Appalachian Power plan would add solar, wind and energy storage

The utility's plan would help it meet clean energy mandates.

Appalachian Power said it wants to acquire or contract for 294 MW of solar and 204 MW of wind power over the next three years as part of its plan to meet targets set in 2020 by the Virginia Clean Economy Act (VCEA).

The law requires the utility to file an annual plan with the Virginia State Corporation Commission (SCC) outlining how it will meet key mandates to achieve 100% carbon-free status by 2050. 

The plan filed with the SCC is the company’s second update since the VCEA became law. Appalachian Power said it intends to meet its VCEA targets primarily through investments in solar, wind, energy storage, and purchase of market renewable energy certificates (RECs).

The company’s short-term plans are to add nearly 500 MW of solar and wind power to the company’s renewables portfolio over the next three years. By 2040, the company expects to add around 3,300 MW of solar, 2,600 MW of energy storage, and nearly 3,000 MW of onshore wind to its current portfolio of wind and hydro resources. 

Reports said that at the end of the third quarter of 2021 around 64.5% of the power generated or purchased by Appalachian Power came from coal. Natural gas provided another 19.1%, while wind and hydroelectric power made up the remaining 16.4%.

The largest project in the utility’s short-term plan would add 204 MW of wind energy to the company’s renewables portfolio. Located in Illinois, the project is expected to be operational in December 2024, and would represent Appalachian Power’s largest wind resource project to date. In the filing, the company seeks permission to recover the costs associated with the purchase of the facility.

The company also is seeking approval to recover costs associated with its purchase of two solar energy projects: a 50 MW solar facility in Berkeley County, W.Va., and a 4.9 MW solar facility in Amherst County, Va.

The company’s short-term plans also include the purchase of a 150 MW solar facility in Pittsylvania County, Va. The company is seeking permission from the SCC to move forward with its intention to acquire the project, as well as regulatory approval to enter into agreements to buy the output of three Virginia solar facilities through power purchase agreements (PPAs). The three solar facilities would add around 89 MW of capacity to the company’s energy supply. 

In addition to the nearly 500 MW in solar and wind projects outlined by the company, the plan includes 55 MW of separate solar projects that are or will be in service in the coming months. In its filing, the company is seeking to include in rates the costs associated with these projects and the Amherst solar energy project, as well as market REC purchases that is said are necessary for annual compliance.  

The company is considering adding energy storage to improve reliability for customers who receive power from the company’s Glade Station – White Top circuit in southwest Virginia. The utility said that energy storage would improve reliability by providing a back-up source of power when an outage occurs. Although included in the filing, the project is still in the planning stages.  

The utility said that customer bills are expected to increase as the company adds more renewables to comply with the VCEA’s requirements. If approved as requested, residential customers using 1,000 kWh a month would see an approximate $2.37 increase in their monthly bill.

Appalachian Power has 1 million customers in Virginia, West Virginia and Tennessee (as AEP Appalachian Power). It is part of American Electric Power, which is focused on building a smarter energy infrastructure and delivering new technologies and custom energy solutions.

In October, the utility added 20 MW of solar power through a PPA with Leatherwood Solar, a solar generation facility in Henry County, Va. developed by Energix Renewables.

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.


 

IntelligentValue Home
Close Window

DISCLAIMER

All content herein is issued solely for informational purposes and is not to be construed as an offer to sell or the solicitation of an offer to buy, nor should it be interpreted as a recommendation to buy, hold or sell (short or otherwise) any security.  All opinions, analyses, and information included herein are based on sources believed to be reliable, but no representation or warranty of any kind, expressed or implied, is made including but not limited to any representation or warranty concerning accuracy, completeness, correctness, timeliness or appropriateness. We undertake no obligation to update such opinions, analysis or information. You should independently verify all information contained on this website. Some information is based on analysis of past performance or hypothetical performance results, which have inherent limitations. We make no representation that any particular equity or strategy will or is likely to achieve profits or losses similar to those shown. Shareholders, employees, writers, contractors, and affiliates associated with ETFOptimize.com may have ownership positions in the securities that are mentioned. If you are not sure if ETFs, algorithmic investing, or a particular investment is right for you, you are urged to consult with a Registered Investment Advisor (RIA). Neither this website nor anyone associated with producing its content are Registered Investment Advisors, and no attempt is made herein to substitute for personalized, professional investment advice. Neither ETFOptimize.com, Global Alpha Investments, Inc., nor its employees, service providers, associates, or affiliates are responsible for any investment losses you may incur as a result of using the information provided herein. Remember that past investment returns may not be indicative of future returns.

Copyright © 1998-2017 ETFOptimize.com, a publication of Optimized Investments, Inc. All rights reserved.