About Cabling Installation & Maintenance

Our mission: Bringing practical business and technical intelligence to today's structured cabling professionals

For more than 30 years, Cabling Installation & Maintenance has provided useful, practical information to professionals responsible for the specification, design, installation and management of structured cabling systems serving enterprise, data center and other environments. These professionals are challenged to stay informed of constantly evolving standards, system-design and installation approaches, product and system capabilities, technologies, as well as applications that rely on high-performance structured cabling systems. Our editors synthesize these complex issues into multiple information products. This portfolio of information products provides concrete detail that improves the efficiency of day-to-day operations, and equips cabling professionals with the perspective that enables strategic planning for networks’ optimum long-term performance.

Throughout our annual magazine, weekly email newsletters and 24/7/365 website, Cabling Installation & Maintenance digs into the essential topics our audience focuses on.

  • Design, Installation and Testing: We explain the bottom-up design of cabling systems, from case histories of actual projects to solutions for specific problems or aspects of the design process. We also look at specific installations using a case-history approach to highlight challenging problems, solutions and unique features. Additionally, we examine evolving test-and-measurement technologies and techniques designed to address the standards-governed and practical-use performance requirements of cabling systems.
  • Technology: We evaluate product innovations and technology trends as they impact a particular product class through interviews with manufacturers, installers and users, as well as contributed articles from subject-matter experts.
  • Data Center: Cabling Installation & Maintenance takes an in-depth look at design and installation workmanship issues as well as the unique technology being deployed specifically for data centers.
  • Physical Security: Focusing on the areas in which security and IT—and the infrastructure for both—interlock and overlap, we pay specific attention to Internet Protocol’s influence over the development of security applications.
  • Standards: Tracking the activities of North American and international standards-making organizations, we provide updates on specifications that are in-progress, looking forward to how they will affect cabling-system design and installation. We also produce articles explaining the practical aspects of designing and installing cabling systems in accordance with the specifications of established standards.

Cabling Installation & Maintenance is published by Endeavor Business Media, a division of EndeavorB2B.

Contact Cabling Installation & Maintenance

Editorial

Patrick McLaughlin

Serena Aburahma

Advertising and Sponsorship Sales

Peter Fretty - Vice President, Market Leader

Tim Carli - Business Development Manager

Brayden Hudspeth - Sales Development Representative

Subscriptions and Memberships

Subscribe to our newsletters and manage your subscriptions

Feedback/Problems

Send a message to our general in-box

 

Fluence Validates Safety of Gridstack Pro 5000 in Benchmark-Setting Fire Safety Tests

ARLINGTON, Va., June 12, 2025 (GLOBE NEWSWIRE) -- Fluence Energy, Inc. ("Fluence") (NASDAQ: FLNC), a global market leader delivering intelligent energy storage, services, and asset optimization software, today announced the successful completion of one of the largest fire safety evaluations in the energy storage industry. In partnership with CSA Group, a leading product testing, inspection, and certification organization, Fluence rigorously tested its high-density Gridstack Pro 5000 Series system. The results of these tests demonstrate that the system not only meets but exceeds current and emerging safety standards.  

Prior to the fire tests, Fluence conducted five days of explosion testing—two days of dispersion testing followed by three days of deflagration testing—continuing to lead the industry as one of the first companies to perform such a comprehensive explosion risk assessment. During dispersion testing, the system’s active ventilation effectively exhausted gases as designed, in compliance with NFPA 69, demonstrating its ability to prevent flammable gas accumulation. During deflagration testing, all six deflagration panels deployed as intended, in accordance with NFPA 68, validating the effectiveness of Gridstack Pro 5000’s passive safety features under extreme conditions.  

Gridstack Pro 5000 is designed to deliver up to 5.6 MWh of energy within a 20-foot enclosure, making it one of the highest density solutions on the market today to undergo this level of testing. To validate its safety at this scale, the system underwent rigorous testing using fully charged batteries. The large-scale fire tests were conducted at Safe Laboratories in North Carolina under the observation of CSA Group. These tests far exceeded the requirements of the current UL 9540A standard and aligned with emerging safety standards, including the forthcoming NFPA 855 (2026).  

Four enclosures containing live batteries were set up using minimum spacings, with the deflagration panels on the center enclosure opened. A fire was deliberately ignited in the center enclosure and allowed to fully develop without the use of fire suppression or firefighting intervention. The results confirmed that Gridstack Pro 5000 enclosures are designed to prevent propagation of battery fires under the conditions tested, even in tightly spaced layouts. No enclosure-to-enclosure propagation occurred, and surrounding battery cells remained within safe limits.  

“We designed Gridstack Pro 5000 to push the boundaries of what is possible in energy storage density, and with that comes a responsibility to prove it can be done safely,” said Peter Williams, Fluence SVP and Chief Product and Supply Chain Officer. “This testing goes far beyond what the industry currently requires and is not only a validation of our design, but a real-world demonstration of how next-generation systems must perform under worst-case scenarios.”  

To promote transparency and technical rigor, Fluence invited independent observers, including subject matter experts from organizations such as Hiller and members of standards development committees, to observe testing at Safe Labs.  

"Fluence continues to show its commitment to fire safety by going above and beyond industry standards," said Paul Hayes, Hiller VP of Energy Infrastructure, Fire Protection Engineer. "The scale and extent of their testing demonstrate readiness to meet the requirements of the upcoming 2026 NFPA 855 safety standard ahead of publication. Gridstack Pro 5000's successful performance under multiple physical test scenarios confirms the system's safety architecture and Fluence's commitment to industry safety standards.” 

Throughout the fire tests, Fluence collected detailed gas sampling data to support plume analysis, emergency response training, and permitting guidance—complementing the company’s broader safety initiatives, including specialized battery energy storage system training for first responders.  

Since 2022, Fluence has advanced safety testing protocols and certification processes across the energy storage industry through deflagration and large-scale fire testing. The company collaborates with leading laboratories to incorporate advanced safety features into its systems, aiming to prevent, detect, and contain thermal events while maximizing energy capacity within increasingly compact footprints. 

About Fluence 


Fluence Energy, Inc. (Nasdaq: FLNC) is a global market leader delivering intelligent energy storage and optimization software for renewables and storage. The Company's solutions and operational services are helping to create a more resilient grid and unlock the full potential of renewable portfolios. With gigawatts of projects successfully contracted, deployed, and under management across nearly 50 markets, the Company is transforming the way we power our world for a more sustainable future. 

For more information, visit our website, or follow us on LinkedIn or X. To stay up to date on the latest industry insights, sign up for Fluence's Full Potential Blog

Cautionary Statement Regarding Forward-Looking Statements    

The statements contained in this press release that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, Section 21E of the Securities Exchange Act of 1934, as amended, and the Private Securities Litigation Reform Act of 1995. Such statements can be identified by the fact that they do not relate strictly to historical or current facts. When used in this press release, words such as “may,” “possible,” “will,” “should,” “expects,” “plans,” “anticipates,” “could,” “intends,” “targets,” “projects,” “commits,” “contemplates,” “believes,” “estimates,” “predicts,” “potential,” or “continue,” or the negative of these terms or other similar expressions and variations thereof and similar words and expressions are intended to identify such forward-looking statements, but the absence of these words does not mean that a statement is not forward-looking. 

The forward-looking statements contained in this press release are based on our current expectations and beliefs concerning future developments, as well as a number of assumptions concerning future events, and their potential effects on our business. These forward-looking statements are not guarantees of performance, and there can be no assurance that future developments affecting our business will be those that we have anticipated. These forward-looking statements involve a number of risks, uncertainties (some of which are beyond our control), or other assumptions that may cause actual results or performance to be materially different from those expressed or implied by these forward-looking statements, which include, but are not limited to, factors set forth under Item 1A.“Risk Factors” in our Annual Report on Form 10-K for the fiscal year ended September 30, 2024, filed with the Securities and Exchange Commission (“SEC”) on November 29, 2024, and in other filings we make with the SEC from time to time. New risks and uncertainties emerge from time to time and it is not possible for us to predict all such risk factors, nor can we assess the effect of all such risk factors on our business or the extent to which any factor or combination of factors may cause actual results to differ materially from those contained in any forward-looking statements. Should one or more of these risks or uncertainties materialize, or should any of the assumptions prove incorrect, actual results may vary in material respects from those projected in these forward-looking statements. You are cautioned not to place undue reliance on any forward-looking statements made in this press release. Each forward-looking statement speaks only as of the date of the particular statement, and we undertake no obligation to publicly update or revise any forward-looking statements to reflect events or circumstances that occur, or which we become aware of, after the date hereof, except as otherwise may be required by law. 

Media Contact 


Shayla Ebsen, Director of Communications 

Email: shayla.ebsen@fluenceenergy.com
Phone: +1 (605) 645-7486 

Analyst Contact 


Lexington May, Vice President of Investor Relations and Sustainability 

Email: investorrelations@fluenceenergy.com
Phone: +1 (713) 909-5629 


Primary Logo

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.