California PUC adopts plan to add 25.5GW of renewables by 2023

The California Public Utilities Commission (CPUC) approved plans to add around 25,500 MW of renewable energy resources and 15,000 MW of energy storage and demand response resources by 2032. The decision also adopted a 35 million metric ton (MMT) electric sector greenhouse gas emission (GHG) planning target. That goal, also to be achieved by 2032, is tighter than an earlier 46 […]

The California Public Utilities Commission (CPUC) approved plans to add around 25,500 MW of renewable energy resources and 15,000 MW of energy storage and demand response resources by 2032. 

The decision also adopted a 35 million metric ton (MMT) electric sector greenhouse gas emission (GHG) planning target. That goal, also to be achieved by 2032, is tighter than an earlier 46 MMT GHG target.

The CPUC said its February 10 decision equates to 73% Renewables Portfolio Standard (RPS) resources and 86% GHG-free resources by 2032.  

The preferred system plan portfolio differs from one previously adopted by including more solar and battery storage, as well as new long-duration storage, out-of-state wind, and offshore wind resources.  

The decision said the process to include offshore wind in IRP capacity expansion models began in early 2020 and is due to wrap up in 2022. A March 2021 joint agency policy report to state legislators showed that offshore wind was likely to be needed in California’s 100% clean energy portfolio by 2045. 

The commission said that three load serving entities already have included around 300 MW of offshore wind in their integrated resource plans. Those resources would connect to the state’s electric power grid at interconnection points in Humboldt County and at Central Coast locations. 

Including offshore and out-of-state wind resources show their increased viability as “cost-effective resources” to help meet state goals, the CPUC said.  

A preliminary analysis of CPUC’s preferred system plan portfolio of the load serving entities (LSEs) indicated that sufficient space exists for these new resources on the existing transmission system. It said that “only limited transmission upgrades” would be needed by 2032.  

The CPUC said this finding would be validated in detail by the California Independent System Operator (CAISO) in its 2022-2023 Transmission Planning Process (TPP). The TPP is an evaluation of the CAISO transmission grid to identify grid upgrades needed to address reliability, meet state policy goals, and provide economic benefits. 

The regulatory decision also ordered utility procurement of two battery storage projects that were identified by the CAISO as alternatives to transmission upgrades in the previous TPP cycle. The projects are both in Pacific Gas and Electric’s service area. They include a 95 MW 4-hour storage resource on the Kern-Lamont 115 kV system and a 50 MW 4-hour storage resource at the Mesa 115 kV substation. 

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.


 

IntelligentValue Home
Close Window

DISCLAIMER

All content herein is issued solely for informational purposes and is not to be construed as an offer to sell or the solicitation of an offer to buy, nor should it be interpreted as a recommendation to buy, hold or sell (short or otherwise) any security.  All opinions, analyses, and information included herein are based on sources believed to be reliable, but no representation or warranty of any kind, expressed or implied, is made including but not limited to any representation or warranty concerning accuracy, completeness, correctness, timeliness or appropriateness. We undertake no obligation to update such opinions, analysis or information. You should independently verify all information contained on this website. Some information is based on analysis of past performance or hypothetical performance results, which have inherent limitations. We make no representation that any particular equity or strategy will or is likely to achieve profits or losses similar to those shown. Shareholders, employees, writers, contractors, and affiliates associated with ETFOptimize.com may have ownership positions in the securities that are mentioned. If you are not sure if ETFs, algorithmic investing, or a particular investment is right for you, you are urged to consult with a Registered Investment Advisor (RIA). Neither this website nor anyone associated with producing its content are Registered Investment Advisors, and no attempt is made herein to substitute for personalized, professional investment advice. Neither ETFOptimize.com, Global Alpha Investments, Inc., nor its employees, service providers, associates, or affiliates are responsible for any investment losses you may incur as a result of using the information provided herein. Remember that past investment returns may not be indicative of future returns.

Copyright © 1998-2017 ETFOptimize.com, a publication of Optimized Investments, Inc. All rights reserved.