About Cabling Installation & Maintenance

Our mission: Bringing practical business and technical intelligence to today's structured cabling professionals

For more than 30 years, Cabling Installation & Maintenance has provided useful, practical information to professionals responsible for the specification, design, installation and management of structured cabling systems serving enterprise, data center and other environments. These professionals are challenged to stay informed of constantly evolving standards, system-design and installation approaches, product and system capabilities, technologies, as well as applications that rely on high-performance structured cabling systems. Our editors synthesize these complex issues into multiple information products. This portfolio of information products provides concrete detail that improves the efficiency of day-to-day operations, and equips cabling professionals with the perspective that enables strategic planning for networks’ optimum long-term performance.

Throughout our annual magazine, weekly email newsletters and 24/7/365 website, Cabling Installation & Maintenance digs into the essential topics our audience focuses on.

  • Design, Installation and Testing: We explain the bottom-up design of cabling systems, from case histories of actual projects to solutions for specific problems or aspects of the design process. We also look at specific installations using a case-history approach to highlight challenging problems, solutions and unique features. Additionally, we examine evolving test-and-measurement technologies and techniques designed to address the standards-governed and practical-use performance requirements of cabling systems.
  • Technology: We evaluate product innovations and technology trends as they impact a particular product class through interviews with manufacturers, installers and users, as well as contributed articles from subject-matter experts.
  • Data Center: Cabling Installation & Maintenance takes an in-depth look at design and installation workmanship issues as well as the unique technology being deployed specifically for data centers.
  • Physical Security: Focusing on the areas in which security and IT—and the infrastructure for both—interlock and overlap, we pay specific attention to Internet Protocol’s influence over the development of security applications.
  • Standards: Tracking the activities of North American and international standards-making organizations, we provide updates on specifications that are in-progress, looking forward to how they will affect cabling-system design and installation. We also produce articles explaining the practical aspects of designing and installing cabling systems in accordance with the specifications of established standards.

Cabling Installation & Maintenance is published by Endeavor Business Media, a division of EndeavorB2B.

Contact Cabling Installation & Maintenance

Editorial

Patrick McLaughlin

Serena Aburahma

Advertising and Sponsorship Sales

Peter Fretty - Vice President, Market Leader

Tim Carli - Business Development Manager

Brayden Hudspeth - Sales Development Representative

Subscriptions and Memberships

Subscribe to our newsletters and manage your subscriptions

Feedback/Problems

Send a message to our general in-box

 

Steppe Gold Provides Corporate Update - over 100,000 Oz Gold Production

By: Newsfile

Ulaanbaatar, Mongolia--(Newsfile Corp. - October 23, 2023) - Steppe Gold Limited (TSX: STGO) (OTCQX: STPGF) (FSE: 2J9) ("Steppe Gold" or the "Company") is pleased to provide an operations update.

Highlights: (all $ figures USD unless stated)

  • ATO Gold Mine production passes the 100,000 oz threshold
  • Project to date mined ore has reached 3.894M tonnes
  • Project to date stacked ore has reached 3.529M tonnes
  • Increasing its annual production from approximately 30koz in 2023 and 2024 to over 100koz Au Eq from the end of 2025

The Company is pleased to report production from the Phase 1 heap leach operations recently passed the 100,000 oz milestone.

This equates to gross revenue of $188M and royalties and taxes paid to the Mongolian treasury of approximately $13M in the project to date.

From the start of commercial production in April 2020, the mine has seen uninterrupted production, while withstanding major disruption to reagent supplies. This has been a credit to all Steppe Gold team members. It has generated consistent economic activity for all our stakeholders - driving training and employment in the region and supporting economic activity in our local communities.

Mining and stacking activities in the third quarter continued on-plan and the Company mined and stacked 261,694 and 247,044 tonnes respectively in the quarter. This brings the total for the project to date to 3.894M tonnes and 3.529 tonnes respectively.

To recap third quarter production - production from the third quarter comprised 7,587 oz of gold and 20,757 oz of silver. This brings the year-to-date total to 20,686 oz of gold and 57,995 oz of silver. With over 65,000 oz remaining at the heap leach operations, we expect to see uninterrupted production at the ATO Gold Mine in 2024 and 2025 as the Company continues its Phase 2 Expansion with first concentrate expected in late 2025 or early 2026.

Mr Bataa Tumur-Ochir, Steppe Gold Chairman and CEO, commented, "We are very excited to pass the 100,000 oz milestone at the ATO Gold Mine. In difficult circumstances our team has remained focused on delivering the best production outcomes, using responsible mining best practices and, most importantly, providing a safe workplace for all our team members. We are a proud Mongolian company and I want to thank all our stakeholders and partners who have shown us great support in our journey so far. We are excited about the next phase of the project as we move to be a 100,000 oz p.a producer, fulfilling the promise of home-grown Mongolian mining companies on the world stage."

Steppe Gold Limited
Steppe Gold is Mongolia's premier precious metals company.

For Further information, please contact:
Bataa Tumur-Ochir, Chairman and CEO

Shangri-La office, Suite 1201, Olympic Street
19A, Sukhbaatar District 1,
Ulaanbaatar 14241, Mongolia
Tel: +976 7732 1914

Cautionary Note Regarding Forward-Looking Statements:
The above contains forward-looking statements that are subject to a number of known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those anticipated in our forward-looking statements. Factors that could cause such differences include: changes in world commodity markets, equity markets, costs and supply of materials relevant to the mining industry, change in government and changes to regulations affecting the mining industry. Forward-looking statements in this release include, among other things, statements regarding the trading of the Common Shares and business, economic, and political conditions in Mongolia. Although we believe the expectations reflected in our forward-looking statements are reasonable, results may vary, and we cannot guarantee future results, levels of activity, performance or achievements. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the content of this news release

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/184824

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.