NV Energy to add BESS as it works to trim reliance on western energy markets

The BESS is part of a plan by NV Energy to reduce its reliance on western energy markets, which it said have been roiled by droughts, heatwaves and California energy policies.

Energy Vault Holdings said that NV Energy awarded it a project to deploy a 220 MW/440MWh short-duration Battery Energy Storage System (BESS). Work is expected to start in Q2 2023 with commercial operation expected by the end of 2023.

The two-hour, grid-tied energy storage system is designed to store and dispatch excess renewable energy, including wind and solar power. The BESS will be charged and discharged on a daily basis and designed to dispatch stored renewable energy at peak consumption hours to help meet the high demand during Nevada’s peak load hours.

This is Energy Vault’s first public utility customer for our short duration energy storage solutions.

In late November, NV Energy filed with state utility regulators a plan to reduce its reliance on the open energy market and increase renewable energy capacity in Nevada.

The proposal is intended to help address the effects of heatwaves and drought on the availability of western energy resources and to shield the utility from the impacts of California regulatory changes and resource adequacy challenges that the state has experienced.

Over the past three summers, Nevada’s energy supply has been “challenged and has seen increased risk” of summer energy shortages due to increased competition for energy across the west, primarily due to energy shortfalls in California, said Doug Cannon, NV Energy president and CEO in a statement.

The plan would add Nevada-based energy generation and storage capacity to enter service in the summer of 2024 and 2025 and to make upgrades to the transmission system to accommodate more renewable energy resources.

Planned-for resources include:

  • The grid-tied battery storage system on the site of the coal-fired Valmy Generating Station, which is planned for retirement by year-end 2025.
  • 120 MW portfolio of geothermal projects from Ormat
  • 20 MW Enhanced Geothermal system from Eavor
  • 440 MW of natural gas-fired combustion peaking turbines on the site of the Silverhawk Generating Station in southern Nevada. The turbines would be capable of running on hydrogen.

Energy Vault’s BESSs have expected lives that range from 10 to 20 years. The company said it makes use of a purpose-built AC block system leveraging an innovative architecture to lower cost, improve performance, and ensure the highest level of project safety.

The company’s BESS integrates hardware components from a network of battery and power electronics manufacturers, and incorporates modular inverters in an effort to improve uptime and insulate against the potential consolidated damages of lost capacity. The battery systems use a flexible system architecture to help achieve long-term asset resiliency as grid conditions and market parameters change, as well as improved augmentation by avoiding reliance on a single manufacturer.

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.


 

IntelligentValue Home
Close Window

DISCLAIMER

All content herein is issued solely for informational purposes and is not to be construed as an offer to sell or the solicitation of an offer to buy, nor should it be interpreted as a recommendation to buy, hold or sell (short or otherwise) any security.  All opinions, analyses, and information included herein are based on sources believed to be reliable, but no representation or warranty of any kind, expressed or implied, is made including but not limited to any representation or warranty concerning accuracy, completeness, correctness, timeliness or appropriateness. We undertake no obligation to update such opinions, analysis or information. You should independently verify all information contained on this website. Some information is based on analysis of past performance or hypothetical performance results, which have inherent limitations. We make no representation that any particular equity or strategy will or is likely to achieve profits or losses similar to those shown. Shareholders, employees, writers, contractors, and affiliates associated with ETFOptimize.com may have ownership positions in the securities that are mentioned. If you are not sure if ETFs, algorithmic investing, or a particular investment is right for you, you are urged to consult with a Registered Investment Advisor (RIA). Neither this website nor anyone associated with producing its content are Registered Investment Advisors, and no attempt is made herein to substitute for personalized, professional investment advice. Neither ETFOptimize.com, Global Alpha Investments, Inc., nor its employees, service providers, associates, or affiliates are responsible for any investment losses you may incur as a result of using the information provided herein. Remember that past investment returns may not be indicative of future returns.

Copyright © 1998-2017 ETFOptimize.com, a publication of Optimized Investments, Inc. All rights reserved.