Under the terms of the asset management agreements, PSNC Energy receives storage asset management fees of which 75% are credited to rate payers. No fees are received under supply service agreements. The agreements expire March 31, 2015. 

12

Table of Contents


2.
RATE AND OTHER REGULATORY MATTERS
 
Rate Matters
 
Electric - Cost of Fuel
 
SCE&G's retail electric rates include a cost of fuel component approved by the SCPSC which may be adjusted periodically to reflect changes in the price of fuel purchased by SCE&G. In connection with its annual review of base rates for fuel costs, and by order dated April 30, 2013, the SCPSC approved a settlement agreement among SCE&G, the ORS and the SCEUC in which SCE&G agreed to reduce its environmental fuel cost component effective with the first billing cycle of May 2013. The order also provided for the accrual of certain debt-related carrying costs on a portion of SCE&G's under-collected balance of fuel costs, and approved SCE&G's total fuel cost component.

By order dated April 29, 2014, the SCPSC approved a settlement agreement among SCE&G, the ORS and SCEUC in which SCE&G agreed to increase its base fuel cost component by approximately $10.3 million for the 12-month period beginning with the first billing cycle of May 2014.  The SCPSC's order also provides for, among other things, the application of approximately $46 million in deferred gains from the settlement of certain interest rate swaps, previously recorded as regulatory liabilities, to reduce the under-collected balance of fuel costs in April 2014 and the accrual of certain debt-related carrying costs on its under-collected balance of fuel costs during the period May 1, 2014 through April 30, 2015. 

The increase to the base fuel cost component is offset by a reduction in SCE&G’s rate rider related to pension costs, which was approved by the SCPSC in March 2014. The reduction was requested by SCE&G as a result of the lower net periodic benefit cost it expects to record during 2014. See also Note 8.

Electric - Base Rates

In October 2013, SCE&G received an accounting order from the SCPSC directing it to remove from rate base deferred income tax assets arising from capital expenditures related to the New Units and to accrue carrying costs (recorded as a regulatory asset) on those amounts during periods in which they are not included in rate base.  Such carrying costs are determined at SCE&G’s weighted average long-term borrowing rate, and during the first quarter of 2014, $1.2 million of such carrying costs were accrued within other income. SCE&G anticipates that when the New Units are placed in service and accelerated tax deprecation is recognized on them, these deferred income tax assets will decline.  When these deferred income tax assets are fully offset by related deferred income tax liabilities, the carrying cost accruals will cease, and the regulatory asset will begin to be amortized.

SCE&G files an IRP with the SCPSC annually which evaluates future electric generation needs based on several factors, including customer energy demands, EPA regulations, reserve margins and fuel costs. SCE&G's 2012 IRP identified six coal-fired units that SCE&G has retired or intends to retire by 2018, subject to future developments in environmental regulations, among other matters. Three of these units had been retired by December 31, 2013. The net carrying value of these retired units is recorded in regulatory assets as unrecovered plant and is being amortized over the units' previously estimated remaining useful lives as approved by the SCPSC. See also Note 1.

SCE&G's DSM Programs for electric customers provide for an annual rider, approved by the SCPSC, to allow recovery of the costs and net lost margin revenue associated with the DSM Programs, along with an incentive for investing in such programs. SCE&G submits annual filings regarding the DSM Programs, net lost margin revenues, program costs, incentives and net program benefits. The SCPSC approved the following rate changes pursuant to annual DSM Programs filings, which went into effect as indicated:

Year
 
Effective
 
Amount
2014
 
First billing cycle of May
 
$15.4 million
2013
 
First billing cycle of May
 
$16.9 million
2012
 
First billing cycle of May
 
$19.6 million


13

Table of Contents

Other activity related to SCE&G’s DSM Programs is as follows:

In May 2013 the SCPSC ordered the deferral as a regulatory asset of one-half of net lost margin revenues and provided for their recovery over a 12-month period beginning with the first billing cycle in May 2014.

In November 2013 the SCPSC approved SCE&G’s continued use of DSM Programs for another six years, including use of the rate rider mechanism and a revised portfolio of DSM Programs.

By order dated April 30, 2014, in response to SCE&G’s annual DSM Programs filing, the SCPSC approved SCE&G’s request to (1) recover one-half of the balance of allowable costs beginning with bills rendered on and after the first billing cycle of May 2014 and to recover the remaining balance of allowable costs beginning with bills rendered on and after the first billing cycle of May 2015, (2) utilize approximately $17.8 million of the gains from the recent settlement of certain interest rate derivative instruments, previously deferred as regulatory liabilities, to offset a portion of the net lost margin revenues component of SCE&G’s DSM Programs rider, and (3) apply $5.0 million of its storm damage reserve and a portion of the gains from the recent settlement of certain interest rate derivative instruments, currently estimated to be $5.5 million, to the remaining balance of deferred net lost margin revenue as of April 30, 2014, deferred within regulatory assets resulting from the May 2013 order previously described. In addition, the SCPSC, upon recommendation of the ORS, reduced by 25%, or $6.6 million , the amount of net lost margin revenues SCE&G expects to experience over the 12 month period beginning with the first billing cycle of May 2014, and ordered that the $6.6 million be applied to decrease the amount of program costs deferred for recovery.  Actual net lost margin revenues not collected in the current DSM Programs rate rider is subject to true up in the following program year.

Electric – BLRA
    
Under the BLRA, SCE&G is allowed to file revised rates with the SCPSC each year to incorporate the financing cost of any incremental construction work in progress incurred for new nuclear generation. Requested rate adjustments are based on SCE&G’s updated cost of debt and capital structure and on an allowed return on common equity of 11.0%. The SCPSC has approved the following rate changes under the BLRA effective for bills rendered on and after October 30 in the years indicated:
Year
 
Action
 
Amount
2013
 
2.9
%
Increase
 
$67.2 million
2012
 
2.3
%
Increase
 
$52.1 million

Gas
 
SCE&G
 
The RSA is designed to reduce the volatility of costs charged to customers by allowing for timely recovery of the costs that regulated utilities incur related to natural gas infrastructure. The SCPSC has approved the following rate changes pursuant to annual RSA filings effective with the first billing cycle of November in the years indicated:
Year
 
Action
 
Amount
2013
 
  No change
 
-
2012
 
2.1
%
Increase
 
$7.5 million

SCE&G's natural gas tariffs include a PGA clause that provides for the recovery of actual gas costs incurred. SCE&G's gas rates are calculated using a methodology which may adjust the cost of gas monthly based on a 12-month rolling average, and its gas purchasing policies and practices are reviewed annually by the SCPSC. The annual review conducted for the 12-month period ended July 31, 2013 resulted in the SCPSC issuing an order finding that SCE&G's gas purchasing policies and practices during the review period were reasonable and prudent.

PSNC Energy
 
PSNC Energy is subject to a Rider D rate mechanism which allows it to recover from customers all prudently incurred gas costs and certain uncollectible expenses related to gas cost.  The Rider D rate mechanism also allows PSNC Energy to recover, in any manner authorized by the NCUC, losses on negotiated gas and transportation sales.
 

14

Table of Contents

PSNC Energy’s rates are established using a benchmark cost of gas approved by the NCUC, which may be periodically adjusted to reflect changes in the market price of natural gas. PSNC Energy revises its tariffs with the NCUC as necessary to track these changes and accounts for any over- or under-collection of the delivered cost of gas in its deferred accounts for subsequent rate consideration. The NCUC reviews PSNC Energy’s gas purchasing practices annually. In addition, PSNC Energy utilizes a CUT which allows it to adjust its base rates semi-annually for residential and commercial customers based on average per customer consumption.

In October 2013, in connection with PSNC Energy's 2013 Annual Prudence Review, the NCUC issued an order finding that PSNC Energy's gas costs, including all hedging transactions, were reasonable and prudently incurred during the 12 months ended March 31, 2013.

During the third quarter of 2013, the State of North Carolina passed legislation that changed statutes covering gross receipts, sales and use, excise, franchise and income taxes.  In the fourth quarter, in response to this legislation, the NCUC initiated a proceeding to investigate how it should proceed in response to the enactment of such legislation.  Because the investigation was not completed before January 1, 2014, the NCUC issued an order notifying utilities that the incremental revenue requirement impact associated with the change in the level of state income tax expense included in each utility’s cost of service would be deemed to be collected on a provisional basis (subject to refund) beginning January 1, 2014. As of March 31, 2014, revenues subject to refund were not significant.  PSNC Energy cannot predict when the NCUC’s investigation will be complete, but does not expect the resolution of this matter to have a material impact on its financial condition, results of operations or cash flows. 

Regulatory Assets and Regulatory Liabilities
 
The Company’s cost-based, rate-regulated utilities recognize in their financial statements certain revenues and expenses in different time periods than do enterprises that are not rate-regulated.  As a result, the Company has recorded regulatory assets and regulatory liabilities which are summarized in the following tables. Other than unrecovered plant, substantially all regulatory assets are either explicitly excluded from rate base or are effectively excluded from rate base due to their being offset by related liabilities.
Millions of dollars
 
March 31,
2014
 
December 31,
2013
Regulatory Assets:
 
 

 
 

Accumulated deferred income taxes
 
$
258

 
$
259

Under-collections - electric fuel adjustment clause
 
36

 
18

Environmental remediation costs
 
41

 
41

AROs and related funding
 
373

 
368

Franchise agreements
 
30

 
31

Deferred employee benefit plan costs
 
235

 
238

Deferred losses on interest rate derivatives
 
210

 
124

Deferred pollution control costs
 
37

 
37

Unrecovered plant
 
143

 
145

DSM Programs
 
56

 
51

Other
 
48

 
48

Total Regulatory Assets
 
$
1,467

 
$
1,360

Regulatory Liabilities:
 
 

 
 

Accumulated deferred income taxes
 
$
23

 
$
24

Asset removal costs
 
705

 
695

Storm damage reserve
 
14

 
27

Monetization of bankruptcy claim
 
28

 
29

Deferred gains on interest rate derivatives
 
106

 
181

Planned major maintenance
 
5

 
10

Other
 
1

 

Total Regulatory Liabilities
 
$
882

 
$
966



15

Table of Contents

Accumulated deferred income tax liabilities that arose from utility operations that have not been included in customer rates are recorded as a regulatory asset.  Substantially all of these regulatory assets relate to depreciation and are expected to be recovered over the remaining lives of the related property which may range up to approximately 70 years.  Similarly, accumulated deferred income tax assets arising from deferred investment tax credits are recorded as a regulatory liability.
 
Under-collections - electric fuel adjustment clause represent amounts due from customers pursuant to the fuel adjustment clause as approved by the SCPSC during annual hearings which are not expected to be recovered in retail electric rates within 12 months. 

Environmental remediation costs represent costs associated with the assessment and clean-up of sites currently or formerly owned by the Company, and are expected to be recovered over periods of up to approximately 26 years.
 
ARO and related funding represents the regulatory asset associated with the legal obligation to decommission and dismantle Summer Station and conditional AROs related to generation, transmission and distribution properties, including gas pipelines. These regulatory assets are expected to be recovered over the related property lives and periods of decommissioning which may range up to approximately 90 years.
 
Franchise agreements represent costs associated with electric and gas franchise agreements with the cities of Charleston and Columbia, South Carolina.  Based on an SCPSC order, SCE&G is recovering these amounts through cost of service rates through 2021.

Employee benefit plan costs of the regulated utilities have historically been recovered as they have been recorded under generally accepted accounting principles. Deferred employee benefit plan costs represent amounts of pension and other postretirement benefit costs which were accrued as liabilities and treated as regulatory assets pursuant to FERC guidance, as well as costs deferred pursuant to specific SCPSC regulatory orders. In connection with a December 2012 rate order, approximately $63 million of deferred pension costs for electric operations are to be recovered through utility rates over approximately 30 years. In connection with the October 2013 RSA order, approximately $14 million of deferred pension costs for gas operations are to be recovered through utility rates over approximately 14 years. The remainder of the deferred benefit costs are expected to be recovered through utility rates, primarily over average service periods of participating employees, or up to approximately 12 years.
 
Planned major maintenance related to certain fossil fueled turbine/generation equipment and nuclear refueling outages is accrued in periods other than when incurred, as approved pursuant to specific SCPSC orders.  SCE&G collects and accrues $18.4 million annually for fossil fueled turbine/generation equipment maintenance, and collects and accrues $16.8 million annually for nuclear-related refueling charges.
 
Deferred losses or gains on interest rate derivatives represent (i) the effective portions of changes in fair value and payments made or received upon settlement of certain interest rate derivatives designated as cash flow hedges and (ii) the changes in fair value and payments received upon settlement of certain other interest rate derivatives not so designated. The amounts recorded with respect to (i) are expected to be amortized to interest expense over the lives of the underlying debt, up to approximately 30 years. The amounts recorded with respect to (ii) are expected to be similarly amortized to interest expense except when, in the case of deferred gains, such amounts are applied otherwise at the direction of the SCPSC. Also, as discussed at Rate Matters - Electric - Base Rates, certain of these deferred amounts will be applied to offset unrecorded net lost margin revenues related to DSM Programs.
 
Deferred pollution control costs represent deferred depreciation and operating and maintenance costs associated with the scrubbers installed at certain coal-fired generating plants pursuant to specific regulatory orders.  Such costs are being recovered through utility rates through 2045.
 
Unrecovered plant represents the carrying value of coal-fired generating units, including related materials and supplies inventory, retired from service prior to being fully depreciated. Pursuant to SCPSC approval, SCE&G is amortizing these amounts through cost of service rates over the units' previous estimated remaining useful lives through 2025. Unamortized amounts are included in rate base and are earning a current return.

DSM Programs represents deferred costs and certain unrecovered net lost margin revenues associated with such programs at SCE&G.  Deferred costs are currently being recovered over five years through a SCPSC approved rider.  Unrecovered net lost margin revenues are to be recovered over periods not to exceed 24 months from date of deferral.  See Rate Matters - Electric - Base Rates above for details regarding a 2014 filing with the SCPSC regarding recovery of these deferred costs and unrecovered net lost margin revenues.

16

Table of Contents


Various other regulatory assets are expected to be recovered in rates over periods of up to approximately 30 years.
 
Asset removal costs represent estimated net collections through depreciation rates of amounts to be incurred for the removal of assets in the future.
 
The storm damage reserve represents an SCPSC-approved collection through SCE&G electric rates, capped at $100 million , which can be applied to offset incremental storm damage costs in excess of $2.5 million in a calendar year. Pursuant to specific regulatory orders, SCE&G has suspended storm damage reserve collection through rates indefinitely. During the first quarter of 2014, $13.6 million of the reserve was applied to offset incremental storm damage costs. Also, as discussed at Rate Matters - Electric - Base Rates, in April 2014 $5.0 million of the reserve will be applied to offset unrecovered net lost margin revenues related to DSM Programs.

The monetization of bankruptcy claim represents proceeds from the sale of a bankruptcy claim which are being amortized into operating revenue through February 2024.
 
The SCPSC, the NCUC or the FERC has reviewed and approved through specific orders most of the items shown as regulatory assets. Other regulatory assets include, but are not limited to, certain costs which have not been approved for recovery by the SCPSC, the NCUC or by the FERC. In recording such costs as regulatory assets, management believes the costs will be allowable under existing rate-making concepts that are embodied in rate orders received by the Company. The costs are currently not being recovered, but are expected to be recovered through rates in future periods. In the future, as a result of deregulation or other changes in the regulatory environment or changes in accounting requirements, the Company could be required to write off its regulatory assets and liabilities. Such an event could have a material effect on the Company's results of operations, liquidity or financial position in the period the write-off would be recorded.

3.COMMON EQUITY
 
Changes in common equity during the three months ended March 31, 2014 and 2013 were as follows:
 
 
 
 
 
 
Accumulated Other Comprehensive Income (Loss)
 
 
Millions
 
Common Stock
 
Retained Earnings
 
Gains (Losses) on Cash Flow Hedges
 
Deferred Employee Benefit Plans
 
Total AOCI
 
Total Common Equity
Balance as of January 1, 2014
 
$
2,280

 
$
2,444

 
$
(52
)
 
$
(8
)
 
$
(60
)
 
$
4,664

Net Income
 
 
 
193

 
 
 
 
 
 
 
193

Other Comprehensive Loss
 
 
 
 
 
(1
)
 

 
(1
)
 
(1
)
Total Comprehensive Income (Loss)
 
 
 
193

 
(1
)
 

 
(1
)
 
192

Issuance of Common Stock
 
27

 
 
 
 
 
 
 
 
 
27

Dividends Declared
 
 
 
(74
)
 
 
 
 
 
 
 
(74
)
Balance as of March 31, 2014
 
$
2,307

 
$
2,563

 
$
(53
)
 
$
(8
)
 
$
(61
)
 
$
4,809

 
 
 
 
 
 
 
 
 
 
 
 
 
Balance as of January 1, 2013
 
$
1,983

 
$
2,257

 
$
(70
)
 
$
(16
)
 
$
(86
)
 
$
4,154

Net Income
 
 
 
151

 
 
 
 
 
 
 
151

Other Comprehensive Loss
 
 
 
 
 
7

 

 
7

 
7

Total Comprehensive Income
 
 
 
151

 
7

 

 
7

 
158

Issuance of Common Stock
 
221

 
 
 
 
 
 
 
 
 
221

Dividends Declared
 
 
 
(70
)
 
 
 
 
 
 
 
(70
)
Balance as of March 31, 2013
 
$
2,204

 
$
2,338

 
$
(63
)
 
$
(16
)
 
$
(79
)
 
$
4,463

 
SCANA had 200 million shares of common stock authorized as of March 31, 2014 and December 31, 2013, of which 141.3 million and 140.7 million were issued and outstanding at March 31, 2014 and December 31, 2013, respectively.
 

17


On March 5, 2013, SCANA settled all forward sales contracts related to its common stock through the issuance of approximately 6.6 million common shares, resulting in net proceeds of approximately $196.2 million.

For information related to the reclassifications from AOCI, see Note 6.

4.
LONG-TERM DEBT AND LIQUIDITY
 
Long-term Debt

In March 2013, SCE&G entered into a contract for the purchase of nuclear fuel totaling $100 million and payable in 2016.
    
In January 2013, JEDA issued at a premium, for the benefit of SCE&G,$39.5 million of 4.00% tax-exempt industrial revenue bonds due February 1, 2028, and $14.7 million of3.63% tax-exempt industrial revenue bonds due February 1, 2033. Proceeds from these sales were loaned by JEDA to SCE&G and, together with other available funds, were used to redeem prior to maturity $56.9 million of 5.2%industrial revenue bonds due November 1, 2027.

Substantially all of SCE&G’s and GENCO’s electric utility plant is pledged as collateral in connection with long-term debt.
 
Liquidity
 
SCANA, SCE&G (including Fuel Company) and PSNC Energy had available the following committed LOC, and had outstanding the following LOC advances, commercial paper, and LOC-supported letter of credit obligations: 
 
 
SCANA
 
SCE&G
 
PSNC Energy
Millions of dollars
 
March 31,
2014
 
December 31,
2013
 
March 31,
2014
 
December 31,
2013
 
March 31,
2014
 
December 31,
2013
Lines of credit:
 
 

 
 
 
 
 
 
 
 
 
 
Total committed long-term
 
$
300

 
$
300

 
$
1,400

 
$
1,400

 
$
100

 
$
100

Outstanding commercial paper
(270 or fewer days)
 
$
103

 
$
125

 
$
457

 
$
251

 

 

Weighted average interest rate
 
0.37
%
 
0.39
%
 
0.26
%
 
0.27
%
 

 

Letters of credit supported by LOC
 
$
3

 
$
3

 
$
0.3

 
$
0.3

 

 

Available
 
$
194

 
$
172

 
$
943

 
$
1,149

 
$
100

 
$
100

   
SCANA, SCE&G (including Fuel Company) and PSNC Energy are parties to five-year credit agreements in the amounts of $300 million, $1.2 billion (of which $500 million relates to Fuel Company) and $100 million respectively. In addition, SCE&G is a party to a three-year credit agreement in the amount of $200 million. The five-year agreements expire in October 2018, and the three-year agreement expires in October 2016. These credit agreements are used for general corporate purposes, including liquidity support for each company's commercial paper program and working capital needs and, in the case of Fuel Company, to finance or refinance the purchase of nuclear fuel, certain fossil fuels, and emission and other environmental allowances.  These committed long-term facilities are revolving lines of credit under credit agreements with a syndicate of banks. Wells Fargo Bank, National Association, Bank of America, N.A. and Morgan Stanley Bank, N.A. each provide 10.7% of the aggregate $1.8 billion credit facilities, JPMorgan Chase Bank, N.A., Mizuho Corporate Bank, Ltd., TD Bank N.A., Credit Suisse AG, Cayman Island Branch and UBS Loan Finance LLC each provide 8.9%, and Branch Banking and Trust Company, Union Bank, N.A. and U.S. Bank National Association each provide 6.3%Two other banks provide the remaining support. The Company pays fees to the banks as compensation for maintaining the committed lines of credit. Such fees were not material in any period presented.
The Company is obligated with respect to an aggregate of $67.8 million of industrial revenue bonds which are secured by letters of credit issued by Branch Banking and Trust Company.  The letters of credit expire, subject to renewal, in the fourth quarter of 2014.

5.INCOME TAXES
 
During 2013, the Company amended certain of its tax returns to claim certain tax-defined research and development deductions and credits. In connection with these filings, the Company recorded an unrecognized tax benefit of $3.0 million. If

18

Table of Contents

recognized, this tax benefit would affect the Company’s effective tax rate. No other material changes in the status of the Company’s tax positions have occurred through March 31, 2014.

                The Company recognizes interest accrued related to unrecognized tax benefits within interest expense and recognizes tax penalties within other expenses.  The Company has not recorded interest expense or penalties associated with the 2013 uncertain tax position.

During the third quarter of 2013, the State of North Carolina passed legislation that lowered the state corporate income tax rate from 6.9% to 6.0% in 2014 and 5.0% in 2015.  In connection with this change in tax rates, related state deferred tax amounts were remeasured, with the change in their balances being credited to a regulatory liability. The change in income tax rates did not and is not expected to have a material impact on the Company’s financial position, results of operations or cash flows. 

Additionally, during the third quarter of 2013, the IRS issued final regulations regarding the capitalization of certain costs for income tax purposes and re-proposed certain other related regulations (collectively referred to as tangible personal property regulations).  Related IRS revenue procedures were then issued on January 24, 2014. These regulations did not and are not expected to have a material impact on the Company's financial position, results of operations or cash flows.

6.DERIVATIVE FINANCIAL INSTRUMENTS
 
The Company recognizes all derivative instruments as either assets or liabilities in the statement of financial position and measures those instruments at fair value.  The Company recognizes changes in the fair value of derivative instruments either in earnings, as a component of other comprehensive income (loss) or, for regulated subsidiaries, within regulatory assets
or regulatory liabilities, depending upon the intended use of the derivative and the resulting designation. 

Policies and procedures and risk limits are established to control the level of market, credit, liquidity and operational and administrative risks assumed by the Company.  SCANA’s Board of Directors has delegated to a Risk Management Committee the authority to set risk limits, establish policies and procedures for risk management and measurement, and oversee and review the risk management process and infrastructure for SCANA and each of its subsidiaries.  The Risk Management Committee, which is comprised of certain officers, including the Company’s Risk Management Officer and senior officers, apprises the Audit Committee of the Board of Directors with regard to the management of risk and brings to the Audit Committee's attention significant areas of concern. Written policies define the physical and financial transactions that are approved, as well as the authorization requirements and limits for transactions.
 
Commodity Derivatives
 
The Company uses derivative instruments to hedge forward purchases and sales of natural gas, which create market risks of different types.  Instruments designated as cash flow hedges are used to hedge risks associated with fixed price obligations in a volatile market and risks associated with price differentials at different delivery locations. Instruments designated as fair value hedges are used to mitigate exposure to fluctuating market prices created by fixed prices of stored natural gas.  The basic types of financial instruments utilized are exchange-traded instruments, such as NYMEX futures contracts or options, and over-the-counter instruments such as options and swaps, which are typically offered by energy companies and financial institutions.  Cash settlements of commodity derivatives are classified as operating activities in the condensed consolidated statements of cash flows.
 
PSNC Energy hedges natural gas purchasing activities using over-the-counter options and NYMEX futures and options.  PSNC Energy’s tariffs include a provision for the recovery of actual gas costs incurred, including any costs of hedging.  PSNC Energy records premiums, transaction fees, margin requirements and any realized gains or losses from its hedging program in deferred accounts as a regulatory asset or liability for the under- or over-recovery of gas costs.  These derivative financial instruments are not designated as hedges for accounting purposes.
 
Unrealized gains and losses on qualifying cash flow hedges of nonregulated operations are deferred in AOCI.  When the hedged transactions affect earnings, previously recorded gains and losses are reclassified from AOCI to cost of gas.  The effects of gains or losses resulting from these hedging activities are either offset by the recording of the related hedged transactions or are included in gas sales pricing decisions made by the business unit.
 
As an accommodation to certain customers, SEMI, as part of its energy management services, offers fixed price supply contracts which are accounted for as derivatives.  These sales contracts are offset by the purchase of supply futures and swaps

19

Table of Contents

which are also accounted for as derivatives. Neither the sales contracts nor the related supply futures and swaps are designated as hedges for accounting purposes.

Interest Rate Swaps

The Company may use interest rate swaps to manage interest rate risk and exposure to changes in fair value attributable to changes in interest rates on certain debt issuances.  In cases in which the Company synthetically converts variable rate debt to fixed rate debt using swaps that are designated as cash flow hedges, periodic payments to or receipts from swap counterparties related to these derivatives are recorded within interest expense.

In anticipation of the issuance of debt, the Company may use treasury rate lock or forward starting swap agreements that are designated as cash flow hedges.  Except as described in the following paragraph, the effective portions of changes in fair value and payments made or received upon termination of such agreements for regulated subsidiaries are recorded in regulatory assets or regulatory liabilities. For the holding company or nonregulated subsidiaries, such amounts are recorded in AOCI.  Such amounts are amortized to interest expense over the term of the underlying debt. Ineffective portions of fair value changes are recognized in income.

Pursuant to regulatory orders issued, interest rate derivatives entered into by SCE&G after October 2013 are no longer designated as cash flow hedges, and fair value changes and settlement amounts are recorded as regulatory assets and liabilities. Upon settlement, losses on swaps will be amortized over the lives of related debt issuances, and gains may be applied to under-collected fuel, be amortized to interest expense or applied as otherwise directed by the SCPSC.

Cash payments made or received upon termination of these financial instruments are classified as investing activities for cash flow statement purposes.
 
Quantitative Disclosures Related to Derivatives
 
The Company was party to natural gas derivative contracts outstanding in the following quantities:
 
 
Commodity and Other Energy Management Contracts (in MMBTU)
Hedge designation
 
Gas Distribution
 
Retail Gas
Marketing
 
Energy Marketing
 
Total
As of March 31, 2014
 
 

 
 

 
 

 
 

Commodity
 
4,780,000

 
4,325,000

 
1,903,000

 
11,008,000

Energy Management (a)
 

 

 
26,073,219

 
26,073,219

Total (a)
 
4,780,000

 
4,325,000

 
27,976,219

 
37,081,219

 
 
 
 
 
 
 
 
 
As of December 31, 2013
 
 

 
 

 
 

 
 

Commodity
 
6,070,000

 
6,726,000

 
2,560,000

 
15,356,000

Energy Management (b)
 

 

 
27,359,958

 
27,359,958

Total (b)
 
6,070,000

 
6,726,000

 
29,919,958

 
42,715,958

 
(a)  Includes an aggregate 258,615 MMBTU related to basis swap contracts in Energy Marketing.
(b)  Includes an aggregate 348,453 MMBTU related to basis swap contracts in Energy Marketing.
 
The Company was party to interest rate swaps designated as cash flow hedges with aggregate notional amounts of $128.8 million at March 31, 2014 and $128.8 million at December 31, 2013. The Company was party to interest rate swaps not designated as cash flow hedges with an aggregate notional amount of $1.3 billion at March 31, 2014 and $1.3 billion at December 31, 2013.
 

20

Table of Contents

The fair value of energy-related derivatives and interest rate derivatives was reflected in the condensed consolidated balance sheet as follows:
 
 
Fair Values of Derivative Instruments
 
 
Asset Derivatives
 
Liability Derivatives
 
 
Balance Sheet
 
Fair
 
Balance Sheet
 
Fair
Millions of dollars
 
Location
 
Value
 
Location
 
Value
As of March 31, 2014
 
 
 
 

 
 
 
 

Derivatives designated as hedging instruments
 
 
 
 

 
 
 
 

Interest rate
 
 
 


 
Derivative financial instruments
 
$
4

 
 
 
 


 
Other deferred credits and other liabilities
 
19

Commodity
 
Prepayments and other
 
$
2

 
 
 


Total
 
 
 
$
2

 
 
 
$
23

 
 
 
 
 
 
 
 
 
Derivatives not designated as hedging instruments
 
 
 
 

 
 
 
 

Interest rate
 
Other deferred debits and other assets
 
$
2

 
Derivative financial instruments
 
$
40

 
 
 
 


 
Other deferred credits and other liabilities
 
43

Commodity
 
Prepayments and other
 
3

 
 
 
 
Energy Management
 
Prepayments and other
 
3

 
Derivative financial instruments
 
3

 
 
Other deferred debits and other assets
 
4

 
Other deferred credits and other liabilities
 
4

Total
 
 
 
$
12

 
 
 
$
90


As of December 31, 2013
 
 
 
 

 
 
 
 

Derivatives designated as hedging instruments
 
 
 
 

 
 
 
 

Interest rate
 
 
 


 
Derivative financial instruments
 
$
5

 
 
 
 


 
Other deferred credits and other liabilities
 
14

Commodity
 
Prepayments and other
 
$
2

 
 
 


Total
 
 
 
$
2

 
 
 
$
19

 
 
 
 
 
 
 
 
 
Derivatives not designated as hedging instruments
 
 
 
 

 
 
 
 

Interest rate
 
Prepayments and other
 
$
13

 
Derivative financial instruments
 
$
1

 
 
Other deferred debits and other assets
 
19

 
 
 
 
Commodity
 
Prepayments and other
 
2

 
 
 
 
Energy management
 
Prepayments and other
 
4

 
Derivative financial instruments
 
4

 
 
Other deferred debits and other assets
 
4

 
Other deferred credits and other liabilities
 
4

Total
 
 
 
$
42

 
 
 
$
9


 The effect of derivative instruments on the condensed consolidated statements of income is as follows: 

Fair Value Hedges

The Company had no interest rate or commodity derivatives designated as fair value hedges for any period presented.


21

Table of Contents

Cash Flow Hedges

Derivatives in Cash Flow Hedging Relationships
 
 
Gain (Loss) Deferred in Regulatory Accounts
 
 
 
Loss Reclassified from Deferred Accounts into Income
 
 
 
 
 
Millions of dollars
 
(Effective Portion)
 
 
 
(Effective Portion)
 
 
2014

 
2013

 
Location
 
2014

 
2013

Three Months Ended March 31,
 
 
 
 
 
 
 
 
 
 
Interest rate
 
$
(3
)
 
$
35

 
Interest expense
 
$
(1
)
 
$
(1
)
 
 
 
Gain (Loss) Recognized in OCI, net of tax
 
 
 
Gain (Loss) Reclassified from AOCI into Income, net of tax
 
 
 
 
 
Millions of dollars
 
(Effective Portion)
 
 
 
(Effective Portion)
 
 
2014

 
2013

 
Location
 
2014

 
2013

Three Months Ended March 31,
 
 
 
 
 
 
 
 
 
 
Interest rate
 
$
(2
)
 
$
1

 
Interest expense
 
$
(2
)
 
$
(2
)
Commodity
 
3

 
2

 
Gas purchased for resale
 
4

 
(2
)
Total
 
$
1

 
$
3

 
 
 
$
2

 
$
(4
)

As of March 31, 2014, the Company expects that during the next 12 months reclassifications from AOCI to earnings arising from cash flow hedges will include approximately $1.0 million as a decrease to gas cost and approximately $6.2 million as an increase to interest expense, assuming natural gas and financial markets remain at their current levels.  As of March 31, 2014, all of the Company’s commodity cash flow hedges settle by their terms before the end of 2016.

Hedge Ineffectiveness
 
Other losses recognized in income representing ineffectiveness on interest rate hedges designated as cash flow hedges were insignificant in each of the three months ended March 31, 2014 and 2013, respectively.

Derivatives not designated as Hedging Instruments
 
 
 
 
Millions of dollars
 
Loss Deferred in Regulatory Accounts
 
Gain Reclassified from Deferred Accounts into Income
Three Months Ended March 31, 2014
 
 
 
Location
 
Amount
Interest rate contracts
 
$
(112
)
 
Other Income
 
$

 
No losses were deferred in regulatory accounts, and no amounts were reclassified from deferred accounts into income, for the three months ended March 31, 2013. As of March 31, 2014, the Company expects that during the next 12 months reclassifications from other current liabilities and deferred regulatory accounts to earnings arising from derivatives not designated as hedges will include $67.8 million as an increase to other income. The effect of this increase on net income will be entirely offset by the recovery of certain undercollected fuel costs and net lost margin revenues from DSM Programs as further described in Note 2.

Credit Risk Considerations
 
The Company limits credit risk in its commodity and interest rate derivatives activities by assessing the creditworthiness of potential counterparties before entering into transactions with them and continuing to evaluate their creditworthiness on an ongoing basis. In this regard, the Company uses credit ratings provided by credit rating agencies and current market-based qualitative and quantitative data, as well as financial statements, to assess the financial health of counterparties on an ongoing basis. The Company uses standardized master agreements which may include collateral requirements. These master agreements permit the netting of cash flows associated with a single counterparty. Cash, letters of credit and parental/affiliate guarantees may be obtained as security from counterparties in order to mitigate credit risk. The collateral agreements permit the secured party to demand the posting of cash or letters of credit in the event an exposure

22

Table of Contents

exceeds the established threshold. The threshold represents an unsecured credit limit which may be supported by a parental/affiliate guaranty, as determined in accordance with the Company's credit policies and due diligence. In addition, collateral agreements allow for the termination and liquidation of all positions in the event of a failure or inability to post collateral.
 
Certain of the Company’s derivative instruments contain contingent provisions that may require the Company to provide collateral upon the occurrence of specific events, primarily credit downgrades.  As of March 31, 2014 and December 31, 2013, the Company has posted $30.9 million and $26.8 million, respectively, of collateral related to derivatives with contingent provisions that were in a net liability position.  Collateral related to the positions expected to close in the next 12 months is recorded in Prepayments and other on the condensed consolidated balance sheets. Collateral related to noncurrent positions is recorded in Other within Deferred Debits and Other Assets on the condensed consolidated balance sheets. If all of the contingent features underlying these instruments had been fully triggered as of March 31, 2014 and December 31, 2013, the Company could have been required to post an additional $78.1 million and $0.0 million, respectively, of collateral with its counterparties.  The aggregate fair value of all derivative instruments with contingent provisions that are in a net liability position as of March 31, 2014 and December 31, 2013 is $109.0 million and $25.2 million, respectively.

In addition, as of March 31, 2014 and December 31, 2013, the Company has collected no cash collateral related to interest rate derivatives with contingent provisions that are in a net asset position. If all the contingent features underlying these instruments were fully triggered as of March 31, 2014 and December 31, 2013, the Company could request $2.0 million and $34.1 million, respectively, of cash collateral from its counterparties. The aggregate fair value of all derivative instruments with contingent provisions that are in a net asset position as of March 31, 2014 and December 31, 2013 is $2.0 million and $34.1 million, respectively. In addition, at March 31, 2014, the Company could have called on letters of credit in the amount of $5.0 million related to $7.0 million in commodity derivatives that are in a net asset position, compared to letters of credit of $6.0 million related to derivatives of $6.0 million at December 31, 2013, if all the contingent features underlying these instruments had been fully triggered.

Information related to the Company's offsetting of derivative assets follows:
 
 
 
 
 
 
 
Gross Amounts Not Offset in the Statement of Financial Position
 
 
Millions of dollars
Gross Amounts of Recognized Assets
 
Gross Amounts Offset in the Statement of Financial Position
 
Net Amounts Presented in the Statement of Financial Position
 
Financial Instruments
 
Cash Collateral Received
 
Net Amount
As of March 31, 2014
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
2

 

 
$
2

 
$
(2
)
 

 

Commodity
5

 

 
5

 

 

 
$
5

Energy Management
7

 

 
7

 

 

 
7

   Total
$
14

 

 
$
14

 
$
(2
)
 

 
$
12

 
 
 
 
 
 
 
 
 
 
 
 
Balance sheet location
Prepayments and other
 
$
8

 
 
 
 
 
 
 
Other deferred debits and other assets
 
6

 
 
 
 
 
 
 
Total
 
 
 
$
14

 
 
 
 
 
 
As of December 31, 2013
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
32

 

 
$
32

 
$
(1
)
 

 
$
31

Commodity
4

 

 
4

 

 

 
4

Energy Management
8

 

 
8

 

 

 
8

   Total
$
44

 

 
$
44

 
$
(1
)
 

 
$
43

 
 
 
 
 
 
 
 
 
 
 
 
Balance sheet location
Prepayments and other
 
$
21

 
 
 
 
 
 
 
Other deferred debits and other assets
 
23

 
 
 
 
 
 
 
Total
 
 
 
$
44

 
 
 
 
 
 
 

23

Table of Contents

Information related to the Company's offsetting of derivative liabilities follows:
 
 
 
 
 
 
 
Gross Amounts Not Offset in the Statement of Financial Position
 
 
Millions of dollars
Gross Amounts of Recognized Liabilities
 
Gross Amounts Offset in the Statement of Financial Position
 
Net Amounts Presented in the Statement of Financial Position
 
Financial Instruments
 
Cash Collateral Posted
 
Net Amount
As of March 31, 2014
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
106

 

 
$
106

 
$
(2
)
 
$
(26
)
 
$
78

Energy Management
7

 

 
7

 

 
(5
)
 
2

 
$
113

 

 
$
113

 
$
(2
)
 
$
(31
)
 
$
80

 
 
 
 
 
 
 
 
 
 
 
 
Balance sheet location
Derivative financial instruments
 
$
47

 
 
 
 
 
 
 
Other deferred credits and other liabilities
 
66

 
 
 
 
 
 
 
Total
 
 
 
$
113

 
 
 
 
 
 
As of December 31, 2013
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
20

 

 
$
20

 
$
(1
)
 
$
(19
)
 

Energy Management
8

 

 
8

 

 
(6
)
 
$
2

 
$
28

 

 
$
28

 
$
(1
)
 
$
(25
)
 
$
2

 
 
 
 
 
 
 
 
 
 
 
 
Balance sheet location
Derivative financial instruments
 
$
10

 
 
 
 
 
 
 
Other deferred credits and other liabilities
 
18

 
 
 
 
 
 
 
Total
 
 
 
$
28

 
 
 
 
 
 

7.
FAIR VALUE MEASUREMENTS, INCLUDING DERIVATIVES
 
The Company values available for sale securities using quoted prices from a national stock exchange, such as the NASDAQ, where the securities are actively traded.  For commodity derivative and energy management assets and liabilities, the Company uses unadjusted NYMEX prices to determine fair value, and considers such measures of fair value to be Level 1 for exchange traded instruments and Level 2 for over-the-counter instruments.  The Company’s interest rate swap agreements are valued using discounted cash flow models with independently sourced data.  Fair value measurements, and the level within the fair value hierarchy in which the measurements fall, were as follows:
 
 
As of March 31, 2014
 
As of December 31, 2013
Millions of dollars
 
Level 1
 
Level 2
 
Level 1
 
Level 2
Assets:
 
 
 
 
 
 
 
 
Available for sale securities
 
$
11

 

 
$
9

 

Interest rate contracts
 

 
$
2

 

 
$
32

Commodity contracts
 
3

 
2

 
2

 
2

Energy management contracts
 
1

 
6

 
1

 
7

Liabilities:
 
 
 
 
 
 
 
 
Interest rate contracts
 

 
106

 

 
20

Commodity contracts
 

 

 

 

Energy management contracts
 

 
10

 

 
12

 
There were no Level 3 fair value measurements for either period presented, and there were no transfers of fair value amounts into or out of Levels 1, 2 or 3 during the periods presented.
 

24

Table of Contents

Financial instruments for which the carrying amount may not equal estimated fair value at March 31, 2014 and December 31, 2013 were as follows:
 
 
March 31, 2014
 
December 31, 2013
Millions of dollars
 
Carrying
Amount
 
Estimated
Fair Value
 
Carrying
Amount
 
Estimated
Fair Value
Long-term debt
 
$
5,441.5

 
$
6,096.8

 
$
5,449.3

 
$
5,916.3


Fair values of long-term debt instruments are based on net present value calculations using independently sourced market data that incorporate a developed discount rate using similarly rated long-term debt, along with benchmark interest rates.  As such, the aggregate fair values presented above are considered to be Level 2. Early settlement of long-term debt may not be possible or may not be considered prudent.

Carrying values of short-term borrowings approximate fair value, and are based on quoted prices from dealers in the commercial paper market. The resulting fair value is considered to be Level 2.

8.
EMPLOYEE BENEFIT PLANS
 
Pension and Other Postretirement Benefit Plans
 
Components of net periodic benefit cost recorded by the Company were as follows: 
 
 
Pension Benefits
 
Other Postretirement Benefits
Millions of dollars
 
2014
 
2013
 
2014
 
2013
Three months ended March 31,
 
 

 
 

 
 

 
 

Service cost
 
$
5.0

 
$
5.9

 
$
1.2

 
$
1.6

Interest cost
 
10.2

 
9.5

 
3.1

 
2.8

Expected return on assets
 
(16.8
)
 
(15.4
)
 

 

Prior service cost amortization
 
1.0

 
1.7

 
0.1

 
0.2

Transition obligation amortization
 

 

 

 
0.2

Amortization of actuarial losses
 
1.3

 
5.4

 
0.1

 
0.8

Net periodic benefit cost
 
$
0.7

 
$
7.1

 
$
4.5

 
$
5.6


No significant contribution to the pension trust is expected for the foreseeable future, nor is a limitation on benefit payments expected to apply. SCE&G recovers current pension costs through either a rate rider that may be adjusted annually for retail electric operations or through cost of service rates for gas operations. Certain pension costs arising prior to 2013 were deferred for future recovery under regulatory orders as discussed in Note 2.

9.
COMMITMENTS AND CONTINGENCIES

Nuclear Insurance

Under Price-Anderson, SCE&G (for itself and on behalf of Santee Cooper, a one-third owner of Summer Station Unit 1) maintains agreements of indemnity with the NRC that, together with private insurance, cover third-party liability arising from any nuclear incident occurring at SCE&G's nuclear power plant. Price-Anderson provides funds up to $13.6 billion for public liability claims that could arise from a single nuclear incident. Each nuclear plant is insured against this liability to a maximum of $375 million by ANI with the remaining coverage provided by a mandatory program of deferred premiums that could be assessed, after a nuclear incident, against all owners of commercial nuclear reactors. Each reactor licensee is currently liable for up to $127.3 million per reactor owned for each nuclear incident occurring at any reactor in the United States, provided that not more than $18.9 million of the liability per reactor would be assessed per year.  SCE&G’s maximum assessment, based on its two-thirds ownership of Summer Station Unit 1, would be $84.8 million per incident, but not more than $12.6 million per year. Both the maximum assessment per reactor and the maximum yearly assessment are adjusted for inflation at least every five years.


25

Table of Contents

SCE&G currently maintains insurance policies (for itself and on behalf of Santee Cooper) with NEIL.  The policies provide coverage to Summer Station Unit 1 for property damage and outage costs up to $2.75 billion resulting from an event of nuclear origin. In addition, a builder's risk insurance policy has been purchased from NEIL for the construction of the New Units. This policy provides the owners of the New Units up to $500 million in limits of accidental property damage occurring during construction. The NEIL policies, in the aggregate, are subject to a maximum loss of $2.75 billion for any single loss occurrence. All of the NEIL policies permit retrospective assessments under certain conditions to cover insurer’s losses.  Based on the current annual premium, SCE&G’s portion of the retrospective premium assessment would not exceed $41.6 million.
 
To the extent that insurable claims for property damage, decontamination, repair and replacement and other costs and expenses arising from a nuclear incident at Summer Station Unit 1 exceed the policy limits of insurance, or to the extent such insurance becomes unavailable in the future, and to the extent that SCE&G's rates would not recover the cost of any purchased replacement power, SCE&G will retain the risk of loss as a self-insurer.  SCE&G has no reason to anticipate a serious nuclear incident.  However, if such an incident were to occur, it likely would have a material impact on the Company’s results of operations, cash flows and financial position.

New Nuclear Construction

SCE&G, on behalf of itself and as agent for Santee Cooper, has contracted with the Consortium for the design and construction of the New Units at the site of Summer Station.  SCE&G's share of the estimated cash outlays (future value, excluding AFC) totals approximately $5.4 billion for plant and related transmission infrastructure costs, and is projected based on historical one-year and five-year escalation rates as required by the SCPSC.

SCE&G's current ownership share in the New Units is 55%. Under an agreement signed in January 2014 (and subject to customary closing conditions, including necessary regulatory approvals), SCE&G has agreed to acquire an additional 5% ownership in the New Units. Under the terms of this agreement SCE&G will acquire a 1% ownership interest in the New Units at the commercial operation date of Unit 2, will acquire an additional 2% ownership interest no later than the first anniversary of such commercial operation date, and will acquire the final 2% no later than the second anniversary of such commercial operation date. Under the terms of the agreement SCE&G has agreed to pay an amount equal to Santee Cooper's actual cost of the percentage conveyed as of the date of conveyance, which SCE&G estimates will be approximately $500 million for the entire 5% interest. In addition, the agreement provides that Santee Cooper will not transfer any of its remaining interest in the New Units to third parties until the New Units are complete. This transaction will not affect the payment obligations between the parties during construction for the New Units, nor is it anticipated that the payments would be reflected in a revised rates filing under the BLRA.

Under the BLRA, the SCPSC has approved, among other things, the construction milestone schedule and capital costs estimates schedule for the New Units. The effect of this approval is that it constitutes a final and binding determination that the New Units are used and useful for utility purposes, and that the capital costs associated with the New Units are prudent utility costs and expenses and are properly included in rates, so long as the New Units are constructed or are being constructed within the parameters of the approved construction milestone schedule, including specified contingencies, and the approved capital costs estimates schedule. The BLRA provides that SCE&G may apply to the SCPSC annually for an order to recover through revised rates SCE&G’s weighted average cost of capital applied to all or part of the outstanding balance of construction work in progress concerning the New Units. Such annual rate changes are described in Note 2.

The parties to the EPC Contract have established both informal and formal dispute resolution procedures in order to resolve issues that arise during the course of constructing a project of this magnitude.  During the course of activities under the EPC Contract, issues have materialized that have impacted the project budget and schedule. Claims by the Consortium specifically relating to COL delays, design modifications of the shield building and certain pre-fabricated structural modules for the New Units and unanticipated rock conditions at the site which resulted in assertions of contractual entitlement to recover additional costs have been resolved. SCE&G expects to resolve any additional disputes through both the informal and formal procedures and anticipates that any additional costs that arise through such dispute resolution processes, as well as other costs identified from time to time, will be recoverable through rates.

The substantial completion dates currently approved by the SCPSC for Units 2 and 3 are March 15, 2017 and May 15, 2018. The SCPSC has also approved an 18-month contingency period beyond each of these dates.

In November 2012, the SCPSC approved a petition by SCE&G under the BLRA for an updated construction milestone schedule and additional updated capital costs for the New Units. In addition, the SCPSC approved revised substantial completion dates for the New Units based on the March 30, 2012 issuance of the COL and the amounts agreed upon by SCE&G and the Consortium in July 2012 to resolve claims by the Consortium for costs related to COL delays, design

26

Table of Contents

modifications of the shield building and certain pre-fabricated structural modules for the New Units and unanticipated rock conditions at the site. Immediately thereafter, two parties filed separate petitions requesting that the SCPSC reconsider its order, and on December 12, 2012, the SCPSC denied both petitions.  In March 2013, both parties appealed the SCPSC's order to the South Carolina Supreme Court, contending that the SCPSC erred in granting approval of the updated capital costs for the New Units. The South Carolina Supreme Court heard arguments related to those appeals on April 16, 2014.  SCE&G is unable to predict the outcome of these appeals.

The Consortium has experienced delays in the schedule for fabrication and delivery of sub-modules for the New Units. The fabrication and delivery of sub-modules are a focus area of the Consortium, including sub-modules for module CA20, which is part of the auxiliary building, and CA01, which houses components inside the containment vessel. Modules CA20 and CA01 are considered critical path items for both New Units. All sub-modules for CA20 have been received on site and its assembly is underway. CA20 is expected to be ready for placement on the nuclear island of Unit 2 in May 2014. In addition, the delivery schedule of sub-modules for CA01 is expected to support completion of on-site fabrication to allow it to be ready for placement on the nuclear island of Unit 2 during the latter half of 2014. With this schedule, the Consortium continues to indicate that the substantial completion of Unit 2 is expected to be late 2017 or the first quarter of 2018 and that the substantial completion of Unit 3 is expected to be approximately 12 months after that of Unit 2. These dates are within the SCPSC-approved 18-month contingency period. SCE&G cannot predict with certainty the extent to which the issue with the sub-modules or the delays in the substantial completion of the New Units will result in increased project costs. However, the preliminary estimate of the delay-related costs associated with SCE&G's share of the New Units is approximately $200 million. SCE&G has not accepted responsibility for any of these delay-related costs and expects to have further discussions with the Consortium regarding such responsibility. Additionally, the EPC Contract provides for liquidated damages in the event of a delay in the completion of the facility, which will also be included in discussions with the Consortium. SCE&G believes its responsibility for any portion of the $200 million estimate should ultimately be substantially less, once all of the relevant factors are considered.

During the fourth quarter of 2013, the Consortium began a full re-baselining of the Unit 2 and Unit 3 construction schedules to incorporate a more detailed evaluation of the engineering and procurement activities necessary to accomplish the schedule and to provide a detailed reassessment of the impact of the revised Unit 2 and Unit 3 schedules on engineering and design resource allocations, procurement, construction work crew efficiencies, and other items. The result will be a revised fully integrated project schedule that will provide detailed information on budget and cost and the timing of specific construction activities and cash flow requirements. SCE&G anticipates that the revised schedule and the cost estimate at completion for all non-firm and fixed scopes of work will be finalized in the latter half of 2014. SCE&G plans to reevaluate and reschedule its owners cost estimates and cash flow requirements in light of the new schedule.

The construction milestone schedule approved by the SCPSC in November 2012 provides for 146 construction milestone dates, which are each subject to an 18-month schedule contingency. As of May 3, 2014, 98 milestones have been completed. The currently scheduled completion dates for 44 of the remaining milestones have been delayed between two and 17 months. If, as a result of the re-baselining of the construction schedules for the New Units, the time period for achieving any of the milestones extends beyond its 18-month schedule contingency and/or the capital costs estimates increase, then SCE&G, as provided for under the BLRA, may petition the SCPSC for an order to update the construction milestone schedule and/or capital costs estimates schedule. The BLRA provides that the SCPSC shall grant the petition for modification if the record justifies a finding that the change is not the result of imprudence by SCE&G.

In addition to the above-described project delays, SCE&G is also aware of financial difficulties at a supplier responsible for certain significant components of the project.  The Consortium is monitoring the potential for disruptions in such equipment fabrication and possible responses.  Any disruptions could impact the project's schedule or costs, and such impacts could be material.

When the NRC issued the COLs for the New Units, two of the conditions that it imposed were requiring inspection and testing of certain components of the New Units' passive cooling system, and requiring the development of strategies to respond to extreme natural events resulting in the loss of power at the New Units.  In addition, the NRC directed the Office of New Reactors to issue to SCE&G an order requiring enhanced, reliable spent fuel pool instrumentation, as well as a request for information related to emergency plant staffing.  These conditions and requirements are responsive to the NRC's Near-Term Task Force report titled “Recommendations for Enhancing Reactor Safety in the 21st Century.”  This report was prepared in the wake of the March 2011 earthquake-generated tsunami, which severely damaged several nuclear generating units and their back-up cooling systems in Japan.  SCE&G continues to evaluate the impact of these conditions and requirements that may be imposed on the construction and operation of the New Units, and prepared and submitted an integrated response plan for the New Units to the NRC in August 2013.  SCE&G cannot predict what additional regulatory or other outcomes may be

27

Table of Contents

implemented in the United States, or how such initiatives would impact SCE&G's existing Summer Station or the construction or operation of the New Units.

Subject to a national megawatt capacity limitation, the electricity to be produced by the New Units (advanced nuclear units, as defined) is expected to qualify for nuclear production tax credits under Section 45J of the Internal Revenue Code. Following the pouring of safety-related concrete for each of the New Units’ reactor buildings (March 2013 for Unit 2 and November 2013 for Unit 3), SCE&G has applied to the IRS for its allocations of such national megawatt capacity limitation. The IRS will forward the applications to the DOE for appropriate certification.

Environmental
 
As part of the President's Climate Action Plan and by Presidential Memorandum issued June 25, 2013, the EPA was directed to issue a revised carbon standard for new power plants by re-proposing NSPS under the CAA for emissions of carbon dioxide from newly constructed fossil fuel-fired units. The rule became final on January 8, 2014 and requires all new fossil fuel-fired power plants to meet the carbon dioxide emissions profile of a combined cycle natural gas plant. While most new natural gas plants will not be required to include any new technologies, no new coal-fired plants can be constructed without carbon capture and sequestration capabilities. The Company is evaluating the final rule, but does not plan to construct new coal-fired units in the foreseeable future. The Memorandum also directed the EPA to issue standards, regulations, or guidelines for existing units by June 1, 2014, to be made final no later than June 1, 2015. The Company also cannot predict when rules will become final for existing units, if at all, or what conditions they may impose on the Company, if any. The Company expects that any costs incurred to comply with GHG emission requirements will be recoverable through rates.

In 2005, the EPA issued the CAIR, which required the District of Columbia and 28 states to reduce nitrogen oxide and sulfur dioxide emissions in order to attain mandated state levels.  CAIR set emission limits to be met in two phases beginning in 2009 and 2015, respectively, for nitrogen oxide and beginning in 2010 and 2015, respectively, for sulfur dioxide.  SCE&G and GENCO determined that additional air quality controls would be needed to meet the CAIR requirements.  On July 6, 2011 the EPA issued the CSAPR.  This rule replaced CAIR and the Clean Air Transport Rule proposed in July 2010 and is aimed at addressing power plant emissions that may contribute to air pollution in other states.  CSAPR requires states in the eastern United States to reduce power plant emissions, specifically sulfur dioxide and nitrogen oxide.  On December 30, 2011, the Court of Appeals issued an order staying CSAPR and reinstating CAIR pending resolution of an appeal of CSAPR. On August 21, 2012, the Court of Appeals vacated CSAPR and left CAIR in place. On April 29, 2014, the U. S. Supreme Court reversed the judgment of the Court of Appeals and CSAPR was remanded to the Court of Appeals for further proceedings consistent with the U. S. Supreme Court opinion. Air quality control installations that SCE&G and GENCO have already completed have allowed the Company to comply with the reinstated CAIR and will also allow it to comply with CSAPR, if reinstated. The Company will continue to pursue strategies to comply with all applicable environmental regulations.  Any costs incurred to comply with such regulations are expected to be recoverable through rates.
 
In April 2012, the EPA's rule containing new standards for mercury and other specified air pollutants became effective.  The rule provides up to four years for facilities to meet the standards, and the Company's evaluation of the rule is ongoing. The Company's decision in 2012 to retire certain coal-fired units or convert them to burn natural gas and its project to build the New Units (see Note 1) along with other actions are expected to result in the Company's compliance with the EPA's rule.  Any costs incurred to comply with this rule or other rules issued by the EPA in the future are expected to be recoverable through rates.

The CWA provides for the imposition of effluent limitations that require treatment for wastewater discharges. Under the CWA, compliance with applicable limitations is achieved under state-issued NPDES permits. As a facility’s NPDES permit is renewed (every five years), any new effluent limitations would be incorporated. The ELG Rule was published in the Federal Register on June 7, 2013, and is expected to be finalized September 30, 2015. The EPA expects compliance within a three to six year time frame as NPDES permits are renewed.

Additionally, the EPA is expected to issue a rule that modifies requirements for existing cooling water intake structures in 2014. The Company is conducting studies and is developing or implementing compliance plans for these initiatives. Congress is expected to consider further amendments to the CWA. Such legislation may include toxicity-based standards as well as limitations to mixing zones. These provisions, if passed, could have a material impact on the financial condition, results of operations and cash flows of the Company. The Company believes that any additional costs imposed by such regulations would be recoverable through rates.

In response to a federal court order to establish a definite timeline for a CCR rule and subsequent obligation via consent decree, the EPA committed to issue new federal regulations affecting the management and disposal of CCRs, such as ash, by December 19, 2014. Such regulations could result in the treatment of some CCRs as hazardous waste and could impose

28

Table of Contents

significant costs to utilities, such as SCE&G and GENCO. While the Company cannot predict how extensive the regulations will be, the Company believes that any additional costs imposed by such regulations would be recoverable through rates.

The Nuclear Waste Act required that the United States government accept and permanently dispose of high-level radioactive waste and spent nuclear fuel by January 31, 1998. The Nuclear Waste Act also imposed on utilities the primary responsibility for storage of their spent nuclear fuel until the repository is available. SCE&G entered into a Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste with the DOE in 1983. As of March 31, 2014, the federal government has not accepted any spent fuel from Summer Station Unit 1, and it remains unclear when the repository may become available. SCE&G has on-site spent nuclear fuel storage capability in its existing fuel pool until at least 2017, and is constructing a dry cask storage facility to accommodate the spent nuclear fuel output for the life of Summer Station Unit 1. SCE&G may evaluate other technology as it becomes available.
 
The provisions of CERCLA authorize the EPA to require the clean-up of hazardous waste sites. In addition, the states of South Carolina and North Carolina have similar laws. The Company maintains an environmental assessment program to identify and evaluate current and former operations sites that could require environmental clean-up. In addition, regulators from the EPA and other federal or state agencies periodically notify the Company that it may be required to perform or participate in the investigation and remediation of a hazardous waste site. As site assessments are initiated, estimates are made of the amount of expenditures, if any, deemed necessary to investigate and remediate each site. These estimates are refined as additional information becomes available; therefore, actual expenditures may differ significantly from the original estimates. Amounts estimated and accrued to date for site assessments and clean-up relate solely to regulated operations. Such amounts are recorded in regulatory assets and amortized, with recovery provided through rates.
 
SCE&G is responsible for four decommissioned MGP sites in South Carolina which contain residues of byproduct chemicals.  These sites are in various stages of investigation, remediation and monitoring under work plans approved by DHEC and the EPA.  SCE&G anticipates that major remediation activities at all these sites will continue until 2017 and will cost an additional $20.2 million, which is accrued in Other within Deferred Credits and Other Liabilities on the condensed consolidated balance sheet.  SCE&G expects to recover any cost arising from the remediation of MGP sites through rates.  At March 31, 2014, deferred amounts, net of amounts previously recovered through rates and insurance settlements, totaled $36.7 million and are included in regulatory assets.
 
PSNC Energy is responsible for environmental clean-up at five sites in North Carolina on which MGP residuals are present or suspected.  PSNC Energy’s actual remediation costs for these sites will depend on a number of factors, such as actual site conditions, third-party claims and recoveries from other PRPs.  PSNC Energy has recorded a liability and associated regulatory asset of approximately $2.8 million, the estimated remaining liability at March 31, 2014. PSNC Energy expects to recover through rates any cost allocable to PSNC Energy arising from the remediation of these sites.

10.
SEGMENT OF BUSINESS INFORMATION
 
The Company’s reportable segments are listed in the following table.  The Company uses operating income to measure profitability for its regulated operations; therefore, net income is not allocated to the Electric Operations and Gas Distribution segments.  The Company uses net income to measure profitability for its Retail Gas Marketing and Energy Marketing segments.  Gas Distribution is comprised of the local distribution operations of SCE&G and PSNC Energy which meet the criteria for aggregation.  All Other includes equity method investments and other nonreportable segments.  Nonreportable segments include a FERC-regulated interstate pipeline company and other companies that conduct nonregulated operations in energy-related and telecommunications industries.
    

29

Table of Contents

Millions of dollars
 
External
Revenue
 
Intersegment Revenue
 
Operating
Income
 
Net
Income
Three Months Ended March 31, 2014
 
 
 
 
 
 
 
 
Electric Operations
 
$
678

 
$
2

 
$
198

 
n/a

Gas Distribution
 
455

 

 
97

 
n/a

Retail Gas Marketing
 
220

 

 
n/a

 
$
22

Energy Marketing
 
234

 
53

 
n/a

 
7

All Other
 
9

 
110

 
8

 
4

Adjustments/Eliminations
 
(6
)
 
(165
)
 
47

 
160

Consolidated Total
 
$
1,590

 
$

 
$
350

 
$
193

Three Months Ended March 31, 2013
 
 
 
 
 
 
 
 
Electric Operations
 
$
583

 
$
2

 
$
153

 
n/a

Gas Distribution
 
379

 

 
93

 
n/a

Retail Gas Marketing
 
179

 

 
n/a

 
$
22

Energy Marketing
 
167

 
42

 
n/a

 
3

All Other
 
12

 
107

 
7

 
3

Adjustments/Eliminations
 
(9
)
 
(151
)
 
40

 
123

Consolidated Total
 
$
1,311

 
$

 
$
293

 
$
151


 
 
March 31,
 
December 31,
 
Segment Assets
 
2014
 
2013
 
Electric Operations
 
$
9,542

 
$
9,488

 
Gas Distribution
 
2,408

 
2,340

 
Retail Gas Marketing
 
162

 
172

 
Energy Marketing
 
154

 
133

 
All Other
 
1,363

 
1,378

 
Adjustments/Eliminations
 
1,713

 
1,653

 
Consolidated Total
 
$
15,342

 
$
15,164

 

30

Table of Contents


ITEM 2.     MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS
OF OPERATIONS
 
SCANA CORPORATION
 
The following discussion should be read in conjunction with Management’s Discussion and Analysis of Financial Condition and Results of Operations appearing in SCANA’s Annual Report on Form 10-K for the year ended December 31, 2013.
RESULTS OF OPERATIONS
FOR THE THREE MONTHS ENDED MARCH 31, 2014
AS COMPARED TO THE CORRESPONDING PERIOD IN 2013
 
Earnings Per Share
 
Earnings per share was as follows:
 
 
2014

 
2013

Basic earnings per share
 
$
1.37

 
$
1.13

Diluted earnings per share
 
$
1.37

 
$
1.11

 
Basic earnings per share increased due to higher electric and gas margins. These margin increases were partially offset by higher operation and maintenance expenses, higher depreciation expense, higher property taxes, higher interest cost and dilution from additional shares outstanding, as further discussed below.

Diluted earnings per share figures give effect to dilutive potential common stock using the treasury stock method. See Note 1 to the condensed consolidated financial statements.
 
Dividends Declared
 
SCANA’s Board of Directors has declared the following dividends on common stock during 2014:
Declaration Date
 
Dividend Per Share
 
Record Date
 
Payment Date
February 20, 2014
 
$0.5250
 
March 10, 2014
 
April 1, 2014
April 24, 2014
 
$0.5250
 
June 10, 2014
 
July 1, 2014

When a dividend payment date falls on a weekend or holiday, the payment is made the following business day.

Electric Operations
 
Electric Operations is comprised of the electric operations of SCE&G, GENCO and Fuel Company.  Electric operations sales margin (including transactions with affiliates) was as follows:
Millions of dollars
 
2014
 
Change
 
2013
Operating revenues
 
$
679.9


16.1
%
 
$
585.6

Less:  Fuel used in generation
 
213.8


13.9
%
 
187.7

Purchased power
 
25.0


*

 
7.0

Margin
 
$
441.1


12.8
%

$
390.9

* Greater than 100%
 
Electric margin increased primarily due to the effects of weather of $20.1 million, customer growth and consumption of $13.2 million and base rate increases under the BLRA and DSM Program rider of $16.7 million. Due to the termination of eWNA effective January 1, 2014, electric margin is subject to the effects of weather.



31


Sales volumes (in GWh) related to the electric margin above, by class, were as follows:
Classification
 
2014
 
Change
 
2013
Residential
 
2,151


15.8
 %
 
1,858

Commercial
 
1,750


4.9
 %
 
1,669

Industrial
 
1,453


3.6
 %
 
1,403

Other
 
140


4.5
 %
 
134

Total Retail Sales
 
5,494


8.5
 %

5,064

Wholesale
 
244


(7.6
)%
 
264

Total Sales
 
5,738


7.7
 %

5,328


Retail sales volume increased by 246 GWh due to the effects of weather and by 131 GWh due to customer growth and higher average use. The decrease in wholesale sales is primarily due to the expiration of a customer contract.

Gas Distribution
 
Gas Distribution is comprised of the local distribution operations of SCE&G and PSNC Energy.  Gas distribution sales margin (including transactions with affiliates) was as follows:
Millions of dollars
 
2014
 
Change
 
2013
Operating revenues
 
$
455.2

 
20.0
%
 
$
379.3

Less:  Gas purchased for resale
 
292.5

 
31.3
%
 
222.7

Margin
 
$
162.7

 
3.9
%
 
$
156.6

 
Margin increased primarily due to residential and commercial customer growth of $3.7 million and increased average usage of $2.3 million. SCE&G's WNA and PSNC Energy's CUT mitigate weather-related fluctuations in margin but have no impact on volumes.
    
Sales volumes (in MMBTU) by class, including transportation, were as follows:
Classification (in thousands)
 
2014
 
Change
 
2013
Residential
 
25,981

 
21.5
 %
 
21,375

Commercial
 
12,767

 
18.7
 %
 
10,758

Industrial
 
5,333

 
(13.4
)%
 
6,161

Transportation
 
10,106

 
(9.8
)%
 
11,200

Total
 
54,187

 
9.5
 %
 
49,494


Total sales volumes increased primarily due to the effects of weather.

Retail Gas Marketing
 
Retail Gas Marketing is comprised of SCANA Energy, which operates in Georgia’s natural gas market.  Retail Gas Marketing operating revenues and net income were as follows:
Millions of dollars
 
2014
 
Change
 
2013
 
Operating revenues
 
$
220.2

 
23.0
%
 
$
179.0

 
Net income
 
22.3

 
0.9
%
 
22.1

 
 
Operating revenues increased in 2014 due to the increased demand related to weather and customer growth. Net income in 2014 was impacted by higher revenues related to the colder than normal weather, offset by higher costs including commodity costs and bad debt expense.
  

32


Energy Marketing
 
Energy Marketing is comprised of the Company’s non-regulated marketing operations, excluding SCANA Energy.  Energy Marketing operating revenues and net income were as follows:

Millions of dollars
 
2014
 
Change
 
2013
Operating revenues
 
$
286.7

 
37.1
%
 
$
209.1

Net income
 
6.5

 
*
 
2.7

 * Greater than 100%

Operating revenues and net income increased due to higher market prices and margins on incremental sales. 

 Other Operating Expenses
 
Other operating expenses were as follows:
Millions of dollars
 
2014
 
Change
 
2013
 
Other operation and maintenance
 
$
180.3

 
2.4
%
 
$
176.1

 
Depreciation and amortization
 
94.9

 
1.7
%
 
93.3

 
Other taxes
 
57.6

 
5.1
%
 
54.8

 
 
Other operation and maintenance expenses increased primarily due to incremental storm related expenses. Depreciation and amortization expense increased due to net plant additions.  Other taxes increased primarily due to higher property taxes.

Other Income (Expense)
 
Other income (expense) includes the results of certain incidental (non-utility) activities, the activities of certain non-regulated subsidiaries and AFC. AFC is a utility accounting practice whereby a portion of the cost of both equity and borrowed funds used to finance construction (which is shown on the balance sheet as construction work in progress) is capitalized.  The Company includes an equity portion of AFC in nonoperating income and a debt portion of AFC in interest charges (credits), both of which have the effect of increasing reported net income.  AFC increased in 2014 due to higher AFC rates.
 
Interest Expense

     Interest charges increased primarily due to increased borrowings.

Income Taxes
 
Income taxes for the three months ended March 31, 2014 were higher than the same period in 2013 primarily due to higher income before taxes which was partially offset by a marginally lower effective tax rate.

LIQUIDITY AND CAPITAL RESOURCES
 
The Company anticipates that its cash obligations will be met through internally generated funds, the incurrence of additional short- and long-term indebtedness and sales of equity securities.  The Company expects that, barring a future impairment of the capital markets, it has or can obtain adequate sources of financing to meet its projected cash requirements for the foreseeable future, including the cash requirements for nuclear construction and refinancing maturing long-term debt.  The Company’s ratio of earnings to fixed charges for the three and 12 months ended March 31, 2014 was 4.52 and 3.38, respectively.
     
The Company is obligated with respect to an aggregate of $67.8 million of industrial revenue bonds which are secured by letters of credit issued by Branch Banking and Trust Company.  These letters of credit expire, subject to renewal, in the fourth quarter of 2014.
 

33

Table of Contents

At March 31, 2014, the Company had net available liquidity of approximately $1.3 billion. The credit agreements total an aggregate of $1.8 billion, of which $200 million is scheduled to expire in October 2016 and the remainder is scheduled to expire in October 2018. The Company regularly monitors the commercial paper and short-term credit markets to optimize the timing of repayment of outstanding balances on its draws, if any, from the credit facilities.  The Company’s long-term debt portfolio has a weighted average maturity of approximately 18 years and bears an average interest cost of 5.7%.  Substantially all of the long-term debt bears fixed interest rates or is swapped to fixed.  To further preserve liquidity, the Company rigorously reviews its projected capital expenditures and operating costs and adjusts them where possible without impacting safety, reliability, and core customer service.

SCE&G has obtained FERC authority to issue short-term indebtedness and to assume liabilities as a guarantor (pursuant to Section 204 of the Federal Power Act). SCE&G may issue unsecured promissory notes, commercial paper and direct loans in amounts not to exceed $1.6 billion outstanding with maturity dates of one year or less, and may enter into guaranty agreements in favor of lenders, bankers, and dealers in commercial paper in amounts not to exceed $600 million. GENCO has obtained FERC authority to issue short-term indebtedness not to exceed $150 million outstanding with maturity dates of one year or less. The authority described herein will expire in October 2014 and is expected to be renewed.

SCANA issued approximately $27 million of common stock during the three months ended March 31, 2014 through various compensation and dividend reinvestment plans.  Similar issuances are expected in future periods. In March 2013, SCANA settled all forward sales contracts related to its common stock through the issuance of approximately 6.6 million common shares, resulting in net proceeds of approximately $196 million.
    
In connection with the expected delays in the substantial completion of the New Units described in Note 9 to the condensed consolidated financial statements, SCE&G's current preliminary estimates of its capital expenditures for new nuclear construction (including transmission) for 2014 through 2016, which are subject to continuing review and adjustment, are $879 million in 2014, $910 million in 2015, and $702 million in 2016.

OTHER MATTERS
 
For information related to environmental matters, nuclear generation, and claims and litigation, see Note 9 to the condensed consolidated financial statements.


ITEM 3.
QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK
 
Interest Rate Risk - The Company's market risk exposures relative to interest rate risk have not changed materially compared with the Company's Annual Report on Form 10-K for the year ended December 31, 2013. Interest rates on substantially all of the Company's outstanding long-term debt, other than credit facility draws, are fixed either through the issuance of fixed rate debt or through the use of interest rate derivatives. The Company is not aware of any facts or circumstances that would significantly affect exposures on existing indebtedness in the near future.
 
For further discussion of changes in long-term debt and interest rate derivatives, see ITEM 2.  MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS – LIQUIDITY AND CAPITAL RESOURCES and also Notes 4, 6 and 7 of the condensed consolidated financial statements.
 
Commodity price risk - The Company uses derivative instruments to hedge forward purchases and sales of natural gas, which create market risks of different types.  See Note 6 of the condensed consolidated financial statements.  The following tables provide information about the Company’s financial instruments that are sensitive to changes in natural gas prices.  Weighted average settlement prices are per 10,000 MMBTU.  Fair value represents quoted market prices for these or similar instruments.

34

Table of Contents

 
 
 
Expected Maturity
 
 
 
Expected Maturity
Futures - Long
 
2014
 
2015
 
 
Options Purchased Call - Long
 
2014
 
2015
Settlement Price (a)
 
4.44

 
4.45

 
 
Strike Price (a)
 
4.03

 
4.62

Contract Amount (b)
 
6.6

 
1.1

 
 
Contract Amount (b)
 
11.3

 
9.1

Fair Value (b)
 
7.5

 
1.2

 
 
Fair Value (b)
 
1.7

 
0.9

 
 
 
 
 
 
 
 
 
 
 
 
Futures - Short
 
2014
 
2015
 
 
 
 
 
 
 
Settlement Price (a)
 
4.43

 
4.04

 
 
 
 
 
 
 
Contract Amount (b)
 
0.6

 
0.3

 
 
 
 
 
 
 
Fair Value (b)
 
0.6

 
0.3

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
(a)  Weighted average, in dollars
 
 
 
 
 
 
 
 
 
(b)  Millions of dollars
 
 
 
 
 
 
 
 
 
 
 
 
Expected Maturity
Swaps
 
2014
 
2015
 
2016
 
2017
 
2018
Commodity Swaps:
 
 

 
 

 
 

 
 

 
 

Pay fixed/receive variable (b)
 
32.8

 
23.1

 
12.6

 
4.6

 
3.6

Average pay rate (a)
 
4.3945

 
4.8081

 
4.5950

 
4.2167

 
4.2421

Average received rate (a)
 
4.4547

 
4.3120

 
4.1516

 
4.2508

 
4.3588

Fair value (b)
 
33.2

 
20.7

 
11.4

 
4.6

 
3.7

Pay variable/receive fixed (b)
 
21.0

 
15.1

 
11.2

 
4.6

 
3.7

Average pay rate (a)
 
4.4431

 
4.2292

 
4.1512

 
4.2508

 
4.3588

Average received rate (a)
 
4.4059

 
4.8945

 
4.6004

 
4.2217

 
4.2471

Fair value (b)
 
20.8

 
17.5

 
12.5

 
4.6

 
3.6

Basis Swaps:
 
 

 
 

 
 

 
 

 
 

Pay variable/receive variable (b)
 
0.6

 
0.5

 

 

 

Average pay rate (a)
 
4.5075

 
4.6610

 

 

 

Average received rate (a)
 
4.4715

 
4.6395

 

 

 

Fair value (b)
 
0.6

 
0.5

 

 

 

 
 
 

 
 

 
 

 
 

 
 

(a) Weighted average, in dollars 
 
 
 
 
 
 
 
 
 
 
(b) Millions of dollars
 
 

 
 

 
 

 
 

 
 

 
 
 
 
 
 
 
 
 
 
 
ITEM 4.
CONTROLS AND PROCEDURES
 
As of March 31, 2014, SCANA conducted an evaluation under the supervision and with the participation of its management, including its CEO and CFO, of (a) the effectiveness of the design and operation of its disclosure controls and procedures and (b) any change in its internal control over financial reporting.  Based on this evaluation, the CEO and CFO concluded that, as of March 31, 2014, SCANA’s disclosure controls and procedures were effective.  There has been no change in SCANA’s internal control over financial reporting during the quarter ended March 31, 2014 that has materially affected or is reasonably likely to materially affect SCANA’s internal control over financial reporting.

35

Table of Contents













SOUTH CAROLINA ELECTRIC & GAS COMPANY
FINANCIAL SECTION

36

Table of Contents

ITEM 1.     FINANCIAL STATEMENTS
SOUTH CAROLINA ELECTRIC & GAS COMPANY
CONDENSED CONSOLIDATED BALANCE SHEETS
(Unaudited)
Millions of dollars
 
March 31,
2014
 
December 31,
2013
Assets
 
 

 
 

Utility Plant In Service
 
$
10,447

 
$
10,378

Accumulated Depreciation and Amortization
 
(3,531
)
 
(3,499
)
Construction Work in Progress
 
2,798

 
2,682

Plant to be Retired, Net
 
176

 
177

Nuclear Fuel, Net of Accumulated Amortization
 
298

 
310

Utility Plant, Net ($708 and $720 related to VIEs)
 
10,188

 
10,048

Nonutility Property and Investments:
 
 

 
 

Nonutility property, net of accumulated depreciation
 
71

 
69

Assets held in trust, net-nuclear decommissioning
 
104

 
101

Other investments
 
2

 
3

Nonutility Property and Investments, Net
 
177

 
173

Current Assets:
 
 

 
 

     Cash and cash equivalents
 
32

 
92

      Receivables, net of allowance for uncollectible accounts of $3 and $3
 
506

 
486

      Affiliated receivables
 
10

 
19

      Inventories (at average cost):
 
 

 
 

     Fuel and gas supply
 
101

 
132

     Materials and supplies
 
122

 
120

     Prepayments and other
 
73

 
80

     Total Current Assets ($93 and $147 related to VIEs)
 
844

 
929

Deferred Debits and Other Assets:
 
 

 
 

Pension asset
 
98

 
96

Regulatory assets
 
1,409

 
1,303

Other
 
133

 
151

     Total Deferred Debits and Other Assets ($39 and $35 related to VIEs)
 
1,640

 
1,550

Total
 
$
12,849

 
$
12,700


See Notes to Condensed Consolidated Financial Statements.

37

Table of Contents

Millions of dollars
 
March 31,
2014
 
December 31,
2013
Capitalization and Liabilities
 
 
 
 
Common Stock - no par value, 40.3 million shares outstanding for all periods presented
 
$
2,499

 
$
2,479

Retained Earnings
 
1,957

 
1,896

Accumulated Other Comprehensive Loss
 
(3
)
 
(3
)
Total Common Equity
 
4,453

 
4,372

Noncontrolling Interest
 
118

 
117

Total Equity
 
4,571

 
4,489

Long-Term Debt, net
 
4,001

 
4,007

Total Capitalization
 
8,572

 
8,496

Current Liabilities:
 
 
 
 
Short-term borrowings
 
457

 
251

Current portion of long-term debt
 
47

 
48

Accounts payable
 
214

 
241

Affiliated payables
 
117

 
117

  Customer deposits and customer prepayments
 
55

 
56

Taxes accrued
 
96

 
223

Interest accrued
 
53

 
64

Dividends declared
 
64

 
62

  Derivative financial instruments
 
41

 
1

Other
 
95

 
71

Total Current Liabilities
 
1,239

 
1,134

Deferred Credits and Other Liabilities:
 
 
 
 
Deferred income taxes, net
 
1,514

 
1,509

Deferred investment tax credits
 
31

 
32

Asset retirement obligations
 
553

 
547

Postretirement benefits
 
174

 
173

Regulatory liabilities
 
644

 
732

Other
 
122

 
77

Total Deferred Credits and Other Liabilities
 
3,038

 
3,070

 Commitments and Contingencies (Note 9)
 

 

Total
 
$
12,849

 
$
12,700

 
See Notes to Condensed Consolidated Financial Statements.

38

Table of Contents

SOUTH CAROLINA ELECTRIC & GAS COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF INCOME
(Unaudited) 
 
 
 Three Months Ended
 
 
March 31,
Millions of dollars
 
2014
 
2013
Operating Revenues:
 
 

 
 
Electric
 
$
680

 
$
585

Gas
 
179

 
143

Total Operating Revenues
 
859

 
728

Operating Expenses:
 
 

 
 
Fuel used in electric generation
 
214

 
188

Purchased power
 
25

 
7

Gas purchased for resale
 
109

 
77

Other operation and maintenance
 
142

 
138

Depreciation and amortization
 
78

 
77

Other taxes
 
52

 
50

Total Operating Expenses
 
620

 
537

Operating Income
 
239

 
191

Other Revenue (Expense):
 
 

 
156,311

Other revenue
 
3

 

Other expense
 
(6
)
 
(4
)
Interest charges, net of allowance for borrowed funds used during construction of $3 and $2
 
(56
)
 
(55
)
Allowance for equity funds used during construction
 
5

 
4

Total Other Expense
 
(54
)
 
(55
)
Income Before Income Tax Expense
 
185

 
136

Income Tax Expense
 
59

 
44

Net Income
 
126

 
92

Net Income Attributable to Noncontrolling Interest
 
(3
)
 
(3
)
Earnings Available to Common Shareholder
 
$
123

 
$
89

 
 
 
 
 
Dividends Declared on Common Stock
 
$
64

 
$
64

 
See Notes to Condensed Consolidated Financial Statements.

39

Table of Contents

SOUTH CAROLINA ELECTRIC & GAS COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(Unaudited)

 
 
Three Months Ended March 31,
Millions of dollars
 
2014
 
2013
Net Income
 
$
126

 
$
92

Total Comprehensive Income
 
126

 
92

Comprehensive income attributable to noncontrolling interest
 
(3
)
 
(3
)
Comprehensive income available to common shareholder
 
$
123

 
$
89

 
See Notes to Condensed Consolidated Financial Statements.

40

Table of Contents

SOUTH CAROLINA ELECTRIC & GAS COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(Unaudited)
 
 
Three Months Ended March 31,
Millions of dollars
 
2014
 
2013
Cash Flows From Operating Activities:
 
 
 
 
Net income
 
$
126

 
$
92

Adjustments to reconcile net income to net cash provided from operating activities:
 
 
 
 
Losses from equity method investments
 
1

 
1

Deferred income taxes, net
 
5

 
12

Depreciation and amortization
 
78

 
78

Amortization of nuclear fuel
 
15

 
13

Allowance for equity funds used during construction
 
(5
)
 
(4
)
Carrying cost recovery
 
(2
)
 

Changes in certain assets and liabilities:
 
 
 
 
Receivables
 
(23
)
 
(7
)
Inventories
 
19

 
10

Prepayments and other
 
7

 
(12
)
Pension and other post retirement benefits
 
(2
)
 

Regulatory assets
 
(107
)
 
11

Regulatory liabilities
 
(94
)
 
27

Accounts payable
 
27

 
4

Taxes accrued
 
(127
)
 
(81
)
Interest accrued
 
(11
)
 
(12
)
Other assets
 
15

 
(21
)
Other liabilities
 
121

 
(21
)
Net Cash Provided From Operating Activities
 
43

 
90

Cash Flows From Investing Activities:
 
 
 
 
Property additions and construction expenditures
 
(260
)
 
(264
)
Proceeds from investments (including derivative collateral posted)
 
4

 
81

Purchase of investments (including derivative collateral posted)
 
(9
)
 
(70
)
Net Cash Used For Investing Activities
 
(265
)
 
(253
)
Cash Flows From Financing Activities:
 
 
 
 
Proceeds from issuance of long-term debt
 

 
57

Repayment of long-term debt
 
(9
)
 
(66
)
Dividends
 
(62
)
 
(46
)
Contributions from parent
 
20

 
221

Short-term borrowings –affiliate, net
 
7

 
(1
)
Short-term borrowings, net
 
206

 
(41
)
Net Cash Provided From Financing Activities
 
162

 
124

Net Decrease In Cash and Cash Equivalents
 
(60
)
 
(39
)
Cash and Cash Equivalents, January 1
 
92

 
51

Cash and Cash Equivalents, March 31
 
$
32

 
$
12

 
 
 
 
 
 Supplemental Cash Flow Information:
 
 
 
 
Cash paid for– Interest (net of capitalized interest of $3 and $2)
 
$
62

 
$
62

– Income taxes
 
59

 

 
 
 
 
 
Noncash Investing and Financing Activities:
 
 
 
 
Accrued construction expenditures
 
67

 
81

Capital leases
 
1

 
1

Nuclear fuel purchase
 

 
97

 
See Notes to Condensed Consolidated Financial Statements.

41

Table of Contents

SOUTH CAROLINA ELECTRIC & GAS COMPANY
NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
For the Three Months Ended March 31, 2014 and 2013
(Unaudited)
 
The following notes should be read in conjunction with the Notes to Consolidated Financial Statements appearing in SCE&G’s Annual Report on Form 10-K for the year ended December 31, 2013.  These are interim financial statements and, due to the seasonality of Consolidated SCE&G’s business and matters that may occur during the rest of the year, the amounts reported in the Condensed Consolidated Statements of Income are not necessarily indicative of amounts expected for the full year.  In the opinion of management, the information furnished herein reflects all adjustments, all of a normal recurring nature, which are necessary for a fair statement of the results for the interim periods reported.
1.
SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES
 
Use of Estimates
 
The preparation of financial statements in conformity with generally accepted accounting principles requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and liabilities at the date of the financial statements and the reported amount of revenues and expenses during the reporting period. Actual results could differ from those estimates.
 
Variable Interest Entities
 
SCE&G has determined that it is the primary beneficiary of GENCO and Fuel Company (which are considered to be VIEs) and, accordingly, the accompanying condensed consolidated financial statements include the accounts of SCE&G, GENCO and Fuel Company. The equity interests in GENCO and Fuel Company are held solely by SCANA, SCE&G’s parent. Accordingly, GENCO’s and Fuel Company’s equity and results of operations are reflected as noncontrolling interest in Consolidated SCE&G’s condensed consolidated financial statements.
 
GENCO owns a coal-fired electric generating station with a 605 MW net generating capacity (summer rating). GENCO’s electricity is sold, pursuant to a FERC-approved tariff, solely to SCE&G under the terms of a power purchase agreement and related operating agreement. The effects of these transactions are eliminated in consolidation. Substantially all of GENCO’s property (carrying value of approximately $476 million) serves as collateral for its long-term borrowings. Fuel Company acquires, owns and provides financing for SCE&G’s nuclear fuel, certain fossil fuels and emission allowances. See also Note 4.

Plant to be Retired

As previously disclosed, in 2012, SCE&G identified six coal-fired units that it intends to retire by 2018, subject to future developments in environmental regulations, among other matters. These units had an aggregate generating
capacity (summer 2012) of 730 MW. Three of these units had been retired by December 31, 2013, and their net carrying value is recorded in regulatory assets (see Note 2). The net carrying value of the remaining units is identified as Plant to be Retired, Net in the condensed consolidated financial statements. SCE&G plans to request recovery of and a return on the net carrying value of these remaining units in future rate proceedings in connection with their retirement, and expects that such deferred amounts will be recovered through rates. In the meantime, these units remain in use and in rate base, and SCE&G depreciates them using composite straight-line rates approved by the SCPSC.

2.
RATE AND OTHER REGULATORY MATTERS
 
Rate Matters
 
Electric - Cost of Fuel
 
SCE&G's retail electric rates include a cost of fuel component approved by the SCPSC which may be adjusted periodically to reflect changes in the price of fuel purchased by SCE&G. In connection with its annual review of base rates for fuel costs, and by order dated April 30, 2013, the SCPSC approved a settlement agreement among SCE&G, the ORS and the SCEUC in which SCE&G agreed to reduce its environmental fuel cost component effective with the first billing cycle of May 2013. The order also provided for the accrual of certain debt-related carrying costs on a portion of SCE&G's under-collected balance of fuel costs. and approved SCE&G's total fuel cost component.

42

Table of Contents


By order dated April 29, 2014, the SCPSC approved a settlement agreement among SCE&G, the ORS and SCEUC in which SCE&G agreed to increase its base fuel cost component by approximately $10.3 million for the 12-month period beginning with the first billing cycle of May 2014.  The SCPSC's order also provides for, among other things, the application of approximately $46 million in deferred gains from the settlement of certain interest rate swaps, previously recorded as regulatory liabilities, to reduce the under-collected balance of fuel costs in April 2014 and the accrual of certain debt-related carrying costs on its under-collected balance of fuel costs during the period May 1, 2014 through April 30, 2015. 
    
The increase to the base fuel cost component is offset by a reduction in SCE&G’s rate rider related to pension costs, which was approved by the SCPSC in March 2014. The reduction was requested by SCE&G as a result of the lower net periodic benefit cost it expects to record during 2014. See also Note 8.

Electric - Base Rates

In October 2013, SCE&G received an accounting order from the SCPSC directing it to remove from rate base deferred income tax assets arising from capital expenditures related to the New Units and to accrue carrying costs (recorded as a regulatory asset) on those amounts during periods in which they are not included in rate base.  Such carrying costs are determined at SCE&G’s weighted average long-term borrowing rate, and during the first quarter of 2014, $1.2 million of such carrying costs were accrued within other income. SCE&G anticipates that when the New Units are placed in service and accelerated tax deprecation is recognized on them, these deferred income tax assets will decline.  When these deferred income tax assets are fully offset by related deferred income tax liabilities, the carrying cost accruals will cease, and the regulatory asset will begin to be amortized.

SCE&G files an IRP with the SCPSC annually which evaluates future electric generation needs based on several factors, including customer energy demands, EPA regulations, reserve margins and fuel costs. SCE&G's 2012 IRP identified six coal-fired units that SCE&G has retired or intends to retire by 2018, subject to future developments in environmental regulations, among other matters. Three of these units had been retired by December 31, 2013. The net carrying value of these retired units is recorded in regulatory assets as unrecovered plant and is being amortized over the units' previously estimated remaining useful lives as approved by the SCPSC. See also Note 1.

SCE&G's DSM Programs for electric customers provide for an annual rider, approved by the SCPSC, to allow recovery of the costs and net lost margin revenues associated with the DSM Programs, along with an incentive for investing in such programs. SCE&G submits annual filings regarding the DSM Programs, net lost margin revenues, program costs, incentives and net program benefits. The SCPSC approved the following rate changes pursuant to annual DSM Programs filings, which went into effect as indicated:

Year
 
Effective
 
Amount
2014
 
First billing cycle of May
 
$15.4 million
2013
 
First billing cycle of May
 
$16.9 million
2012
 
First billing cycle of May
 
$19.6 million

Other activity related to SCE&G’s DSM Programs is as follows:

In May 2013 the SCPSC ordered the deferral as a regulatory asset of one-half of net lost margin revenues and provided for their recovery over a 12-month period beginning with the first billing cycle in May 2014.

In November 2013 the SCPSC approved SCE&G’s continued use of DSM Programs for another six years, including use of the rate rider mechanism and a revised portfolio of DSM Programs.

By order dated April 30, 2014, in response to SCE&G’s annual DSM Programs filing, the SCPSC approved SCE&G’s request to (1) recover one-half of the balance of allowable costs beginning with bills rendered on and after the first billing cycle of May 2014 and to recover the remaining balance of allowable costs beginning with bills rendered on and after the first billing cycle of May 2015, (2) utilize approximately $17.8 million of the gains from the recent settlement of certain interest rate derivative instruments, previously deferred as regulatory liabilities, to offset a portion of the net lost margin revenues component of SCE&G’s DSM Programs rider, and (3) apply $5.0 million of its storm damage reserve and a portion of the gains from the recent settlement of certain interest rate derivative instruments, currently estimated to be $5.5 million , to the remaining balance of deferred net lost margin revenue as of April 30, 2014, deferred within

43

Table of Contents

regulatory assets resulting from the May 2013 order previously described. In addition, the SCPSC, upon recommendation of the ORS, reduced by 25%, or $6.6 million , the amount of net lost margin revenues SCE&G expects to experience over the 12 month period beginning with the first billing cycle of May 2014, and ordered that the $6.6 million be applied to decrease the amount of program costs deferred for recovery.  Actual net lost magin revenues not collected in the current DSM Programs rate rider is subject to true up in the following program year.

Electric – BLRA
    
Under the BLRA, SCE&G is allowed to file revised rates with the SCPSC each year to incorporate the financing cost of any incremental construction work in progress incurred for new nuclear generation. Requested rate adjustments are based on SCE&G’s updated cost of debt and capital structure and on an allowed return on common equity of 11.0%. The SCPSC has approved the following rate changes under the BLRA effective for bills rendered on and after October 30 in the years indicated:
Year
 
Action
 
Amount
2013
 
2.9
%
Increase
 
$67.2 million
2012
 
2.3
%
Increase
 
$52.1 million

Gas
  
The RSA is designed to reduce the volatility of costs charged to customers by allowing for timely recovery of the costs that regulated utilities incur related to natural gas infrastructure. The SCPSC has approved the following rate changes pursuant to annual RSA filings effective with the first billing cycle of November in the years indicated:
Year
 
Action
 
Amount
2013
 
  No change
 
-
2012
 
2.1
%
Increase
 
$7.5 million

SCE&G's natural gas tariffs include a PGA clause that provides for the recovery of actual gas costs incurred. SCE&G's gas rates are calculated using a methodology which may adjust the cost of gas monthly based on a 12-month rolling average, and its gas purchasing policies and practices are reviewed annually by the SCPSC. The annual review conducted for the 12-month period ended July 31, 2013 resulted in the SCPSC issuing an order finding that SCE&G's gas purchasing policies and practices during the review period were reasonable and prudent.

Regulatory Assets and Regulatory Liabilities
 
Consolidated SCE&G has significant cost-based, rate-regulated operations and recognizes in its financial statements certain revenues and expenses in different time periods than do enterprises that are not rate-regulated.  As a result, Consolidated SCE&G has recorded regulatory assets and regulatory liabilities, which are summarized in the following tables.  Other than unrecovered plant, substantially all regulatory assets are either explicitly excluded from rate base or are effectively excluded from rate base due to their being offset by related liabilities.
Millions of dollars
 
March 31,
2014
 
December 31,
2013
Regulatory Assets:
 
 

 
 

Accumulated deferred income taxes
 
$
254

 
$
256

Under collections – electric fuel adjustment clause
 
36

 
18

Environmental remediation costs
 
37

 
37

AROs and related funding
 
354

 
350

Franchise agreements
 
30

 
31

Deferred employee benefit plan costs
 
212

 
215

Deferred losses on interest rate derivatives
 
210

 
124

Deferred pollution control costs
 
37

 
37

Unrecovered plant
 
143

 
145

DSM Programs
 
56

 
51

Other
 
40

 
39

Total Regulatory Assets
 
$
1,409

 
$
1,303


44

Table of Contents

Regulatory Liabilities:
 
 
 
 
Accumulated deferred income taxes
 
$
18

 
19

Asset removal costs
 
501

 
495

Storm damage reserve
 
14

 
27

Deferred gains on interest rate derivatives
 
106

 
181

Planned major maintenance
 
5

 
10

Total Regulatory Liabilities
 
$
644

 
$
732


Accumulated deferred income tax liabilities that arose from utility operations that have not been included in customer rates are recorded as a regulatory asset.  Substantially all of these regulatory assets relate to depreciation and are expected to be recovered over the remaining lives of the related property which may range up to approximately 70 years.  Similarly, accumulated deferred income tax assets arising from deferred investment tax credits are recorded as a regulatory liability.
 
Under-collections - electric fuel adjustment clause represent amounts due from customers pursuant to the fuel adjustment clause as approved by the SCPSC during annual hearings which are not expected to be recovered in retail electric rates within 12 months. 

Environmental remediation costs represent costs associated with the assessment and clean-up of sites currently or formerly owned by SCE&G and are expected to be recovered over periods of up to approximately 26 years.
 
ARO and related funding represents the regulatory asset associated with the legal obligation to decommission and dismantle Summer Station and conditional AROs related to generation, transmission and distribution properties.  These regulatory assets are expected to be recovered over the related property lives and periods of decommissioning which may range up to approximately 90 years.
 
Franchise agreements represent costs associated with electric and gas franchise agreements with the cities of Charleston and Columbia, South Carolina. Based on an SCPSC order, SCE&G is recovering these amounts through cost of service rates through 2021.

Employee benefit plan costs of the regulated utilities have historically been recovered as they have been recorded under generally accepted accounting principles. Deferred employee benefit plan costs represent amounts of pension and other postretirement benefit costs which were accrued as liabilities and treated as regulatory assets pursuant to FERC guidance, as well as costs deferred pursuant to specific SCPSC regulatory orders. In connection with a December 2012 rate order, approximately $63 million of deferred pension costs for electric operations are to be recovered through utility rates over approximately 30 years. In connection with the October 2013 RSA order, approximately $14 million of deferred pension costs for gas operations are to be recovered through utility rates over approximately 14 years. The remainder of the deferred benefit costs are expected to be recovered through utility rates, primarily over average service periods of participating employees, or approximately 12 years.
 
Planned major maintenance related to certain fossil fueled turbine/generation equipment and nuclear refueling outages is accrued in periods other than when incurred, as approved pursuant to specific SCPSC orders.  SCE&G collects and accrues $18.4 million annually for fossil fueled turbine/generation equipment maintenance and collects and accrues $16.8 million annually for nuclear-related refueling charges.
 
Deferred losses or gains on interest rate derivatives represent (i) the effective portions of changes in fair value and payments made or received upon settlement of certain interest rate derivatives designated as cash flow hedges and (ii) the changes in fair value and payments received upon settlement of certain other interest rate derivatives not so designated. The amounts recorded with respect to (i) are expected to be amortized to interest expense over the lives of the underlying debt, up to approximately 30 years. The amounts recorded with respect to (ii) are expected to be similarly amortized to interest expense except when, in the case of deferred gains, such amounts are applied otherwise at the direction of the SCPSC. Also, as discussed at Rate Matters - Electric - Base Rates, certain of these deferred amounts will be applied to offset unrecorded net lost margin revenues related to DSM Programs.
 
Deferred pollution control costs represent deferred depreciation and operating and maintenance costs associated with the scrubbers installed at certain coal-fired generating plants pursuant to specific regulatory orders.  Such costs are being recovered through utility rates through 2045. 
 

45

Table of Contents

Unrecovered plant represents the carrying value of coal-fired generating units, including related materials and supplies inventory, retired from service prior to being fully depreciated. Pursuant to SCPSC approval, SCE&G is amortizing these amounts through cost of service rates over the units' previous estimated remaining useful lives through 2025. Unamortized amounts are included in rate base and are earning a current return.

DSM Programs represents deferred costs and certain unrecovered net lost margin revenues associated with such programs at SCE&G.  Deferred costs are currently being recovered over five years through a SCPSC approved rider.  Unrecovered net lost margin revenues are to be recovered over periods not to exceed 24 months from date of deferral.  See Rate Matters - Electric - Base Rates above for details regarding a 2014 filing with the SCPSC regarding recovery of these deferred costs and unrecovered net lost margin revenues.

Various other regulatory assets are expected to be recovered in rates over periods of up to approximately 30 years.
 
Asset removal costs represent estimated net collections through depreciation rates of amounts to be incurred for the removal of assets in the future.
 
The storm damage reserve represents an SCPSC-approved collection through SCE&G electric rates, capped at $100 million, which can be applied to offset incremental storm damage costs in excess of $2.5 million in a calendar year. Pursuant to specific regulatory orders, SCE&G has suspended storm damage reserve collection through rates indefinitely. During the first quarter of 2014, $13.6 million of the reserve was applied to offset incremental storm damage costs. Also, as discussed at Rate Matters - Electric - Base Rates, in April 2014 $5.0 million of the reserve will be applied to offset unrecovered net lost margin revenues related to DSM Programs.

The SCPSC or the FERC has reviewed and approved through specific orders most of the items shown as regulatory assets. Other regulatory assets include, but are not limited to, certain costs which have not been approved for recovery by the SCPSC or by the FERC. In recording such costs as regulatory assets, management believes the costs will be allowable under existing rate-making concepts that are embodied in rate orders received by SCE&G. The costs are currently not being recovered, but are expected to be recovered through rates in future periods. In the future, as a result of deregulation or other changes in the regulatory environment or changes in accounting requirements, Consolidated SCE&G could be required to write off its regulatory assets and liabilities. Such an event could have a material effect on Consolidated SCE&G's results of operations, liquidity or financial position in the period the write-off would be recorded.

3.
EQUITY
 
Changes in common equity during the three months ended March 31, 2014 and 2013 were as follows:
Millions
 
Common Stock
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interest
 
Total Equity
Balance at January 1, 2014
 
$
2,479

 
$
1,896

 
$
(3
)
 
$
117

 
$
4,489

Earnings available to common shareholder
 
 
 
123

 
 
 
3

 
126

Deferred cost of employee benefit plans
 
 
 
 
 

 
 
 

Total Comprehensive Income
 
 
 
123

 

 
3

 
126

Capital contributions from parent
 
20

 
 
 
 
 
 
 
20

Cash dividend declared
 
 
 
(62
)
 
 
 
(2
)
 
(64
)
Balance at March 31, 2014
 
$
2,499

 
$
1,957

 
$
(3
)
 
$
118

 
$
4,571

 
 
 
 
 
 
 
 
 
 
 
Balance at January 1, 2013
 
$
2,167

 
$
1,766

 
$
(4
)
 
$
114

 
$
4,043

Earnings available to common shareholder
 
 
 
89

 
 
 
3

 
92

Deferred cost of employee benefit plans
 
 
 
 
 

 
 
 

Total Comprehensive Income
 
 
 
89

 

 
3

 
92

Capital contributions from parent
 
221

 
 
 
 
 
 
 
221

Cash dividend declared
 
 
 
(62
)
 
 
 
(2
)
 
(64
)
Balance at March 31, 2013
 
$
2,388

 
$
1,793

 
$
(4
)
 
$
115

 
$
4,292

 

46

Table of Contents

SCE&G had 50 million shares of common stock authorized as of March 31, 2014 and December 31, 2013, of which 40.3 million were issued and outstanding during all periods presented. SCE&G had 20 million shares of preferred stock authorized as of March 31, 2014 and December 31, 2013, of which 1,000 shares at a stated value of $100,000 were issued and outstanding during all periods presented. All issued and outstanding shares of SCE&G's common and preferred stock are held by SCANA.

Reclassifications from AOCI into earnings of the amortization of deferred employee benefit costs were not significant for any period presented.

4. LONG-TERM DEBT AND LIQUIDITY
 
Long-term Debt

In March 2013, SCE&G entered into a contract for the purchase of nuclear fuel totaling $100 million and payable in 2016.
    
In January 2013, JEDA issued at a premium, for the benefit of SCE&G,$39.5 million of 4.00% tax-exempt industrial revenue bonds due February 1, 2028, and $14.7 million of 3.63% tax-exempt industrial revenue bonds due February 1, 2033. Proceeds from these sales were loaned by JEDA to SCE&G and, together with other available funds, were used to redeem prior to maturity 56.9 million of 5.2% industrial revenue bonds due November 1, 2027.

 Substantially all of Consolidated SCE&G’s electric utility plant is pledged as collateral in connection with long-term debt.

Liquidity
 
SCE&G (including Fuel Company) had available the following committed LOC, and had outstanding the following LOC advances, commercial paper, and LOC-supported letter of credit obligations:
Millions of dollars
 
March 31,
2014
 
December 31,
2013
Lines of credit:
 
 
 
 
Total committed long-term
 
$
1,400

 
$
1,400

Outstanding commercial paper (270 or fewer days)
 
457

 
$
251

Weighted average interest rate
 
0.26
%
 
0.27
%
Letters of credit supported by LOC
 
$
0.3

 
$
0.3

Available
 
$
943

 
$
1,149

 
SCE&G and Fuel Company are parties to five-year credit agreements in the amount of $1.2 billion (of which $500 million relates to Fuel Company). In addition, SCE&G is a party to a three-year credit agreement in the amount of $200 million. The five-year agreements expire in October 2018, and the three-year agreement expires in October 2016. These credit agreements are used for general corporate purposes, including liquidity support for each company’s commercial paper program and working capital needs and, in the case of Fuel Company, to finance or refinance the purchase of nuclear fuel, certain fossil fuels, and emission and other environmental allowances. These committed long-term facilities are revolving lines of credit under credit agreements with a syndicate of banks. Wells Fargo Bank, National Association, Bank of America, N. A. and Morgan Stanley Bank, N.A. each provide 10.7% of the aggregate $1.4 billion credit facilities, JPMorgan Chase Bank, N.A., Mizuho Corporate Bank, Ltd., TD Bank N.A., Credit Suisse AG, Cayman Islands Branch and UBS Loan Finance LLC each provide 8.9% and Branch Banking and Trust Company, Union Bank, N.A. and U.S. Bank National Association each provide 6.3%Two other banks provide the remaining support. Consolidated SCE&G pays fees to the banks as compensation for maintaining the committed lines of credit. Such fees were not material in any period presented.

Consolidated SCE&G is obligated with respect to an aggregate of $67.8 million of industrial revenue bonds which are secured by letters of credit issued by Branch Banking and Trust Company.  The letters of credit expire, subject to renewal, in the fourth quarter of 2014.

Consolidated SCE&G participates in a utility money pool. Money pool borrowings and investments bear interest at short-term market rates. Consolidated SCE&G’s interest income and expense from money pool transactions were not

47

Table of Contents

significant for any period presented. At March 31, 2014 and December 31, 2013, Consolidated SCE&G had outstanding money pool borrowings due to an affiliate of $33.8 million and $27.3 million, respectively.

5.
INCOME TAXES
 
During 2013, SCANA amended certain of its consolidated tax returns to claim certain tax-defined research and development deductions and credits. In connection with these filings, Consolidated SCE&G recorded an unrecognized tax benefit of $3.0 million. If recognized, this tax benefit would affect the Company’s effective tax rate. No other material changes in the status of Consolidated SCE&G’s tax positions have occurred through March 31, 2014.

                Consolidated SCE&G recognizes interest accrued related to unrecognized tax benefits within interest expense and recognizes tax penalties within other expenses.  Consolidated SCE&G has not recorded interest expense or penalties associated with the 2013 uncertain tax position.

Additionally, during the third quarter of 2013, the IRS issued final regulations regarding the capitalization of certain costs for income tax purposes and re-proposed certain other related regulations (collectively referred to as tangible personal property regulations).  Related IRS revenue procedures were then issued on January 24, 2014. These regulations did not and are not expected to have a material impact on Consolidated SCE&G's financial position, results of operations or cash flows.

6.
DERIVATIVE FINANCIAL INSTRUMENTS
 
Consolidated SCE&G recognizes all derivative instruments as either assets or liabilities in the statement of financial position and measures those instruments at fair value.  Consolidated SCE&G recognizes changes in the fair value of derivative instruments either in earnings or within regulatory assets or regulatory liabilities, depending upon the intended use of the derivative and the resulting designation. 

Policies and procedures and risk limits are established to control the level of market, credit, liquidity and operational and administrative risks assumed by Consolidated SCE&G.  SCANA’s Board of Directors has delegated to a Risk Management Committee the authority to set risk limits, establish policies and procedures for risk management and measurement, and oversee and review the risk management process and infrastructure for SCANA and each of its subsidiaries, including Consolidated SCE&G.  The Risk Management Committee, which is comprised of certain officers, including the Consolidated SCE&G’s Risk Management Officer and senior officers, apprises the Audit Committee of the Board of Directors with regard to the management of risk and brings to the Audit Committee’s attention significant areas of concern.  Written policies define the physical and financial transactions that are approved, as well as the authorization requirements and limits for transactions.
 
Interest Rate Swaps
 
Consolidated SCE&G synthetically converts variable rate debt to fixed rate debt using swaps that are designated as cash flow hedges. Periodic payments to or receipts from swap counterparties related to these derivatives are recorded within interest expense.
 
In anticipation of the issuance of debt, Consolidated SCE&G may use treasury rate lock or forward starting swap agreements. Pursuant to regulatory orders, interest rate derivatives entered into by SCE&G after October 2013 are no longer designated as cash flow hedges, and fair value changes and settlement amounts are recorded as regulatory assets and liabilities. Upon settlement, losses on swaps will be amortized over the lives of related debt issuances, and gains may be applied to under-collected fuel, be amortized to interest expense or applied as otherwise directed by the SCPSC.

Cash payments made or received upon termination of these financial instruments are classified as investing activities for cash flow statement purposes.

Quantitative Disclosures Related to Derivatives
 
Consolidated SCE&G was a party to interest rate swaps designated as cash flow hedges with an aggregate notional amount of $36.4 million at March 31, 2014 and $36.4 million at December 31, 2013. Consolidated SCE&G was party to interest rate swaps not designated as cash flow hedges with an aggregate notional amount of $1.3 billion at March 31, 2014 and $1.3 billion at December 31, 2013, respectively.
 
The fair value of interest rate derivatives was reflected in the condensed consolidated balance sheet as follows:
 
 
Fair Values of Derivative Instruments
 
 
Asset Derivatives
 
Liability Derivatives
 
 
Balance Sheet
 
Fair
 
Balance Sheet
 
Fair
Millions of dollars
 
Location 
 
Value
 
Location 
 
Value
As of March 31, 2014
 
 
 
 
 
 
 
 
Derivatives designated as hedging instruments
 
 
 
 
 
 
 
 
Interest rate contracts
 
 
 


 
Derivative financial instruments
 
$
1

 
 
 
 


 
Other deferred credits and other liabilities
 
2

Total
 
 
 


 
 
 
$
3

 
 
 
 
 
 
 
 
 
Derivatives not designated as hedging instruments
 
 
 
 
 
 
 
 
Interest rate contracts
 
Other deferred debits and other assets
 
$
2

 
Derivative financial instruments
 
$
40

 
 
 
 


 
Other deferred credits and other liabilities
 
43

Total
 
 
 
$
2

 
 
 
$
83

 
 
 
 
 
 
 
 
 
As of December 31, 2013
 
 
 
 

 
 
 
 

Derivatives designated as hedging instruments
 
 
 
 

 
 
 
 

Interest rate contracts
 
 
 


 
Derivative financial instruments
 
$
1

Total
 
 
 


 
 
 
$
1

 
 
 
 
 
 
 
 
 
Derivatives not designated as hedging instruments
 
 
 
 
 
 
 
 
Interest rate contracts
 
Prepayments and other
 
$
13

 
Derivative financial instruments
 
$
1

 
 
Other deferred debits and other assets
 
19

 
 
 
 
Total
 
 
 
$
32

 
 
 
$
1

 
 
 
 
 
 
 
 
 
     
The effect of derivative instruments on the condensed consolidated statement of income is as follows:
Derivatives in Cash Flow Hedging Relationships
 
Gain (Loss) Deferred in Regulatory Accounts
 
 
 
Loss Reclassified from Deferred Accounts into Income
 
 
 
 
 
 
(Effective Portion)
 
 
 
(Effective Portion)
Millions of dollars
 
2014

 
2013

 
Location
 
2014

 
2013

Three Months Ended March 31,
 
 
 
 
 
 
 
 
 
 
Interest rate contracts
 
$
(3
)
 
$
35

 
Interest expense
 
$
(1
)
 
$
(1
)

Hedge Ineffectiveness

Other gains (losses) recognized in income representing ineffectiveness on interest rate hedges designated as cash flow hedges were insignificant in each of the three months ended March 31, 2014 and 2013, respectively.

Derivatives not designated as Hedging Instruments
 
 
 
 
Millions of dollars
 
Loss Deferred in Regulatory Accounts
 
Gain Reclassified from Deferred Accounts into Income
 
 
 
 
Location
 
Amount
Three Months Ended March 31, 2014
 
 
 
 
 
 
Interest rate contracts
 
$
(112
)
 
Other Income
 
$


No losses were deferred in regulatory accounts, and no amounts were reclassified from deferred accounts into income, for the three months ended March 31, 2013. As of March 31, 2014, Consolidated SCE&G expects that during the next 12 months reclassifications from other current liabilities and deferred regulatory accounts to earnings arising from derivatives not designated as hedges will include $67.8 million as an increase to other income. The effect of this increase on net income will be entirely offset by the recovery of certain undercollected fuel costs and net lost margin revenues from DSM Programs as further described in Note 2.

Credit Risk Considerations
 
Consolidated SCE&G limits credit risk in its derivatives activities by assessing the creditworthiness of potential counterparties before entering into transactions with them and continuing to evaluate their creditworthiness on an ongoing basis. In this regard, Consolidated SCE&G uses credit ratings provided by credit rating agencies and current market-based qualitative and quantitative data as well as financial statements, to assess the financial health of counterparties on an ongoing basis. Consolidated SCE&G uses standardized master agreements which may include collateral requirements. These master agreements permit the netting of cash flows associated with a single counterparty. Cash, letters of credit and parental/affiliate guarantees may be obtained as security from counterparties in order to mitigate credit risk. The collateral agreements permit the secured party to demand the posting of cash or letters of credit in the event an exposure exceeds the established threshold. The threshold represents an unsecured credit limit which may be supported by a parental/affiliate guaranty, as determined in accordance with Consolidated SCE&G's credit policies and due diligence. In addition, collateral agreements allow for the termination and liquidation of all positions in the event of a failure or inability to post collateral.

Certain of Consolidated SCE&G’s derivative instruments contain contingent provisions that may require Consolidated SCE&G to provide collateral upon the occurrence of specific events, primarily credit downgrades.  As of March 31, 2014 and December 31, 2013, Consolidated SCE&G has posted $4.1 million and $1.5 million, respectively, of collateral related to derivatives with contingent provisions that were in a net liability position.  Collateral related to the positions expected to close in the next 12 months are recorded in Prepayments and other on the condensed consolidated balance sheets. Collateral related to noncurrent positions is recorded in Other within Deferred Debits and Other Assets on the condensed consolidated balance sheets. If all of the contingent features underlying these instruments had been fully triggered as of March 31, 2014 and December 31, 2013, Consolidated SCE&G could have been required to post an additional $80.1 million and $0.0 million, respectively, of collateral with its counterparties.  The aggregate fair value of all derivative instruments with contingent provisions that are in a net liability position as of March 31, 2014 and December 31, 2013 is $84.2 million and $1.0 million, respectively.

In addition, as of March 31, 2014 and December 31, 2013, Consolidated SCE&G has collected no cash collateral related to interest rate derivatives with contingent provisions that are in a net asset position. If all the contingent features underlying these instruments were fully triggered as of March 31, 2014 and December 31, 2013, Consolidated SCE&G could request $0.0 million and $31.7 million, respectively, of cash collateral from its counterparties. The aggregate fair value of all derivative instruments with contingent provisions that are in a net asset position as of March 31, 2014 and December 31, 2013 is $0.0 million and $31.7 million, respectively.

Information related to Consolidated SCE&G's derivative assets follows:
 
 
 
 
 
 
 
Gross Amounts Not Offset in the Statement of Financial Position
 
 
Millions of dollars
Gross Amounts of Recognized Assets
 
Gross Amounts Offset in the Statement of Financial Position
 
Net Amounts Presented in the Statement of Financial Position
 
Financial Instruments
 
Cash Collateral Received
 
Net Amount
As of March 31, 2014
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
2

 

 
$
2

 
$
(2
)
 

 

 
 
 
 
 
 
 
 
 
 
 
 
Balance Sheet Location
Other deferred debits and other assets
 
$
2

 
 
 
 
 
 
 
Total
 
 
 
$
2

 
 
 
 
 
 
As of December 31, 2013
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
32

 

 
$
32

 
$
(1
)
 

 
$
31

 
 
 
 
 
 
 
 
 
 
 
 
Balance Sheet Location
Prepayments and other
 
$
13

 
 
 
 
 
 
 
Other deferred debits and other assets
 
19

 
 
 
 
 
 
 
Total
 
 
 
$
32

 
 
 
 
 
 

Information related to Consolidated SCE&G's derivative liabilities follows:
 
 
 
 
 
 
 
Gross Amounts Not Offset in the Statement of Financial Position
 
 
Millions of dollars
Gross Amounts of Recognized Liabilities
 
Gross Amounts Offset in the Statement of Financial Position
 
Net Amounts Presented in the Statement of Financial Position
 
Financial Instruments
 
Cash Collateral Posted
 
Net Amount
As of March 31, 2014
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
86

 

 
$
86

 
$
(2
)
 
$
(4
)
 
$
80

 
 
 
 
 
 
 
 
 
 
 
 
Balance Sheet Location
Derivative financial instruments
 
$
41

 
 
 
 
 
 
 
Other deferred credits and other liabilities
 
45

 
 
 
 
 
 
 
Total
 
 
 
$
86

 
 
 
 
 
 
As of December 31, 2013
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
2

 

 
$
2

 
$
(1
)
 
$
(1
)
 

 
 
 
 
 
 
 
 
 
 
 
 
Balance Sheet Location
Derivative financial instruments
 
$
2

 
 
 
 
 
 
 
Total
 
 
 
$
2

 
 
 
 
 
 


48

Table of Contents

7.
FAIR VALUE MEASUREMENTS, INCLUDING DERIVATIVES
 
Consolidated SCE&G’s interest rate swap agreements are valued using discounted cash flow models with independently sourced data.  Fair value Level 2 measurements were as follows: 
Millions of dollars
 
March 31, 2014
 
December 31, 2013

Assets -
 
Interest rate contracts
 
$
2

 
$
32

Liabilities -
 
Interest rate contracts
 
86

 
2

 
There were no Level 1 or Level 3 fair value measurements for either period presented, and there were no transfers of fair value amounts into or out of Levels 1, 2 or 3 during the periods presented.
 
Financial instruments for which the carrying amount may not equal estimated fair value at March 31, 2014 and December 31, 2013 were as follows:
 
 
March 31, 2014
 
December 31, 2013
Millions of dollars
 
Carrying
Amount
 
Estimated
Fair
Value
 
Carrying
Amount
 
Estimated
Fair
Value
Long-term debt
 
$
4,047.6

 
$
4,574.2

 
$
4,054.9

 
$
4,433.0


Fair values of long-term debt instruments are based on net present value calculations using independently sourced market data that incorporate a developed discount rate using similarly rated long-term debt, along with benchmark interest rates.  As such, the aggregate fair values presented above are considered to be Level 2.  Early settlement of long-term debt may not be possible or may not be considered prudent.
 
Carrying values of short-term borrowings approximate fair value, and are based on quoted prices from dealers in the commercial paper market. The resulting fair value is considered to be Level 2.

8.
EMPLOYEE BENEFIT PLANS
 
Pension and Other Postretirement Benefit Plans
 
Consolidated SCE&G participates in SCANA’s noncontributory defined benefit pension plan, which covers substantially all regular, full-time employees, and also participates in SCANA’s unfunded postretirement health care and life insurance programs, which provide benefits to active and retired employees.  Components of net periodic benefit cost recorded by Consolidated SCE&G were as follows:
 
 
Pension Benefits
 
Other Postretirement Benefits
Millions of dollars
 
2014
 
2013
 
2014
 
2013
Three months ended March 31,
 
 

 
 

 
 

 
 

Service cost
 
$
4.0

 
$
4.8

 
$
1.0

 
$
1.2

Interest cost
 
8.6

 
8.0

 
2.4

 
2.2

Expected return on assets
 
(14.2
)
 
(13.0
)
 

 

Prior service cost amortization
 
0.9

 
1.4

 
0.1

 
0.2

Amortization of actuarial losses
 
1.1

 
4.6

 
0.1

 
0.6

Net periodic benefit cost
 
$
0.4

 
$
5.8

 
$
3.6

 
$
4.2


No significant contribution to the pension trust is expected for the foreseeable future, nor is a limitation on benefit payments expected to apply. SCE&G recovers current pension costs through either a rate rider that may be adjusted annually for retail electric operations or through cost of service rates for gas operations. Certain pension costs arising prior to 2013 were deferred for future recovery under regulatory orders as discussed in Note 2.


49

Table of Contents

9.
COMMITMENTS AND CONTINGENCIES

 Nuclear Insurance

Under Price-Anderson, SCE&G (for itself and on behalf of Santee Cooper, a one-third owner of Summer Station Unit 1) maintains agreements of indemnity with the NRC that, together with private insurance, cover third-party liability arising from any nuclear incident occurring at SCE&G's nuclear power plant. Price-Anderson provides funds up to $13.6 billion for public liability claims that could arise from a single nuclear incident. Each nuclear plant is insured against this liability to a maximum of $375 million by ANI with the remaining coverage provided by a mandatory program of deferred premiums that could be assessed, after a nuclear incident, against all owners of commercial nuclear reactors. Each reactor licensee is currently liable for up to $127.3 million per reactor owned for each nuclear incident occurring at any reactor in the United States, provided that not more than $18.9 million of the liability per reactor would be assessed per year.  SCE&G’s maximum assessment, based on its two-thirds ownership of Summer Station Unit 1, would be $84.8 million per incident, but not more than $12.6 million per year. Both the maximum assessment per reactor and the maximum yearly assessment are adjusted for inflation at least every five years.
 
SCE&G currently maintains insurance policies (for itself and on behalf of Santee Cooper) with NEIL.  The policies provide coverage to Summer Station Unit 1 for property damage and outage costs up to $2.75 billion resulting from an event of nuclear origin. In addition, a builder's risk insurance policy has been purchased from NEIL for the construction of the New Units. This policy provides the owners of the New Units up to $500 million in limits of accidental property damage occurring during construction. The NEIL policies, in the aggregate, are subject to a maximum loss of $2.75 billion for any single loss occurrence. All of the NEIL policies permit retrospective assessments under certain conditions to cover insurer’s losses.  Based on the current annual premium, SCE&G’s portion of the retrospective premium assessment would not exceed $41.6 million.
 
To the extent that insurable claims for property damage, decontamination, repair and replacement and other costs and expenses arising from a nuclear incident at Summer Station Unit 1 exceed the policy limits of insurance, or to the extent such insurance becomes unavailable in the future, and to the extent that SCE&G's rates would not recover the cost of any purchased replacement power, SCE&G will retain the risk of loss as a self-insurer.  SCE&G has no reason to anticipate a serious nuclear incident.  However, if such an incident were to occur, it likely would have a material impact on Consolidated SCE&G’s results of operations, cash flows and financial position.

New Nuclear Construction

SCE&G, on behalf of itself and as agent for Santee Cooper, has contracted with the Consortium for the design and construction of the New Units at the site of Summer Station.  SCE&G's share of the estimated cash outlays (future value, excluding AFC) totals approximately $5.4 billion for plant and related transmission infrastructure costs, and is projected based on historical one-year and five-year escalation rates as required by the SCPSC.

SCE&G's current ownership share in the New Units is 55%. Under an agreement signed in January 2014 (and subject to customary closing conditions, including necessary regulatory approvals), SCE&G has agreed to acquire an additional 5% ownership in the New Units from Santee Cooper. Under the terms of this agreement SCE&G will acquire a 1% ownership interest in the New Units at the commercial operation date of Unit 2, will acquire an additional 2% ownership interest no later than the first anniversary of such commercial operation date, and will acquire the final 2% no later than the second anniversary of such commercial operation date. Under the terms of the agreement SCE&G has agreed to pay an amount equal to Santee Cooper's actual cost of the percentage conveyed as of the date of conveyance, which SCE&G estimates will be approximately $500 million for the entire 5% interest. In addition, the agreement provides that Santee Cooper will not transfer any of its remaining interest in the New Units to third parties until the New Units are complete. This transaction will not affect the payment obligations between the parties during construction for the New Units, nor is it anticipated that the payments would be reflected in a revised rates filing under the BLRA.

Under the BLRA, the SCPSC has approved, among other things, the construction milestone schedule and capital costs estimates schedule for the New Units. The effect of this approval is that it constitutes a final and binding determination that the New Units are used and useful for utility purposes, and that the capital costs associated with the New Units are prudent utility costs and expenses and are properly included in rates, so long as the New Units are constructed or are being constructed within the parameters of the approved construction milestone schedule, including specified contingencies, and the approved capital costs estimates schedule. The BLRA provides that SCE&G may apply to the SCPSC annually for an order to recover through revised rates SCE&G’s weighted average cost of capital applied to all or part of the outstanding balance of construction work in progress concerning the New Units. Such annual rate changes are described in Note 2.


50

Table of Contents

The parties to the EPC Contract have established both informal and formal dispute resolution procedures in order to resolve issues that arise during the course of constructing a project of this magnitude.  During the course of activities under the EPC Contract, issues have materialized that have impacted the project budget and schedule. Claims by the Consortium specifically relating to COL delays, design modifications of the shield building and certain pre-fabricated structural modules for the New Units and unanticipated rock conditions at the site which resulted in assertions of contractual entitlement to recover additional costs have been resolved. SCE&G expects to resolve any additional disputes through both the informal and formal procedures and anticipates that any additional costs that arise through such dispute resolution processes, as well as other costs identified from time to time, will be recoverable through rates.

The substantial completion dates currently approved by the SCPSC for Units 2 and 3 are March 15, 2017 and May 15, 2018. The SCPSC has also approved an 18-month contingency period beyond each of these dates.

In November 2012, the SCPSC approved a petition by SCE&G under the BLRA for an updated construction milestone schedule and additional updated capital costs for the New Units. In addition, the SCPSC approved revised substantial completion dates for the New Units based on the March 30, 2012 issuance of the COL and the amounts agreed upon by SCE&G and the Consortium in July 2012 to resolve claims by the Consortium for costs related to COL delays, design modifications of the shield building and certain pre-fabricated structural modules for the New Units and unanticipated rock conditions at the site. Immediately thereafter, two parties filed separate petitions requesting that the SCPSC reconsider its order, and on December 12, 2012, the SCPSC denied both petitions.  In March 2013, both parties appealed the SCPSC's order to the South Carolina Supreme Court, contending that the SCPSC erred in granting approval of the updated capital costs for the New Units. The South Carolina Supreme Court heard arguments related to those appeals on April 16, 2014.  SCE&G is unable to predict the outcome of these appeals.

The Consortium has experienced delays in the schedule for fabrication and delivery of sub-modules for the New Units. The fabrication and delivery of sub-modules are a focus area of the Consortium, including sub-modules for module CA20, which is part of the auxiliary building, and CA01, which houses components inside the containment vessel. Modules CA20 and CA01 are considered critical path items for both New Units. All sub-modules for CA20 have been received on site and its assembly is underway. CA20 is expected to be ready for placement on the nuclear island of Unit 2 in May 2014. In addition, the delivery schedule of sub-modules for CA01 is expected to support completion of on-site fabrication to allow it to be ready for placement on the nuclear island of Unit 2 during the latter half of 2014. With this schedule, the Consortium continues to indicate that the substantial completion of Unit 2 is expected to be late 2017 or the first quarter of 2018 and that the substantial completion of Unit 3 is expected to be approximately 12 months after that of Unit 2. These dates are within the SCPSC-approved 18-month contingency period. SCE&G cannot predict with certainty the extent to which the issue with the sub-modules or the delays in the substantial completion of the New Units will result in increased project costs. However, the preliminary estimate of the delay-related costs associated with SCE&G's share of the New Units is approximately $200 million. SCE&G has not accepted responsibility for any of these delay-related costs and expects to have further discussions with the Consortium regarding such responsibility. Additionally, the EPC Contract provides for liquidated damages in the event of a delay in the completion of the facility, which will also be included in discussions with the Consortium. SCE&G believes its responsibility for any portion of the $200 million estimate should ultimately be substantially less, once all of the relevant factors are considered.

During the fourth quarter of 2013, the Consortium began a full re-baselining of the Unit 2 and Unit 3 construction schedules to incorporate a more detailed evaluation of the engineering and procurement activities necessary to accomplish the schedule and to provide a detailed reassessment of the impact of the revised Unit 2 and Unit 3 schedules on engineering and design resource allocations, procurement, construction work crew efficiencies, and other items. The result will be a revised fully integrated project schedule that will provide detailed information on budget and cost and the timing of specific construction activities and cash flow requirements. SCE&G anticipates that the revised schedule and the cost estimate at completion for all non-firm and fixed scopes of work will be finalized in the latter half of 2014. SCE&G plans to reevaluate and reschedule its owners cost estimates and cash flow requirements in light of the new schedule.

The construction milestone schedule approved by the SCPSC in November 2012 provides for 146 construction milestone dates, which are each subject to an 18-month schedule contingency. As of May 3, 2014, 98 milestones have been completed. The currently scheduled completion dates for 44 of the remaining milestones have been delayed between two and 17 months. If, as a result of the re-baselining of the construction schedules for the New Units, the time period for achieving any of the milestones extends beyond its 18-month schedule contingency and/or the capital costs estimates increase, then SCE&G, as provided for under the BLRA, may petition the SCPSC for an order to update the construction milestone schedule and/or capital costs estimates schedule. The BLRA provides that the SCPSC shall grant the petition for modification if the record justifies a finding that the change is not the result of imprudence by SCE&G.


51

Table of Contents


In addition to the above-described project delays, SCE&G is also aware of financial difficulties at a supplier responsible for certain significant components of the project.  The Consortium is monitoring the potential for disruptions in such equipment fabrication and possible responses.  Any disruptions could impact the project's schedule or costs, and such impacts could be material.

When the NRC issued the COLs for the New Units, two of the conditions that it imposed were requiring inspection and testing of certain components of the New Units' passive cooling system, and requiring the development of strategies to respond to extreme natural events resulting in the loss of power at the New Units.  In addition, the NRC directed the Office of New Reactors to issue to SCE&G an order requiring enhanced, reliable spent fuel pool instrumentation, as well as a request for information related to emergency plant staffing.  These conditions and requirements are responsive to the NRC's Near-Term Task Force report titled “Recommendations for Enhancing Reactor Safety in the 21st Century.”  This report was prepared in the wake of the March 2011 earthquake-generated tsunami, which severely damaged several nuclear generating units and their back-up cooling systems in Japan.  SCE&G continues to evaluate the impact of these conditions and requirements that may be imposed on the construction and operation of the New Units, and prepared and submitted an integrated response plan for the New Units to the NRC in August 2013.  SCE&G cannot predict what additional regulatory or other outcomes may be implemented in the United States, or how such initiatives would impact SCE&G's existing Summer Station or the construction or operation of the New Units.

Subject to a national megawatt capacity limitation, the electricity to be produced by the New Units (advanced nuclear units, as defined) is expected to qualify for nuclear production tax credits under Section 45J of the Internal Revenue Code. Following the pouring of safety-related concrete for each of the New Units’ reactor buildings (March 2013 for Unit 2 and November 2013 for Unit 3), SCE&G has applied to the IRS for its allocations of such national megawatt capacity limitation. The IRS will forward the applications to the DOE for appropriate certification.

Environmental
 
As part of the President's Climate Action Plan and by Presidential Memorandum issued June 25, 2013, the EPA was directed to issue a revised carbon standard for new power plants by re-proposing NSPS under the CAA for emissions of carbon dioxide from newly constructed fossil fuel-fired units. The rule became final on January 8, 2014 and requires all new fossil fuel-fired power plants to meet the carbon dioxide emissions profile of a combined cycle natural gas plant. While most new natural gas plants will not be required to include any new technologies, no new coal-fired plants can be constructed without carbon capture and sequestration capabilities. Consolidated SCE&G is evaluating the final rule, but does not plan to construct new coal-fired units in the foreseeable future. The Memorandum also directed the EPA to issue standards, regulations, or guidelines for existing units by June 1, 2014, to be made final no later than June 1, 2015. Consolidated SCE&G also cannot predict when rules will become final for existing units, if at all, or what conditions they may impose on Consolidated SCE&G, if any. Consolidated SCE&G expects that any costs incurred to comply with GHG emission requirements will be recoverable through rates.

In 2005, the EPA issued the CAIR, which required the District of Columbia and 28 states to reduce nitrogen oxide and sulfur dioxide emissions in order to attain mandated state levels.  CAIR set emission limits to be met in two phases beginning in 2009 and 2015, respectively, for nitrogen oxide and beginning in 2010 and 2015, respectively, for sulfur dioxide.  SCE&G and GENCO determined that additional air quality controls would be needed to meet the CAIR requirements. On July 6, 2011 the EPA issued the CSAPR.  This rule replaced CAIR and the Clean Air Transport Rule proposed in July 2010 and is aimed at addressing power plant emissions that may contribute to air pollution in other states.  CSAPR requires states in the eastern United States to reduce power plant emissions, specifically sulfur dioxide and nitrogen oxide.  On December 30, 2011, the Court of Appeals issued an order staying CSAPR and reinstating CAIR pending resolution of an appeal of CSAPR. On August 21, 2012, the Court of Appeals vacated CSAPR and left CAIR in place. On April 29, 2014, the U. S. Supreme Court reversed the judgment of the Court of Appeals and CSAPR was remanded to the Court of Appeals for further proceedings consistent with the U. S. Supreme Court opinion. Air quality control installations that SCE&G and GENCO have already completed have allowed Consolidated SCE&G to comply with the reinstated CAIR and will also allow it to comply with CSAPR, if reinstated.  Consolidated SCE&G will continue to pursue strategies to comply with all applicable environmental regulations.  Any costs incurred to comply with such regulations are expected to be recoverable through rates.

In April 2012, the EPA's rule containing new standards for mercury and other specified air pollutants became effective.  The rule provides up to four years for facilities to meet the standards, and Consolidated SCE&G's evaluation of the rule is ongoing. Consolidated SCE&G's decision in 2012 to retire certain coal-fired units or convert them to burn natural gas and its project to build the New Units (see Note 1) along with other actions are expected to result in Consolidated SCE&G's

52

Table of Contents

compliance with the EPA's rule.  Any costs incurred to comply with this rule or other rules issued by the EPA in the future are expected to be recoverable through rates.

The CWA provides for the imposition of effluent limitations that require treatment for wastewater discharges. Under the CWA, compliance with applicable limitations is achieved under state-issued NPDES permits. As a facility’s NPDES permit is renewed (every five years), any new effluent limitations would be incorporated. The ELG Rule was published in the Federal Register on June 7, 2013, and is expected to be finalized September 30, 2015. The EPA expects compliance within a three to six year time frame as NPDES permits are renewed.

Additionally, the EPA is expected to issue a rule that modifies requirements for existing cooling water intake structures in 2014. Consolidated SCE&G is conducting studies and is developing or implementing compliance plans for these initiatives. Congress is expected to consider further amendments to the CWA. Such legislation may include toxicity-based standards as well as limitations to mixing zones. These provisions, if passed, could have a material impact on the financial condition, results of operations and cash flows of Consolidated SCE&G. Consolidated SCE&G believes that any additional costs imposed by such regulations would be recoverable through rates.

In response to a federal court order to establish a definite timeline for a CCR rule and subsequent obligation via consent decree, the EPA committed to issue new federal regulations affecting the management and disposal of CCRs, such as ash, by December 19, 2014. Such regulations could result in the treatment of some CCRs as hazardous waste and could impose significant costs to utilities, such as SCE&G and GENCO. While Consolidated SCE&G cannot predict how extensive the regulations will be, Consolidated SCE&G believes that any additional costs imposed by such regulations would be recoverable through rates.

The Nuclear Waste Act required that the United States government accept and permanently dispose of high-level radioactive waste and spent nuclear fuel by January 31, 1998. The Nuclear Waste Act also imposed on utilities the primary responsibility for storage of their spent nuclear fuel until the repository is available. SCE&G entered into a Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste with the DOE in 1983. As of December 31, 2013, the federal government has not accepted any spent fuel from Summer Station Unit 1, and it remains unclear when the repository may become available. SCE&G has on-site spent nuclear fuel storage capability in its existing fuel pool until at least 2017, and is constructing a dry cask storage facility to accommodate the spent nuclear fuel output for the life of Summer Station Unit 1. SCE&G may evaluate other technology as it becomes available.
 
The provisions of CERCLA authorize the EPA to require the clean-up of hazardous waste sites. In addition, the state of South Carolina has similar laws. Consolidated SCE&G maintains an environmental assessment program to identify and evaluate current and former operations sites that could require environmental clean-up. In addition, regulators from the EPA and other federal or state agencies periodically notify Consolidated SCE&G that it may be required to perform or participate in the investigation and remediation of a hazardous waste site. As site assessments are initiated, estimates are made of the amount of expenditures, if any, deemed necessary to investigate and remediate each site. These estimates are refined as additional information becomes available; therefore, actual expenditures may differ significantly from the original estimates. Amounts estimated and accrued to date for site assessments and clean-up relate solely to regulated operations. Such amounts are recorded in regulatory assets and amortized, with recovery provided through rates.
 
SCE&G is responsible for four decommissioned MGP sites in South Carolina which contain residues of byproduct chemicals.  These sites are in various stages of investigation, remediation and monitoring under work plans approved by DHEC and the EPA.  SCE&G anticipates that major remediation activities at all these sites will continue until 2017 and will cost an additional $20.2 million, which is accrued in Other within Deferred Credits and Other Liabilities on the condensed consolidated balance sheet.  SCE&G expects to recover any cost arising from the remediation of MGP sites through rates.  At March 31, 2014, deferred amounts, net of amounts previously recovered through rates and insurance settlements, totaled $36.7 million and are included in regulatory assets.

10.
AFFILIATED TRANSACTIONS
 
CGT transports natural gas to SCE&G to serve retail gas customers and certain electric generation requirements.  Such purchases totaled approximately $5.5 million and $8.4 million for the three months ended March 31, 2014 and 2013, respectively.  SCE&G had approximately $3.3 million and $3.3 million payable to CGT for transportation services at March 31, 2014 and December 31, 2013, respectively. SCE&G had approximately $2.5 million and1.3 million receivable from CGT for transportation services at March 31, 2014 and December 31, 2013, respectively.
 

53

Table of Contents

SCE&G purchases natural gas and related pipeline capacity from SEMI to serve its retail gas customers and certain electric generation requirements.  Such purchases totaled approximately $53.4 million and $42.1 million for the three months ended March 30, 2014 and 2013, respectively.  SCE&G’s payables to SEMI for such purposes were $17.2 million and $12.5 million as of March 31, 2014 and December 31, 2013, respectively.
 
SCE&G owns 40% of Canadys Refined Coal, LLC, which is involved in the manufacturing and sale of refined coal to reduce emissions. SCE&G accounts for this investment using the equity method.  SCE&G’s receivable from this affiliate was $4.4 million at March 31, 2014 and $18.0 million at December 31, 2013.  SCE&G’s payable to this affiliate was $4.4 million at March 31, 2014 and $18.0 million at December 31, 2013.  SCE&G’s total purchases from this affiliate were $39.2 million and $14.3 million for the three months ended March 31, 2014 and 2013, respectively.  SCE&G’s total sales to this affiliate were $39.0 million and $14.3 million for the three months ended March 31, 2014 and 2013, respectively.

SCANA Services provides the following services to Consolidated SCE&G, which are rendered at direct or allocated cost: information systems services, customer services, marketing and sales, human resources, corporate compliance, purchasing, financial services, risk management, public affairs, legal services, investor relations, gas supply and capacity management, strategic planning, general administrative services, and retirement benefits. In addition, SCANA Services processes and pays invoices for Consolidated SCE&G and is reimbursed. Costs for these services were $76.2 million and $78.6 million for the three months ended March 31, 2014 and 2013, respectively. Consolidated SCE&G's payables to SCANA Services for these services were $45.6 million and $49.1 million at March 31, 2014 and December 31, 2013, respectively.
Money pool borrowings from an affiliate are described in Note 4.

11.
SEGMENT OF BUSINESS INFORMATION
 
Consolidated SCE&G’s reportable segments are listed in the following table.  Consolidated SCE&G uses operating income to measure profitability for its regulated operations.  Therefore, earnings available to common shareholder are not allocated to the Electric Operations and Gas Distribution segments.  Intersegment revenues were not significant.

 
 
External
 
Operating
 
Earnings Available to
Millions of dollars
 
Revenue
 
Income
 
Common Shareholder
Three Months Ended March 31, 2014
 
 
 
 
 
 
Electric Operations
 
$
680

 
$
198

 
n/a

Gas Distribution
 
179

 
41

 
n/a

Adjustments/Eliminations
 

 

 
$
123

Consolidated Total
 
$
859

 
$
239

 
$
123


Three Months Ended March 31, 2013
 
 
 
 
 
 
Electric Operations
 
$
585

 
$
153

 
n/a

Gas Distribution
 
143

 
38

 
n/a

Adjustments/Eliminations
 

 

 
$
89

Consolidated Total
 
$
728

 
$
191

 
$
89


 
 
March 31,
 
December 31,
 
 
Segment Assets
 
2014
 
2013
 
 
Electric Operations
 
$
9,542

 
$
9,488

 
 
Gas Distribution
 
692

 
686

 
 
Adjustments/Eliminations
 
2,615

 
2,526

 
 
Consolidated Total
 
$
12,849

 
$
12,700

 
 


54

Table of Contents



ITEM 2.
MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
 
SOUTH CAROLINA ELECTRIC & GAS COMPANY
 
The following discussion should be read in conjunction with Management’s Discussion and Analysis of Financial Condition and Results of Operations appearing in SCE&G’s Annual Report on Form 10-K for the year ended December 31, 2013. 
RESULTS OF OPERATIONS
FOR THE THREE MONTHS ENDED MARCH 31. 2014
AS COMPARED TO THE CORRESPONDING PERIOD IN 2013
 
Net Income
 
Net income for Consolidated SCE&G was as follows:
 
Millions of dollars
 
2014
 
Change
 
2013
Net income
 
$
126.2

 
37.5
%
 
$
91.8


 Net income increased due to higher electric and gas margins.  These margin increases were partially offset by higher operation and maintenance expenses, higher depreciation expense, higher interest cost and higher property taxes, as further described below.
 
Dividends Declared
 
Consolidated SCE&G’s Boards of Directors declared the following dividends on common stock (all of which was held by SCANA) during 2014:
Declaration Date
 
Amount
 
Quarter Ended
 
Payment Date
February 20, 2014
 
$64.3 million
 
March 31, 2014
 
April 1, 2014
April 24, 2014
 
$64.4 million
 
June 30, 2014
 
July 1, 2014
 
Electric Operations 

Electric Operations is comprised of the electric operations of SCE&G, GENCO and Fuel Company.  Electric operations sales margin (including transactions with affiliates) was as follows:
Millions of dollars
 
2014
 
Change
 
2013
Operating revenues
 
$
679.9

 
16.1
%
 
$
585.6

Less: Fuel used in generation
 
213.8

 
13.9
%
 
187.7

          Purchased power
 
25.0

 
*

 
7.0

Margin
 
$
441.1

 
12.8
%
 
$
390.9

* Greater than 100%

Electric margin increased primarily due to the effects of weather of $20.1 million, customer growth and consumption of $13.2 million and base rate increases under the BLRA and DSM Program rider of $16.7 million. Due to the termination of eWNA effective January 1, 2014, electric margin is subject to the effects of weather.

 

55

Table of Contents

Sales volumes (in GWh) related to the electric margin above, by class, were as follows:
Classification
 
2014
 
Change
 
2013
Residential
 
2,151

 
15.8
 %
 
1,858

Commercial
 
1,750

 
4.9
 %
 
1,669

Industrial
 
1,453

 
3.6
 %
 
1,403

Other
 
140

 
4.5
 %
 
134

Total Retail Sales
 
5,494

 
8.5
 %
 
5,064

Wholesale
 
244

 
(7.6
)%
 
264

Total Sales
 
5,738

 
7.7
 %
 
5,328


Retail sales volume increased by 246 GWh due to the effects of weather and by 131 GWh due to customer growth and higher average use. The decrease in wholesale sales is primarily due to the expiration of a customer contract.

Gas Distribution
 
Gas Distribution is comprised of the local distribution operations of SCE&G.  Gas distribution sales margin (including transactions with affiliates) was as follows:
Millions of dollars
 
2014
 
Change
 
2013
Operating revenues
 
$
178.9

 
25.4
%
 
$
142.7

Less: Gas purchased for resale
 
109.2

 
41.6
%
 
77.1

Margin
 
$
69.7

 
6.3
%
 
$
65.6

 
Margin increased primarily due to residential and commercial customer growth of $1.8 million and increased average usage of $2.3 million. SCE&G's WNA mitigates weather-related fluctuations in margin but has no impact on volumes.

Sales volumes (in MMBTU) by class, including transportation, were as follows: 
Classification (in thousands)
 
2014
 
Change
 
2013

Residential
 
8,440

 
30.7
 %
 
6,459

Commercial
 
5,184

 
20.7
 %
 
4,294

Industrial
 
4,520

 
(15.8
)%
 
5,369

Transportation
 
654

 
(50.3
)%
 
1,316

Total
 
18,798

 
7.8
 %
 
17,438


Total sales volumes increased primarily due to the effects of weather.
 
Other Operating Expenses
 
Other operating expenses were as follows:
Millions of dollars
 
2014
 
Change
 
2013
Other operation and maintenance
 
$
141.7

 
2.4
%
 
$
138.4

Depreciation and amortization
 
78.1

 
0.6
%
 
77.6

Other taxes
 
52.3

 
5.4
%
 
49.6


Other operation and maintenance expenses increased primarily due to incremental storm related expenses. Depreciation and amortization expense increased due to net plant additions.  Other taxes increased primarily due to higher property taxes.

Other Expense
 
Other income (expense) includes the results of certain incidental (non-utility) activities and AFC. AFC is a utility accounting practice whereby a portion of the cost of both equity and borrowed funds used to finance construction (which is shown on the balance sheet as construction work in progress) is capitalized.  Consolidated SCE&G includes an equity portion

56

Table of Contents

of AFC in nonoperating income and a debt portion of AFC in interest charges (credits), both of which have the effect of increasing reported net income.  AFC increased in 2014 due to higher AFC rates.

Interest Expense
 
Interest charges increased primarily due to increased borrowings.

Income Taxes
 
Income taxes for the three months ended March 31, 2014 were higher than the same period in 2013 primarily due to higher income before taxes which was partially offset by a marginally lower effective tax rate.

LIQUIDITY AND CAPITAL RESOURCES
 
Consolidated SCE&G anticipates that its cash obligations will be met through internally generated funds, the incurrence of additional short- and long-term indebtedness, and equity contributions from its parent company.  Consolidated SCE&G expects that, barring a future impairment of the capital markets, it has or can obtain adequate sources of financing to meet its projected cash requirements for the foreseeable future, including the cash requirements for nuclear construction and refinancing maturing long-term debt.  Consolidated SCE&G’s ratio of earnings to fixed charges for the three and 12 months ended March 31, 2014 was 4.11 and 3.66, respectively.

SCE&G received approximately $20 million during the three months ended March 31, 2014 as an equity contribution from its parent company.

Consolidated SCE&G is obligated with respect to an aggregate of $67.8 million of industrial revenue bonds which are secured by letters of credit issued by Branch Banking and Trust Company.  These letters of credit expire, subject to renewal, in the fourth quarter of 2014.
 
At March 31, 2014, Consolidated SCE&G had net available liquidity of approximately $976 million. The credit agreements total an aggregate of $1.4 billion, of which $200 million is scheduled to expire in October 2016 and the remainder is scheduled to expire in October 2018. Consolidated SCE&G regularly monitors the commercial paper and short-term credit markets to optimize the timing of repayment of outstanding balances on its draws, if any, from the credit facilities.  Consolidated SCE&G’s long term debt portfolio has a weighted average maturity of approximately 20 years and bears an average interest cost of 5.7%.  Substantially all of the long-term debt bears fixed interest rates or is swapped to fixed.  To further preserve liquidity, Consolidated SCE&G rigorously reviews its projected capital expenditures and operating costs and adjusts them where possible without impacting safety, reliability, and core customer service.

SCE&G has obtained FERC authority to issue short-term indebtedness and to assume liabilities as a guarantor (pursuant to Section 204 of the Federal Power Act). SCE&G may issue unsecured promissory notes, commercial paper and direct loans in amounts not to exceed $1.6 billion outstanding with maturity dates of one year or less, and may enter into guaranty agreements in favor of lenders, bankers, and dealers in commercial paper in amounts not to exceed $600 million. GENCO has obtained FERC authority to issue short-term indebtedness not to exceed $150 million outstanding with maturity dates of one year or less. The authority described herein will expire in October 2014 and is expected to be renewed.

In connection with the expected delays in the substantial completion of the New Units described in Note 9 to the condensed consolidated financial statements, SCE&G's current preliminary estimates of its capital expenditures for new nuclear construction (including transmission) for 2014 through 2016, which are subject to continuing review and adjustment, are $879 million in 2014, $910 million in 2015, and $702 million in 2016.

OTHER MATTERS
 
For information related to environmental matters, nuclear generation, and claims and litigation, see Note 9 to the condensed consolidated financial statements.

57

Table of Contents

ITEM 4.
CONTROLS AND PROCEDURES
 
As of March 31, 2014, SCE&G conducted an evaluation under the supervision and with the participation of its management, including its CEO and CFO, of (a) the effectiveness of the design and operation of its disclosure controls and procedures and (b) any change in its internal control over financial reporting.  Based on this evaluation, the CEO and CFO concluded that, as of March 31, 2014, SCE&G’s disclosure controls and procedures were effective.  There has been no change in SCE&G’s internal control over financial reporting during the quarter ended March 31, 2014, that has materially affected or is reasonably likely to materially affect SCE&G’s internal control over financial reporting.


PART II.  OTHER INFORMATION 

ITEM 5.    OTHER INFORMATION

SCANA and SCE&G:    

SCANA and SCE&G post information from time to time regarding developments relating to SCE&G’s new nuclear project on SCANA’s website at www.scana.com (which is not intended to be an active hyperlink; the information on SCANA’s website is not a part of this report or any other report or document that SCANA or SCE&G files with or furnishes to the SEC).  On SCANA’s homepage, there is a yellow box containing a link to the New Nuclear Development section of the website.  That section in turn contains a yellow box with a link to project news and updates.  Some of the information that will be posted from time to time, including the quarterly reports that SCE&G submits to the SCPSC and the ORS in connection with the new nuclear project, may be deemed to be material information that has not otherwise become public. Investors, media and others interested in SCE&G’s new nuclear project are encouraged to review this information and can sign up, under the Investor Relations Section at www.scana.com (which is not intended to be an active hyperlink; the information on SCANA’s website is not a part of this report or any other report or document that SCANA or SCE&G files with or furnishes to the SEC) for an email alert when there is a new posting in the New Nuclear Development yellow box.

ITEM 6.
EXHIBITS
 
SCANA and SCE&G:
 
Exhibits filed or furnished with this Quarterly Report on Form 10-Q are listed in the following Exhibit Index.
 
As permitted under Item 601(b) (4) (iii) of Regulation S-K, instruments defining the rights of holders of long-term debt of less than 10 percent of the total consolidated assets of SCANA, for itself and its subsidiaries, and of SCE&G, for itself and its consolidated affiliates, have been omitted and SCANA and SCE&G agree to furnish a copy of such instruments to the SEC upon request.

58

Table of Contents

SIGNATURES
 
Pursuant to the requirements of the Securities Exchange Act of 1934, each of the registrants has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.  The signature of each registrant shall be deemed to relate only to matters having reference to such registrant and any subsidiaries thereof.
 
SCANA CORPORATION
SOUTH CAROLINA ELECTRIC & GAS COMPANY
(Registrants)
 
 
By:
/s/James E. Swan, IV
Date: May 8, 2014
James E. Swan, IV
 
Controller
 
(Principal accounting officer)

59

Table of Contents

EXHIBIT INDEX
 
Applicable to
Form 10-Q of
 
Exhibit No.
SCANA
SCE&G
Description
 
 
 
 
3.01
X
 
Restated Articles of Incorporation of SCANA, as adopted on April 26, 1989 (Filed as Exhibit 3-A to Registration Statement No. 33-49145 and incorporated by reference herein)
 
 
 
 
3.02
X
 
Articles of Amendment dated April 27, 1995 (Filed as Exhibit 4-B to Registration Statement No. 33-62421 and incorporated by reference herein)
 
 
 
 
3.03
X
 
Articles of Amendment effective April 25, 2011 (Filed as Exhibit 4.03 to Registration Statement No. 333-174796 and incorporated by reference herein)
 
 
 
 
3.04
 
X
Restated Articles of Incorporation of SCE&G, as adopted on December 30, 2009 (Filed as Exhibit 1 to Form 8-A (File Number 000-53860) and incorporated by reference herein)
 
 
 
 
3.05
X
 
By-Laws of SCANA as amended and restated as of February 19, 2009 (Filed as Exhibit 4.04 to Registration Statement No. 333-174796 and incorporated by reference herein)
 
 
 
 
3.06
 
X
By-Laws of SCE&G as revised and amended on February 22, 2001 (Filed as Exhibit 3.05 to Registration Statement No. 333-65460 and incorporated by reference herein)
 
 
 
 
12.01
X
X
Statement Re Computation of Ratios (Filed herewith)
 
 
 
 
31.01
X
 
Certification of Principal Executive Officer Required by Rule 13a-14 (Filed herewith)
 
 
 
 
31.02
X
 
Certification of Principal Financial Officer Required by Rule 13a-14 (Filed herewith)
 
 
 
 
31.03
 
X
Certification of Principal Executive Officer Required by Rule 13a-14 (Filed herewith)
 
 
 
 
31.04
 
X
Certification of Principal Financial Officer Required by Rule 13a-14 (Filed herewith)
 
 
 
 
32.01
X
 
Certification of Principal Executive Officer Pursuant to 18 U.S.C. Section 1350 (Furnished herewith)
 
 
 
 
32.02
X
 
Certification of Principal Financial Officer Pursuant to 18 U.S.C. Section 1350 (Furnished herewith)
 
 
 
 
32.03
 
X
Certification of Principal Executive Officer Pursuant to 18 U.S.C. Section 1350 (Furnished herewith)
 
 
 
 
32.04
 
X
Certification of Principal Financial Officer Pursuant to 18 U.S.C. Section 1350 (Furnished herewith)
 
 
 
 
101. INS*
X
X
XBRL Instance Document
 
 
 
 
101. SCH*
X
X
XBRL Taxonomy Extension Schema
 
 
 
 
101. CAL*
X
X
XBRL Taxonomy Extension Calculation Linkbase
 
 
 
 
101. DEF*
X
X
XBRL Taxonomy Extension Definition Linkbase
 
 
 
 
101. LAB*
X
X
XBRL Taxonomy Extension Label Linkbase
 
 
 
 
101. PRE*
X
X
XBRL Taxonomy Extension Presentation Linkbase
 
*   Pursuant to Rule 406T of Regulation S-T, this interactive data file is deemed not filed or part of a registration statement or prospectus for purposes of Sections 11 or 12 of the Securities Act of 1933, is deemed not filed for purposes of Section 18 of the Securities Exchange Act of 1934, and otherwise is not subject to liability under these sections.

60