SYDNEY, Dec. 23, 2024 (GLOBE NEWSWIRE) -- IREN Limited (NASDAQ: IREN) (together with its subsidiaries, โIRENโ or โthe Companyโ) today announced it has reached its year-end target of 31 EH/s installed self-mining capacity, surpassing its original goal of 20 EH/s.
Daniel Roberts, Co-Founder and Co-CEO of IREN, commented:
โWeโre proud to achieve 31 EH/s ahead of schedule, far exceeding the initial year-end target.
This year began with just 20MW of operating data centers at Childress, and we successfully expanded that footprint more than 17-fold to 350MW.
This remarkable progress is a testament to our 500+ on-site team, whose disciplined approach to procurement, construction, safety and innovation has been instrumental in achieving our ambitious growth targets. Their efforts provide a strong foundation as we progress toward our next milestone of 50 EH/s in H1 2025.
With industry-leading efficiency, low electricity costs, and unmatched execution capabilities, IREN is positioned as one of the fastest growing and lowest-cost Bitcoin miners globally.โ
31 EH/s Milestone Achieved
Following completion of Childress Phase 3, IREN has increased its installed self-mining capacity from 28 EH/s to 31 EH/s, achieving 15 J/TH efficiency with 510MW of operating data centers.
Childress now supports 350MW of operating capacity, with an additional 400MW of available power at the 750MW project, enabling further expansion in 2025.
On-Track for 50 EH/s in H1 2025
IREN remains well-positioned to achieve its next growth target of 50 EH/s by H1 2025, supported by:
- Ongoing Construction: Civil works, data center erection and electrical installations for Childress Phases 4 & 5 (2 x 150MW) are progressing
- Long-Lead Procurement: Key electrical equipment is secured, with components either on-site or on order
- Proven Execution: Site teams and processes are in place to sustain the cadence of constructing ~50MW of data centers per month
- S21 Pro Miners Secured: Pre-purchased at a fixed price option of $18.9/TH
Childress Phases 1 - 3 (350MW)
Childress Phases 4 - 5 (300MW)
Forward-Looking Statements
This press release includes โforward-looking statementsโ within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements generally relate to future events or IRENโs future financial or operating performance. For example, forward-looking statements include but are not limited to the Companyโs business strategy, expected operational and financial results, and expected increase in power capacity and hashrate. In some cases, you can identify forward-looking statements by terminology such as โanticipate,โ โbelieve,โ โmay,โ โcan,โ โshould,โ โcould,โ โmight,โ โplan,โ โpossible,โ โproject,โ โstrive,โ โbudget,โ โforecast,โ โexpect,โ โintend,โ โtargetโ, โwill,โ โestimate,โ โpredict,โ โpotential,โ โcontinue,โ โscheduledโ or the negatives of these terms or variations of them or similar terminology, but the absence of these words does not mean that statement is not forward-looking. Such forward-looking statements are subject to risks, uncertainties, and other factors which could cause actual results to differ materially from those expressed or implied by such forward-looking statements. In addition, any statements or information that refer to expectations, beliefs, plans, projections, objectives, performance or other characterizations of future events or circumstances, including any underlying assumptions, are forward-looking.
These forward-looking statements are based on managementโs current expectations and beliefs. These statements are neither promises nor guarantees, but involve known and unknown risks, uncertainties and other important factors that may cause IRENโs actual results, performance or achievements to be materially different from any future results performance or achievements expressed or implied by the forward looking statements, including, but not limited to: Bitcoin price and foreign currency exchange rate fluctuations; IRENโs ability to obtain additional capital on commercially reasonable terms and in a timely manner to meet its capital needs and facilitate its expansion plans; the terms of any future financing or any refinancing, restructuring or modification to the terms of any future financing, which could require IREN to comply with onerous covenants or restrictions, and its ability to service its debt obligations, any of which could restrict its business operations and adversely impact its financial condition, cash flows and results of operations; IRENโs ability to successfully execute on its growth strategies and operating plans, including its ability to continue to develop its existing data center sites and to diversify and expand into the market for high performance computing (โHPCโ) solutions it may offer (including the market for AI Cloud Services); IRENโs limited experience with respect to new markets it has entered or may seek to enter, including the market for HPC solutions (including AI Cloud Services); expectations with respect to the ongoing profitability, viability, operability, security, popularity and public perceptions of the Bitcoin network; expectations with respect to the profitability, viability, operability, security, popularity and public perceptions of any current and future HPC solutions (including AI Cloud Services) that IREN offers; IRENโs ability to secure and retain customers on commercially reasonable terms or at all, particularly as it relates to its strategy to expand into markets for HPC solutions (including AI Cloud Services); IRENโs ability to manage counterparty risk (including credit risk) associated with any current or future customers, including customers of its HPC solutions (including AI Cloud Services) and other counterparties; the risk that any current or future customers, including customers of its HPC solutions (including AI Cloud Services), or other counterparties may terminate, default on or underperform their contractual obligations; Bitcoin global hashrate fluctuations; IRENโs ability to secure renewable energy, renewable energy certificates, power capacity, facilities and sites on commercially reasonable terms or at all; delays associated with, or failure to obtain or complete, permitting approvals, grid connections and other development activities customary for greenfield or brownfield infrastructure projects; IRENโs reliance on power and utilities providers, third party mining pools, exchanges, banks, insurance providers and its ability to maintain relationships with such parties; expectations regarding availability and pricing of electricity; IRENโs participation and ability to successfully participate in demand response products and services and other load management programs run, operated or offered by electricity network operators, regulators or electricity market operators; the availability, reliability and/or cost of electricity supply, hardware and electrical and data center infrastructure, including with respect to any electricity outages and any laws and regulations that may restrict the electricity supply available to IREN; any variance between the actual operating performance of IRENโs miner hardware achieved compared to the nameplate performance including hashrate; IRENโs ability to curtail its electricity consumption and/or monetize electricity depending on market conditions, including changes in Bitcoin mining economics and prevailing electricity prices; actions undertaken by electricity network and market operators, regulators, governments or communities in the regions in which IREN operates; the availability, suitability, reliability and cost of internet connections at IRENโs facilities; IRENโs ability to secure additional hardware, including hardware for Bitcoin mining and any current or future HPC solutions (including AI Cloud Services) it offers, on commercially reasonable terms or at all, and any delays or reductions in the supply of such hardware or increases in the cost of procuring such hardware; expectations with respect to the useful life and obsolescence of hardware (including hardware for Bitcoin mining as well as hardware for other applications, including any current or future HPC solutions (including AI Cloud Services) IREN offers); delays, increases in costs or reductions in the supply of equipment used in IRENโs operations; IRENโs ability to operate in an evolving regulatory environment; IRENโs ability to successfully operate and maintain its property and infrastructure; reliability and performance of IRENโs infrastructure compared to expectations; malicious attacks on IRENโs property, infrastructure or IT systems; IRENโs ability to maintain in good standing the operating and other permits and licenses required for its operations and business; IRENโs ability to obtain, maintain, protect and enforce its intellectual property rights and confidential information; any intellectual property infringement and product liability claims; whether the secular trends IREN expects to drive growth in its business materialize to the degree it expects them to, or at all; any pending or future acquisitions, dispositions, joint ventures or other strategic transactions; the occurrence of any environmental, health and safety incidents at IRENโs sites, and any material costs relating to environmental, health and safety requirements or liabilities; damage to IRENโs property and infrastructure and the risk that any insurance IREN maintains may not fully cover all potential exposures; ongoing proceedings relating in part to the default, and any future litigation, claims and/or regulatory investigations, and the costs, expenses, use of resources, diversion of management time and efforts, liability and damages that may result therefrom; IREN's failure to comply with any laws including the anti-corruption laws of the United States and various international jurisdictions; any failure of IREN's compliance and risk management methods; any laws, regulations and ethical standards that may relate to IRENโs business, including those that relate to Bitcoin and the Bitcoin mining industry and those that relate to any other services it offers, including laws and regulations related to data privacy, cybersecurity and the storage, use or processing of information and consumer laws; IRENโs ability to attract, motivate and retain senior management and qualified employees; increased risks to IRENโs global operations including, but not limited to, political instability, acts of terrorism, theft and vandalism, cyberattacks and other cybersecurity incidents and unexpected regulatory and economic sanctions changes, among other things; climate change, severe weather conditions and natural and man-made disasters that may materially adversely affect IRENโs business, financial condition and results of operations; public health crises, including an outbreak of an infectious disease (such as COVID-19) and any governmental or industry measures taken in response; IRENโs ability to remain competitive in dynamic and rapidly evolving industries; damage to IRENโs brand and reputation; expectations relating to Environmental, Social or Governance issues or reporting; the costs of being a public company; the increased regulatory and compliance costs of IREN ceasing to be a foreign private issuer and an emerging growth company, as a result of which we will be required, among other things, to file periodic reports and registration statements on U.S. domestic issuer forms with the SEC commencing with our next fiscal year, prepare our financial statements in accordance with U.S. GAAP rather than IFRS, and to modify certain of our policies to comply with corporate governance practices required of U.S. domestic issuers; and other important factors discussed under the caption โRisk Factorsโ in IRENโs annual report on Form 20-F filed with the SEC on August 28, 2024 as such factors may be updated from time to time in its other filings with the SEC, accessible on the SECโs website at www.sec.gov and the Investor Relations section of IRENโs website at https://investors.iren.com.
These and other important factors could cause actual results to differ materially from those indicated by the forward-looking statements made in this investor update. Any forward-looking statement that IREN makes in this investor update speaks only as of the date of such statement. Except as required by law, IREN disclaims any obligation to update or revise, or to publicly announce any update or revision to, any of the forward-looking statements, whether as a result of new information, future events or otherwise.
About IREN
IREN is a leading data center business powering the future of Bitcoin, AI and beyond utilizing 100% renewable energy.
- Bitcoin Mining: providing security to the Bitcoin network, expanding to 50 EH/s in H1 2025. Operations since 2019.
- AI Cloud Services: providing cloud compute to AI customers, 1,896 NVIDIA H100 & H200 GPUs. Operations since 2024.
- Next-Generation Data Centers: 510MW of operating data centers, expanding to 810MW in H1 2025. Specifically designed and purpose-built infrastructure for high-performance and power-dense computing applications.
- Technology: technology stack for performance optimization of AI Cloud Services and Bitcoin Mining operations.
- Development Portfolio: 2,310MW of grid-connected power secured across North America, >2,000 acre property portfolio and additional development pipeline.
- 100% Renewable Energy (from clean or renewable energy sources or through the purchase of RECs): targets sites with low-cost & underutilized renewable energy, and supports electrical grids and local communities.
Contacts
| Media Jon Snowballย ย Sodali & Co +61 477 946 068 Megan Boles Aircover Communications +1 562 537 7131 megan.boles@aircoverpr.com | Investors Lincoln Tan IREN +61 407 423 395 lincoln.tan@iren.com | ย |
To keep updated on IRENโs news releases and SEC filings, please subscribe to email alerts at https://iren.com/investor/ir-resources/email-alerts.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/0ab2d3f8-8618-4867-a3de-f8e9ad0f10ee
https://www.globenewswire.com/NewsRoom/AttachmentNg/5c12df6b-7738-47a2-bc7a-8d93f26de8ab