VANCOUVER, BC / ACCESSWIRE / June 25, 2024 / Skeena Resources Limited (TSX:SKE)(NYSE:SKE) ("Skeena" or the "Company") is pleased to announce that it has secured a financing package totaling US$750 million (equivalent to over C$1 billion) with Orion Resource Partners ("Orion") for the development, construction, and general working capital required to advance the Company's 100%-owned Eskay Creek Gold-Silver Project ("Eskay" or the "Project"). This complete funding package significantly de-risks the Project and provides Skeena with optionality, flexibility and stakeholder alignment as the Company progresses Eskay towards production in the first half of 2027. The package provides a significant portion of financing prior to Skeena's receipt of required permits in respect to the Eskay project and therefore, allows the Company to advance the project on the most efficient and expedient schedule to production. Financing Package Highlights: The total financing package of US$750 million is comprised of an equity investment, gold stream, senior secured loan, and a cost over-run facility:
Walter Coles, Executive Chairman of Skeena, commented: "This complete financing package is a result of a competitive and comprehensive process undertaken to find the best financing solution for the Company. The result is certainty of funding to advance Eskay into production while balancing attractive cost of capital, flexibility, and optionality. We welcome Orion alongside existing shareholders as an aligned and committed stakeholder, further validating the merits of the project." "We designed the financing package to provide the Company with important strategic flexibility and significant funding prior to final permits, while maintaining optionality as we continue working to maximize stakeholder value by advancing the Project. On the back of our positive definitive feasibility study released in November 2023, this financing package lays the foundation on which we build Eskay - unlocking value for all our stakeholders as we progress through this stage of growth." Equity Investment - US$100,000,000
Gold Stream - US$200,000,000
Senior Secured Loan - US$350,000,000
Cost Over-run Facility - US$100,000,000
Conclusion: Fully Funded The Company's definitive feasibility study released in November 2023 estimated Eskay's pre-production capital expenditures to be US$528 million (C$713 million), including a US$36 million (C$49 million) contingency. The total financing package of US$750 million, combined with US$44 million (C$59 million) of cash and cash equivalents as of March 31, 2024, provides Skeena with approximately US$794 million of available capital towards the Project, which is substantially more than the remaining estimated capital expenditures required to bring Eskay back into production. With no precious metals hedging or concentrate off-take requirements, the Company retains excellent upside to increasing metals prices. Eskay Timeline The Skeena Management team is focused on advancing the Project in a disciplined manner. With project financing committed, the Company is now working to finalize the 2024 early works programs and detailed engineering plans. Proceeding with the early works program will mitigate timing pressures as Skeena completes the environmental assessment and permitting process. Upcoming development milestones target dates include:
Community Benefit Skeena has always prioritized community engagement and collaboration as crucial elements for ensuring the success of the Project. Skeena acknowledges that its social license to operate must be strongly supported by collaboration and investment in its partnership with the Tahltan Nation. During 2023, Skeena continued investing in the social and economic well-being of the local communities:
To date, the Project has created over C$180 million in wages, contracts, and community contributions for Tahltan-related companies and organizations. Skeena is projecting a further potential C$700 million in contracts to Tahltan businesses throughout the life of the mine. This mine will provide significant long-term value for both the national and local economies. The Company always prioritizes hiring local employees and local suppliers wherever possible. The Project will create over 800 direct jobs and potentially 2,000 jobs for outside service and contract organizations. The Project is expected to contribute roughly C$1.5 billion in direct tax revenue to British Columbia and Canada over the life of the mine. The Company is confident that through further exploration on Skeena's vast property package, the mine life for Eskay will likely be extended beyond the current estimated mine life of 12 years, providing steady employment and long-term jobs to be filled by members of the local communities of northwestern British Columbia.
About Skeena Skeena is a fully financed leading gold developer that is focused on advancing the Eskay Creek Gold-Silver Project and the Snip Gold Project - two past producing mines located in the renowned Golden Triangle in British Columbia, Canada. Eskay Creek represents one of the highest-grade and lowest cost open-pit precious metals mines in the world, with substantial silver by-product production that surpasses many primary silver mines. Skeena is committed to sustainable mining practices and maximizing the potential of its mineral resources. In partnership with the Tahltan First Nation, Skeena strives to foster positive relationships with Indigenous communities while delivering long-term value and sustainable growth for its stakeholders. On behalf of the Board of Directors of Skeena Resources Limited,
Contact Information Investor Inquiries: info@skeenaresources.com Qualified Persons In accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects, Paul Geddes, P.Geo., Senior Vice President, Exploration & Resource Development, is the Qualified Person for the Company and has prepared, validated, and approved the technical and scientific content of this news release. The Company strictly adheres to CIM Best Practices Guidelines in conducting, documenting, and reporting the exploration activities on its projects. Cautionary note regarding forward-looking statements Certain statements and information contained or incorporated by reference in this press release constitute "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation (collectively, "forward-looking statements"). These statements relate to future events or our future performance. The use of words such as "anticipates", "believes", "proposes", "contemplates", "generates", "targets", "is projected", "is planned", "considers", "estimates", "expects", "is expected", "potential" and similar expressions, or statements that certain actions, events or results "may", "might", "will", "could", or "would" be taken, achieved, or occur, may identify forward-looking statements. All statements other than statements of historical fact are forward-looking statements. Specific forward-looking statements contained herein include, but are not limited to, statements regarding the progress of development at Eskay, including the construction budget, schedule and required funding in respect thereof; the timing for and the Company's progress towards commencement of commercial production; the Company's capital structure; the Company's ability to buy back the gold stream in the future; amounts drawn and the timing of and completion of conditions precedent in respect of the Senior Secured Loan, gold stream agreement, additional equity investment and the cost over-run facility, the availability of the Senior Secured Loan as a source of future liquidity; andthe results of the Definitive Feasibility Study, processing capacity of the mine, anticipated mine life, probable reserves, estimated project capital and operating costs, sustaining costs, results of test work and studies, planned environmental assessments, the future price of metals, metal concentrate, and future exploration and development. Such forward-looking statements are based on material factors and/or assumptions which include, but are not limited to, the estimation of mineral resources and reserves, the realization of resource and reserve estimates, metal prices, taxation, the estimation, timing and amount of future exploration and development, capital and operating costs, the availability of financing, the receipt of regulatory approvals, environmental risks, title disputes and the assumptions set forth herein and in the Company's MD&A for the year ended December 31, 2023, its most recently filed interim MD&A, and the Company's Annual Information Form ("AIF") dated March 28, 2024. Such forward-looking statements represent the Company's management expectations, estimates and projections regarding future events or circumstances on the date the statements are made, and are necessarily based on several estimates and assumptions that, while considered reasonable by the Company as of the date hereof, are not guarantees of future performance. Actual events and results may differ materially from those described herein, and are subject to significant operational, business, economic, and regulatory risks and uncertainties. The risks and uncertainties that may affect the forward-looking statements in this news release include, among others: the inherent risks involved in exploration and development of mineral properties, including permitting and other government approvals; changes in economic conditions, including changes in the price of gold and other key variables; changes in mine plans and other factors, including accidents, equipment breakdown, bad weather and other project execution delays, many of which are beyond the control of the Company; environmental risks and unanticipated reclamation expenses; and other risk factors identified in the Company's MD&A for the year ended December 31, 2023, its most recently filed interim MD&A, the AIF dated March 28, 2024, the Company's short form base shelf prospectus dated January 31, 2023, and in the Company's other periodic filings with securities and regulatory authorities in Canada and the United States that are available on SEDAR+ at www.sedarplus.ca or on EDGAR at www.sec.gov. Readers should not place undue reliance on such forward-looking statements. Any forward-looking statement speaks only as of the date on which it is made and the Company does not undertake any obligations to update and/or revise any forward-looking statements except as required by applicable securities laws. Cautionary note to U.S. Investors concerning estimates of Mineral Reserves and Mineral Resources Skeena's Mineral Reserves and Mineral Resources included or incorporated by reference herein have been estimated in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") as required by Canadian securities regulatory authorities, which differ from the requirements of U.S. securities laws. The terms "Mineral Reserve", "Proven Mineral Reserve", "Probable Mineral Reserve", "Mineral Resource", "Measured Mineral Resource", "Indicated Mineral Resource" and "Inferred Mineral Resource" are defined in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") "CIM Definition Standards - For Mineral Resources and Mineral Reserves" adopted by the CIM Council (as amended, the "CIM Definition Standards"). These standards differ significantly from the mineral property disclosure requirements of the U.S. Securities and Exchange Commission in Regulation S-K Subpart 1300 (the "SEC Modernization Rules"). Skeena is not currently subject to the SEC Modernization Rules. Accordingly, Skeena's disclosure of mineralization and other technical information may differ significantly from the information that would be disclosed had Skeena prepared the information under the SEC Modernization Rules. In addition, investors are cautioned not to assume that any part, or all of, Skeena's mineral deposits categorized as "Inferred Mineral Resources" or "Indicated Mineral Resources" will ever be converted into Mineral Reserves. "Inferred Mineral Resources" have a great amount of uncertainty as to their existence, and a great amount of uncertainty as to their economic and legal feasibility. Accordingly, investors are cautioned not to assume that any "Inferred Mineral Resources" that Skeena reports are or will be economically or legally mineable. Under Canadian securities laws, estimates of "Inferred Mineral Resources" may not form the basis of feasibility or prefeasibility studies, except for a Preliminary Economic Assessment as defined under NI 43-101. For these reasons, the Mineral Reserve and Mineral Resource estimates and related information presented herein may not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements under the U.S. federal securities laws and the rules and regulations thereunder. SOURCE: Skeena Resources Limited View the original press release on accesswire.com More NewsView MoreVia MarketBeat
NVIDIA Nears Buy Zone as Rumors Swirl About China Chip Deal ↗
Today 14:23 EST
Via MarketBeat
Tickers
NVDA
These 3 Tech Companies Are Suddenly Paying Bigger Dividends ↗
Today 13:02 EST
BJ’s Wholesale Club and the Case for a Bullish Market Reversal ↗
Today 11:45 EST
Via MarketBeat
Tickers
BJ
Recent QuotesView More
Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes. By accessing this page, you agree to the Privacy Policy and Terms Of Service.
© 2025 FinancialContent. All rights reserved.
|