On Wednesday, May 25, the Illinois Commerce Commission (ICC) made several changes to the state’s rules governing how distributed energy resources (DERs), such as rooftop solar panels and energy storage systems, connect to the state’s electric distribution grid. The revisions to Illinois’ interconnection rules include a number of positive developments that advocates believe will streamline the interconnection process and reduce the time and cost to connect clean energy to the grid. They will also make it easier to utilize energy storage and provide increased transparency about interconnection review results.
Subscribe today to the all-new Factor This! podcast from Renewable Energy World. This podcast is designed specifically for the solar industry and is available wherever you get your podcasts.
Listen to the most recent episode on building out the U.S. solar supply chain, featuring interviews with Rhone Resch, Martin Pochtaruk, and Michael Parr.
Recognizing energy storage’s unique characteristics
One of the key changes establishes protocols for utilizing some of the unique characteristics of energy storage that will make it possible for the state’s grid to accommodate higher levels of renewable energy. That’s because, when paired with energy storage, DER projects can limit the amount of energy they send onto the grid (“non-export” and “limited-export” projects). The amount of electricity a project will send to the grid is a key factor in whether it can interconnect without the need for lengthy study or costly equipment upgrades to ensure grid safety and reliability. Projects that export less or no electricity to the grid are less likely to cause issues.
Because energy storage is a newer technology, most interconnection rules do not yet recognize the possibility of limiting export or have guidelines for handling such projects. The revised Illinois interconnection rules now recognize limited- and non-export projects and establish different review approaches that reflect a project’s limited export amount, where appropriate, when assessing potential grid impacts.
There are several other noteworthy developments in the revised interconnection rules, including:
- Improvements to the way projects are “screened” for potential grid impacts, which will result in fewer projects being required to go through time-consuming and costly study processes before being approved to interconnect.
- Requirements for utilities to provide greater information transparency to interconnection applicants, including details on grid constraints that prevent their projects from proceeding as designed, and more detailed cost and timeline estimates.
- A new pathway for developers to modify their pending DER projects in response to information on grid constraints, allowing them to improve their likelihood of approval without having to withdraw and reapply, as has historically been the case.
All of these changes are expected to allow more projects to successfully interconnect and to increase the pace at which renewable energy can be added to Illinois’ distribution grid.
“This will put more renewable power on the grid faster and cheaper, while still maintaining safety and reliability,” said Staff Attorney Erica S. McConnell of the Environmental Law & Policy Center (ELPC), one of the organizations the helped usher in the new rules. The Interstate Renewable Energy Council (IREC), Vote Solar, and NRDC (Natural Resources Defense Council), also helped garner public support for the rules.
The changes reflect current best practices established through a collaborative research and policy project by utilities and clean energy advocates, including IREC, that resulted in a toolkit of solutions for improving the interconnection of energy storage projects (“the BATRIES Toolkit”).
Related: 8 steps to streamline energy storage interconnection
These changes also build upon the Climate and Equitable Jobs Act (CEJA) Illinois passed last year.
“These interconnection governance changes are necessary for the future of our energy grid and set the stage for groundbreaking programs promised by CEJA,” said Will Kenworthy, Regulatory Director at Vote Solar.
IREC Regulatory Vice President Radina Valova called the changes “cutting edge” in a statement, adding that they should be seen as “a model for other states that want to lead the way to a clean energy future.”
More work to be doneWhile an excellent starting point, one area where the changes fell short of public interest groups’ recommendations is in regard to data reporting requirements for the state’s utilities. The commission declined to require more detailed reporting requirements that would help the commission and interested stakeholders ensure the interconnection process is functioning well and that utilities are delivering on their required obligations. Lack of data on utility performance metrics in the interconnection process is a common problem that prevents accountability and improvements.