About Cabling Installation & Maintenance

Our mission: Bringing practical business and technical intelligence to today's structured cabling professionals

For more than 30 years, Cabling Installation & Maintenance has provided useful, practical information to professionals responsible for the specification, design, installation and management of structured cabling systems serving enterprise, data center and other environments. These professionals are challenged to stay informed of constantly evolving standards, system-design and installation approaches, product and system capabilities, technologies, as well as applications that rely on high-performance structured cabling systems. Our editors synthesize these complex issues into multiple information products. This portfolio of information products provides concrete detail that improves the efficiency of day-to-day operations, and equips cabling professionals with the perspective that enables strategic planning for networks’ optimum long-term performance.

Throughout our annual magazine, weekly email newsletters and 24/7/365 website, Cabling Installation & Maintenance digs into the essential topics our audience focuses on.

  • Design, Installation and Testing: We explain the bottom-up design of cabling systems, from case histories of actual projects to solutions for specific problems or aspects of the design process. We also look at specific installations using a case-history approach to highlight challenging problems, solutions and unique features. Additionally, we examine evolving test-and-measurement technologies and techniques designed to address the standards-governed and practical-use performance requirements of cabling systems.
  • Technology: We evaluate product innovations and technology trends as they impact a particular product class through interviews with manufacturers, installers and users, as well as contributed articles from subject-matter experts.
  • Data Center: Cabling Installation & Maintenance takes an in-depth look at design and installation workmanship issues as well as the unique technology being deployed specifically for data centers.
  • Physical Security: Focusing on the areas in which security and IT—and the infrastructure for both—interlock and overlap, we pay specific attention to Internet Protocol’s influence over the development of security applications.
  • Standards: Tracking the activities of North American and international standards-making organizations, we provide updates on specifications that are in-progress, looking forward to how they will affect cabling-system design and installation. We also produce articles explaining the practical aspects of designing and installing cabling systems in accordance with the specifications of established standards.

Cabling Installation & Maintenance is published by Endeavor Business Media, a division of EndeavorB2B.

Contact Cabling Installation & Maintenance

Editorial

Patrick McLaughlin

Serena Aburahma

Advertising and Sponsorship Sales

Peter Fretty - Vice President, Market Leader

Tim Carli - Business Development Manager

Brayden Hudspeth - Sales Development Representative

Subscriptions and Memberships

Subscribe to our newsletters and manage your subscriptions

Feedback/Problems

Send a message to our general in-box

 

Ximen Receives Final Mines Act Permit for the Kenville Gold Mine - Nelson BC, Canada

VANCOUVER, BC / ACCESSWIRE / April 19, 2023 / Ximen Mining Corp. (TSXV:XIM)(FRA:1XMA)(OTCQB:XXMMF) (the "Company" or "Ximen") announces that it has received the Final Mines Act Permit for its Kenville Gold Mine project in southeastern BC.

"The Kenville Gold Mine, which began operations in 1888, was one of the first underground gold mines in British Columbia. After years of working on this particular permit, the Kenville Gold Mine is now on track to becoming one of the greenest and environmentally-friendly gold mines in Southern BC. While there is still very much to do, our team's tenacity has brought us this far, and we are ready for the next phase of milestones that will finally bring this gold mine to fruition." States Anderson CEO Ximen Mining Corp.

Ximen Mining Corp, Wednesday, April 19, 2023, Press release picture

Ximen Mining Corp's - Kenville Gold Mine - Manager Lloyd Penner

A Mines Act Permit was issued to the Company for the Kenville Mine Project approving the following work:

  • Establishment of new Venango Portal and 1200 m of decline development with associated drill bays, re-mucks, safety bays and sumps.
  • Underground Exploration Drilling (20,250 m) from the new decline.
  • Establishment of one Waste Rock Storage facility.
  • Installation of surface water management structures.
  • Location of portable office structure.
  • Onsite fuel storage.

The permit is comprehensive and includes several conditions for Health and Safety, Geotechnical, Environmental Land and Watercourses, and the Reclamation and Closure Program. Items to be addressed before starting include:

  • 60 days prior to commencement of construction, engineering drawings must be submitted for surface water ponds, ditches, water management and water treatment system pipelines, pumping systems, or diversion channels.
  • 60 days prior to installation of the required monitoring wells and underground dewatering, the location, installation depths, and water level monitoring frequency must be submitted for review and approval.
  • Has Completed and submitted, a Trigger Action Response Plan (TARP) that addresses potential downstream effects on Eagle Creek associated with groundwater inflow rates to the underground workings must be developed and submitted.
  • Has Completed and submitted, underground development, a Ground Control Management Plan must be developed and implemented.
  • Has Completed and submitted, waste rock dump construction, a foundation inspection confirming that unsuitable materials have been removed from the footprint area.
  • Prior to initiation of the first blast, 2 days notification to the Senior Health & Safety Inspector, and 3 business days notification to Fortis BC are required.

Several other items are required once operations commence, as is typical for permits of this type.

The Company is very happy to have this permit in hand and can finally focus on developing the Kenville gold mine project. Design work for water management infrastructure is underway and the Company is looking forward to starting the mine development and finally getting the project underway.

Ximen Mining Corp, Wednesday, April 19, 2023, Press release picture

Photo of ore-type vein material from Kenville.

Ximen Mining Corp, Wednesday, April 19, 2023, Press release picture

Photo of rock truck and scooptram to be deployed at Kenville mine.

Technical disclosure in this news release has been approved by Dr. Mathew Ball, P.Geo., a Qualified Person as defined by National Instrument 43-101 and VP Exploration for Ximen Mining Corp.

On behalf of the Board of Directors,

"Christopher R. Anderson"

Christopher R. Anderson,
President, CEO and Director
604 488-3900

Investor Relations:
Sophy Cesar,
604-488-3900,
ir@XimenMiningCorp.com

About Ximen Mining Corp.

Ximen Mining Corp, Wednesday, April 19, 2023, Press release picture

Ximen Mining Corp. owns 100% interest in three of its precious metal projects located in southern BC. Ximen`s two Gold projects, The Amelia Gold Mine and The Brett Epithermal Gold Project. Ximen also owns the Treasure Mountain Silver Project adjacent to the past producing Huldra Silver Mine. Currently, the Treasure Mountain Silver Project is under an option agreement. The option partner is making annual staged cash and stocks payments as well as funding the development of the project. The company has also in addition acquired 100% interest in the Kenville Gold mine near Nelson British Columbia which comes with surface and underground rights, buildings and equipment.

Ximen is a publicly listed company trading on the TSX Venture Exchange under the symbol XIM, in the USA under the symbol XXMMF, and in Frankfurt, Munich, and Berlin Stock Exchanges in Germany under the symbol 1XMA and WKN with the number as A2JBKL.

Ximen Mining Corp, Wednesday, April 19, 2023, Press release picture

This press release contains certain "forward-looking statements" within the meaning of Canadian securities This press release contains certain "forward-looking statements" within the meaning of Canadian securities legislation, including statements regarding the receipt of TSX Venture Exchange approval and the exercise of the Option by Ximen. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are statements that are not historical facts; they are generally, but not always, identified by the words "expects," "plans," "anticipates," "believes," "intends," "estimates," "projects," "aims," "potential," "goal," "objective," "prospective," and similar expressions, or that events or conditions "will," "would," "may," "can," "could" or "should" occur, or are those statements, which, by their nature, refer to future events. The Company cautions that forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made and they involve a number of risks and uncertainties. Consequently, there can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Except to the extent required by applicable securities laws and the policies of the TSX Venture Exchange, the Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause future results to differ materially from those anticipated in these forward-looking statements include the possibility that the TSX Venture Exchange may not accept the proposed transaction in a timely manner, if at all. The reader is urged to refer to the Company's reports, publicly available through the Canadian Securities Administrators' System for Electronic Document Analysis and Retrieval (SEDAR) at www.sedar.com for a more complete discussion of such risk factors and their potential effects.

This press release shall not constitute an offer to sell or the solicitation of an offer to buy any securities, nor shall there be any sale of securities in any state in the United States in which such offer, solicitation or sale would be unlawful.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: Ximen Mining Corp.



View source version on accesswire.com:
https://www.accesswire.com/750054/Ximen-Receives-Final-Mines-Act-Permit-for-the-Kenville-Gold-Mine--Nelson-BC-Canada

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.