ETFOptimize | High-performance ETF-based Investment Strategies

Quantitative strategies, Wall Street-caliber research, and insightful market analysis since 1998.


ETFOptimize | HOME
Close Window

PPX Provides Update on Construction Activities of Processing Plant at Igor Project

TORONTO, ON / ACCESS Newswire / September 24, 2025 / PPX Mining Corp. (the "Company" or "PPX"; TSX.V:PPX; BVL:PPX) is pleased to announce that construction of the 350 tpd CIL and Flotation plant at its Igor Project in Peru to process gold and silver (dore and precious metal concentrate) continues at an accelerated pace, developing in parallel several activities such as: the installation of leach tanks, assembly of the crushing line, completion of final civil works, last weeks of earthworks in tailings and start of construction of auxiliary works, reaching an advance of the total plant to 55%.

The Company's EPC contractor began the assembly of the mechanical equipment in the milling area, while working on the unfinished civil works. Likewise, JPC Ingenieros began the installation of the leach tanks. In addition, JM&L continues with the preparation of the tailing management area to receive Geotubes. In addition, minor contractors continue with auxiliary components.

The photograph below shows a panoramic view of the construction of the plant as of September 20, 2025:

Installation

The EPC contractor has installed the two 7'x12' ball mills and jaw crusher. The mill motors and reduction gearboxes are also in place and the ring gears installed. Several metal structures such as the cyclone tower, fines hopper, coarse ore hopper, and conveyor belt support structures are also being assembled.

The following photograph, shows the mills:

Cyclone Support tower in the foreground with ball mills:

Leach Tanks

The company JPC Ingenieros, a leader in the manufacture of leach tanks in Peru, has begun their assembly at site and it can be seen that the lower sections of four tanks are in place, the supports for the agitators (painted blue) are also in place for two of the tanks to the left of the following photograph. These sections will be raised on jacks and a further 3 sections welded in, to give a height of 23 feet (7 meters).

See next photograph show the leach tanks:

Tailings Management Area

The earthworks of the tailings management area are in the final stages (sufficient for the first year of operation) and the drainage channels and collection ponds are being finished. An impermeable membrane will be installed on the surface, together with a drain system using perforated plastic tubes covered with crushed stone. Geotubes will be paced on this surface and filled with tailings slurry, with process water being recovered by the drainage system and recycled to the process.

Geomembrane and geotextile materials purchased from China are scheduled to arrive in early October. The total progress to date is 65% of this first stage.

See next photograph shows the tailings management area:

Civil Works

The EPC contractor continues with the last part of the civil works, with the construction of the retaining wall to allow trucks to tip ore into the coarse ore hopper and the circular pedestals for the water tanks and thickener, in addition to the bases of the desorption plant (rectangular), among others.

See photographs below - two circular water pedestals and circular thickener base:

Retaining wall under construction using mechanically reinforced earth construction:

John Thomas, CEO of PPX Mining Corp., commented: "Construction is progressing well, and commissioning should start at year end".

About PPX Mining Corp: PPX Mining Corp. (TSX.V:PPX.V)(SSE:PPX)(BVL:PPX) is a Canadian exploration and development company with assets in northern Peru. The Company's 100% owned Igor gold and silver project is located in the prolific northern Peruvian gold belt in the department of La Libertad. PPX is pursuing a two-pronged strategy to further develop and explore Project Igor. The Callanquitas structure is open along strike and at depth. Parallel structures have not yet been explored. The new discoveries in Portachuelos in 2018, as well as the exploration targets in Domo and Tesoros, show that the Igor Project is becoming a district-scale project with multiple deposits and mineralized zones. Evaluating mineral development alternatives in parallel with exploration drilling will provide dual catalysts for growth and increased shareholder value.

On behalf of the Board of Directors
John Thomas
Chief Executive Officer
82 Richmond Street East
Toronto, Ontario M5C 1P1
Canada
416-361-0737

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Statement

This press release contains forward-looking information and forward-looking statements (collectively, "forward-looking statements") as such terms are defined by applicable securities laws, including, but not limited to statements regarding test results, future plans or management estimates. Forward-looking statements are statements that relate to future events. In this context, forward-looking statements often address expected future business and financial performance and often contain words such as "anticipate," "believe," "plan," "estimate," "expect," and "intend,", statements that an action or event "may," "might," "could," "should," or "will" be taken or occur, or other similar expressions. Forward-looking statements are subject to a number of known and unknown risks and uncertainties, many of which involve factors or circumstances that are beyond the Company's control, and the Company's actual results could differ materially from those stated or implied in forward-looking statements due to many various factors. Such uncertainties and risks include, among others, delays in obtaining or inability to obtain required regulatory approvals in connection with this transaction. Although the Company believes that the expectations reflected in the forward-looking statements are reasonable, the Company cannot guarantee that the events and circumstances reflected in the forward-looking statements will be achieved or occur. The timing of events and circumstances and actual results could differ materially from those projected in the forward-looking statements. Accordingly, one should not place undue reliance on forward- looking statements. All forward-looking statements contained in this press release are made as of today's date, and the Company undertakes no obligation to update or publicly revise any forward-looking statements, whether as a result of new information, future events or otherwise, unless required by law.

SOURCE: PPX Mining Corp.



View the original press release on ACCESS Newswire

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.


 

IntelligentValue Home
Close Window

DISCLAIMER

All content herein is issued solely for informational purposes and is not to be construed as an offer to sell or the solicitation of an offer to buy, nor should it be interpreted as a recommendation to buy, hold or sell (short or otherwise) any security.  All opinions, analyses, and information included herein are based on sources believed to be reliable, but no representation or warranty of any kind, expressed or implied, is made including but not limited to any representation or warranty concerning accuracy, completeness, correctness, timeliness or appropriateness. We undertake no obligation to update such opinions, analysis or information. You should independently verify all information contained on this website. Some information is based on analysis of past performance or hypothetical performance results, which have inherent limitations. We make no representation that any particular equity or strategy will or is likely to achieve profits or losses similar to those shown. Shareholders, employees, writers, contractors, and affiliates associated with ETFOptimize.com may have ownership positions in the securities that are mentioned. If you are not sure if ETFs, algorithmic investing, or a particular investment is right for you, you are urged to consult with a Registered Investment Advisor (RIA). Neither this website nor anyone associated with producing its content are Registered Investment Advisors, and no attempt is made herein to substitute for personalized, professional investment advice. Neither ETFOptimize.com, Global Alpha Investments, Inc., nor its employees, service providers, associates, or affiliates are responsible for any investment losses you may incur as a result of using the information provided herein. Remember that past investment returns may not be indicative of future returns.

Copyright © 1998-2017 ETFOptimize.com, a publication of Optimized Investments, Inc. All rights reserved.