About Cabling Installation & Maintenance

Our mission: Bringing practical business and technical intelligence to today's structured cabling professionals

For more than 30 years, Cabling Installation & Maintenance has provided useful, practical information to professionals responsible for the specification, design, installation and management of structured cabling systems serving enterprise, data center and other environments. These professionals are challenged to stay informed of constantly evolving standards, system-design and installation approaches, product and system capabilities, technologies, as well as applications that rely on high-performance structured cabling systems. Our editors synthesize these complex issues into multiple information products. This portfolio of information products provides concrete detail that improves the efficiency of day-to-day operations, and equips cabling professionals with the perspective that enables strategic planning for networks’ optimum long-term performance.

Throughout our annual magazine, weekly email newsletters and 24/7/365 website, Cabling Installation & Maintenance digs into the essential topics our audience focuses on.

  • Design, Installation and Testing: We explain the bottom-up design of cabling systems, from case histories of actual projects to solutions for specific problems or aspects of the design process. We also look at specific installations using a case-history approach to highlight challenging problems, solutions and unique features. Additionally, we examine evolving test-and-measurement technologies and techniques designed to address the standards-governed and practical-use performance requirements of cabling systems.
  • Technology: We evaluate product innovations and technology trends as they impact a particular product class through interviews with manufacturers, installers and users, as well as contributed articles from subject-matter experts.
  • Data Center: Cabling Installation & Maintenance takes an in-depth look at design and installation workmanship issues as well as the unique technology being deployed specifically for data centers.
  • Physical Security: Focusing on the areas in which security and IT—and the infrastructure for both—interlock and overlap, we pay specific attention to Internet Protocol’s influence over the development of security applications.
  • Standards: Tracking the activities of North American and international standards-making organizations, we provide updates on specifications that are in-progress, looking forward to how they will affect cabling-system design and installation. We also produce articles explaining the practical aspects of designing and installing cabling systems in accordance with the specifications of established standards.

Cabling Installation & Maintenance is published by Endeavor Business Media, a division of EndeavorB2B.

Contact Cabling Installation & Maintenance

Editorial

Patrick McLaughlin

Serena Aburahma

Advertising and Sponsorship Sales

Peter Fretty - Vice President, Market Leader

Tim Carli - Business Development Manager

Brayden Hudspeth - Sales Development Representative

Subscriptions and Memberships

Subscribe to our newsletters and manage your subscriptions

Feedback/Problems

Send a message to our general in-box

 

Westwater Resources Announces Receipt of NPDES Permit

Milestone Achievement Enables Commencement of Site Grading

Westwater Resources, Inc. (NYSE American: WWR), a battery-grade natural graphite development company (“Westwater” or the “Company”), is pleased to announce it has received an NPDES Permit (“Permit”). The Permit is required to commence site grading at the Coosa Graphite Processing Facility (“Coosa Graphite Plant”) located near Kellyton, Alabama. The Permit has been issued by the State of Alabama under the National Pollutant Discharge Elimination System (“NPDES”) to ensure Westwater’s construction efforts comply with the Federal Clean Water Act as it relates to regulated disturbances and any stormwater runoff from the Coosa Graphite Plant site. The Permit, when coupled with the Company’s Best Management Practices, allows Westwater to commence site grading activities at the Coosa Graphite Plant. Site grading activities, anticipated to begin in March, are those required to prepare for building construction.

”This permitting milestone has been met and allows our construction to proceed on time,” said Chris Jones, President and CEO of Westwater. “This is splendid work on the part of the Operations Team in Alabama.”

Westwater has secured contracts for certain long-lead equipment items and continues to focus on adding key contractors to the construction team. Westwater previously announced its intention to start production of critical graphite materials for Lithium-Ion batteries in 2023, once construction and start up is complete.

About Westwater Resources Inc.

Westwater Resources Inc. (NYSE American: WWR) is focused on developing battery-grade natural graphite materials. The Company’s primary project is the Coosa Graphite Project — the most advanced natural graphite project in the contiguous United States — which includes the Coosa Graphite Plant located near Kellyton, Alabama and the associated Coosa Graphite Deposit located across 41,900 acres (~17,000 hectares) in east-central Alabama. For more information, visit www.westwaterresources.net.

Cautionary Statement Regarding Forward-Looking Statements

This news release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as "expects," "estimates," "projects," "anticipates," "believes," "could," “scheduled,” and other similar words. Forward looking statements include, among other things, statements concerning the schedule related to the construction and completion date of the Company’s Coosa Graphite Plant. The Company cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of the Company; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Westwater’s Annual Report on Form 10-K for the year ended December 31, 2020, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: (a) the Company’s ability to successfully permit and construct the Coosa Graphite Plant on schedules consistent with the Coosa Graphite Project business plan; (b) the ability to control costs and avoid cost and schedule overruns during the development and construction of the Coosa Graphite Plant, due to challenges which include, but are not limited to, changes in labor costs, availability and productivity; challenges with management of contractors or vendors, subcontractor performance, adverse weather conditions; shortages, delays, increased costs or inconsistent quality of equipment, materials and labor, contractor or supplier delays; delays due to judicial or regulatory action; and nonperformance under construction agreements (c) unanticipated geological, processing, regulatory and legal or other problems the Company may encounter in the jurisdictions where the Company operates or intends to operate, including but not limited to Alabama and Colorado (d) the Company’s ability to raise additional capital in the future, including the ability to utilize existing financing facilities; (e) spot price and long-term contract price of graphite and vanadium; (f) risks associated with our construction, permitting and operations, and the associated activities of our partners such as Dorfner Anzaplan and Samuel Engineering, including the impact of COVID-19 and its potential impacts to the capital markets; (g) government regulation of the graphite industry and the vanadium industry; (h) world-wide graphite and vanadium supply and demand, including the supply and demand for energy storage batteries; (i) the ability of the Company to enter into and successfully close acquisitions or other material transactions; (j) any graphite or vanadium discoveries not being in high-enough concentration to make it economic to extract the minerals; and (k) new litigation or arbitration. Except as required by law, the Company disclaims any obligation to update or publicly announce any revisions to any of the forward-looking statements contained in this news release.

Contacts

Westwater Resources Inc.

Christopher M. Jones, President & CEO

Phone: 303.531.0480

Jeff Vigil, VP Finance & CFO

Phone: 303.531.0481

Email: Info@WestwaterResources.net

Product Sales Contact:

Jay Wago, Vice President – Sales and Marketing

Phone: 303.531.0472

Email: Sales@westwaterresources.net

Investor Relations

Porter, LeVay & Rose

Michael Porter, President

Phone: 212.564.4700

Email: Westwater@plrinvest.com

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.