About Cabling Installation & Maintenance

Our mission: Bringing practical business and technical intelligence to today's structured cabling professionals

For more than 30 years, Cabling Installation & Maintenance has provided useful, practical information to professionals responsible for the specification, design, installation and management of structured cabling systems serving enterprise, data center and other environments. These professionals are challenged to stay informed of constantly evolving standards, system-design and installation approaches, product and system capabilities, technologies, as well as applications that rely on high-performance structured cabling systems. Our editors synthesize these complex issues into multiple information products. This portfolio of information products provides concrete detail that improves the efficiency of day-to-day operations, and equips cabling professionals with the perspective that enables strategic planning for networks’ optimum long-term performance.

Throughout our annual magazine, weekly email newsletters and 24/7/365 website, Cabling Installation & Maintenance digs into the essential topics our audience focuses on.

  • Design, Installation and Testing: We explain the bottom-up design of cabling systems, from case histories of actual projects to solutions for specific problems or aspects of the design process. We also look at specific installations using a case-history approach to highlight challenging problems, solutions and unique features. Additionally, we examine evolving test-and-measurement technologies and techniques designed to address the standards-governed and practical-use performance requirements of cabling systems.
  • Technology: We evaluate product innovations and technology trends as they impact a particular product class through interviews with manufacturers, installers and users, as well as contributed articles from subject-matter experts.
  • Data Center: Cabling Installation & Maintenance takes an in-depth look at design and installation workmanship issues as well as the unique technology being deployed specifically for data centers.
  • Physical Security: Focusing on the areas in which security and IT—and the infrastructure for both—interlock and overlap, we pay specific attention to Internet Protocol’s influence over the development of security applications.
  • Standards: Tracking the activities of North American and international standards-making organizations, we provide updates on specifications that are in-progress, looking forward to how they will affect cabling-system design and installation. We also produce articles explaining the practical aspects of designing and installing cabling systems in accordance with the specifications of established standards.

Cabling Installation & Maintenance is published by Endeavor Business Media, a division of EndeavorB2B.

Contact Cabling Installation & Maintenance

Editorial

Patrick McLaughlin

Serena Aburahma

Advertising and Sponsorship Sales

Peter Fretty - Vice President, Market Leader

Tim Carli - Business Development Manager

Brayden Hudspeth - Sales Development Representative

Subscriptions and Memberships

Subscribe to our newsletters and manage your subscriptions

Feedback/Problems

Send a message to our general in-box

 

ESGold Accelerates Toward Production with Construction Start at Flagship Gold-Silver Project

VANCOUVER, British Columbia, April 17, 2025 (GLOBE NEWSWIRE) -- via IBN – ESGold Corp. (“ESGold” or the “Company”) (CSE: ESAU | OTCQB: ESAUF | FSE: Z7D) is pleased to announce the commencement of on-site construction and assembly at its Montauban Gold-Silver Project in Quebec, a key milestone that moves the Company into the execution phase of its near-term production strategy.

Following the successful completion of its C$3.45 million financing in April, ESGold has officially initiated the build-out and expansion of its milling and processing facilities. This represents the final major phase of infrastructure development before production begins—transforming Montauban from a legacy mine site into one of Canada’s next active gold and silver operations.

“This is the moment we’ve been working toward—breaking ground and moving decisively toward gold and silver production,” said Brad Kitchen, President of ESGold Corp. “Our team, contractors, and stakeholders are aligned and energized to deliver on our strategy. We are building a clean, scalable, and modern operation that reflects the new era of mining in Quebec. With production targeted for early Q4, Montauban is on track to become a model for sustainable redevelopment of legacy mines.”

Construction Phase Now Underway
As part of this phase, the Company has engaged a prime contractor to lead the mobilization and assembly process at Montauban. Key milestones now underway or scheduled over the coming weeks include:

  • Mobilization of cranes and heavy equipment to commence structural build-out.

  • Delivery and installation of mill components, with site preparation already in progress.

  • Delivery of a 1000-amp, 600V generator, ensuring reliable and scalable on-site power capacity.

  • Deployment of secure communications and monitoring systems, including STARLINK-enabled site connectivity.

  • Installation of security perimeter fencing and surveillance infrastructure to support 24/7 oversight and operational integrity.

  • Extension of the mill building by 1,800 sq. ft.

  • Site cleanup and staging to accommodate phased installation of the mill circuit.
  • Overtime work schedules for field crews to expedite construction and adhere to the Company’s early Q4 production timeline.

This initial construction and mobilization stage is expected to last approximately one month, after which the Company will immediately advance into the next phase of mill circuit installation and commissioning.

Near-Term Outlook and Strategic Roadmap
With permits in hand, infrastructure in place, and funding secured, ESGold remains laser-focused on achieving its dual-track strategy: near-term gold and silver production paired with district-scale exploration.

Over the next month, the Company will also:

  • Complete onsite mineralogy tests to finalize input parameters for processing and optimization.

  • Finalize and publish its Updated Preliminary Economic Assessment (PEA) to reflect elevated gold and silver prices and near-surface upside.

  • Release results from the Ambient Noise Tomography (ANT) Survey, which is producing high-resolution imaging of the deposit’s subsurface footprint, targeting a potential larger mineralized system at depth.

  • Engage provincial and federal bodies to advance grant applications that align with Quebec’s critical mineral strategy and clean mining priorities.

Becoming Canada’s Next Gold-Silver Producer
Montauban operated as a mine for over 80 years. Today, ESGold is breathing new life into the site with the help of clean processing technologies, advanced exploration tools, and a disciplined capital approach that minimizes dilution and prioritizes cash flow generation.

About ESGold Corp.
ESGold Corp. (CSE: ESAU | OTCQB: ESAUF | FSE: Z7D) is a fully permitted, pre-production resource company at the forefront of clean mining and exploration innovation. With proven expertise in Quebec, the Company is advancing its Montauban Gold-Silver Project toward near-term production while delivering long-term value through sustainable resource recovery and strategic exploration. The Montauban Project, located 80 km west of Quebec City, combines production-readiness with untapped district-scale exploration potential.

For more information, please contact ESGold Corp. at +1-888-370-1059 or visit www.esgold.com for additional resources, including a French version of this press release, past news releases, a 3D model of the Montauban processing plant, media interviews, and opinion-editorial pieces.

Stay connected by following us on X (formerly Twitter), LinkedIn, and joining our Telegram channel.

On behalf of the Board of Directors,
Brad Kitchen
President & Director
info@esgold.com
+1-888-370-1059

Forward-Looking Statements:
This news release includes forward-looking statements within the meaning of applicable securities laws. These statements are based on assumptions and expectations that involve a number of known and unknown risks and uncertainties. Actual results could differ materially. Forward-looking information includes statements regarding the expected use of proceeds, the development and construction timelines of the Montauban Project, future production, and anticipated project milestones. Investors are cautioned not to place undue reliance on these forward-looking statements. All forward-looking information contained in this release is qualified by these cautionary statements.

Neither the Canadian Securities Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

Corporate Communications
IBN
Austin, Texas
www.InvestorBrandNetwork.com
512.354.7000 Office
Editor@InvestorBrandNetwork.com


Primary Logo

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.