ENDEAVOUR ACHIEVES FIRST GOLD POUR AT LAFIGUร MINE IN CรTE DโIVOIRE
Constructed in only 21 months ยท Delivered on budget and ahead of schedule ยท Investment phase completed
HIGHLIGHTS:
|
Abidjan, 2 July 2024 โ Endeavour Mining plc (LSE:EDV, TSX:EDV, OTCQX:EDVMF) (โEndeavourโ, the โGroupโ or the โCompanyโ) is pleased to announce that the first gold pour from the Lafiguรฉ mine in Cรดte dโIvoire was achieved on 28 June 2024, marking the successful delivery of the project construction on budget and a quarter ahead of schedule.
Ian Cockerill, CEO, commented โWe are proud to have achieved our first gold pour at Lafiguรฉ, which, alongside the first gold pour at the Sabodala-Massawa BIOXยฎ expansion that we achieved in April, marks the successful completion of the recent phase of investment and growth that we started in Q2-2022. We now begin a new phase of increased free cash flow generation, de-levering and enhanced shareholder returns.
The Lafiguรฉ project is the fifth project that we have successfully built in West Africa in the last decade, which is a testament to the strength of our in-house project construction team and is a demonstration of our competitive advantage in West Africa, the worldโs most prospective and largest gold producing region.
Lafiguรฉ is an excellent example of our ability to leverage this advantage by self-generating a project pipeline. We discovered Lafiguรฉ for a cost of $31 million, equivalent to an industry-low discovery cost of just $12 per ounce of M&I resources. The project was quickly advanced through technical studies and permitting, before construction was launched in Q4-2022, and first gold was delivered only 21 months later for a low capital intensity of approximately $150/oz of M&I resources. In less than eight years we have transformed Lafiguรฉ from a discovery to production, creating a cornerstone asset that has the potential to produce over 200koz per year, at an industry leading all-in sustaining cost of approximately $900/oz for at least 13 years, improving the quality of our existing portfolio.
We believe this level of value creation is repeatable in West Africa, and we have already identified the Assafou deposit on the Tanda-Iguela property in Cรดte dโIvoire, where we have delineated a top tier resource and another potential cornerstone asset, which will underpin our next phase of organic growth in a few years time.
With the current phase of organic growth completed, we are now focused on quickly ramping up our recent development projects to maximise their returns and support our near-term capital allocation priorities of de-levering our balance sheet and enhancing our shareholder returns.โ
Since the start of wet commissioning on 30 May 2024, approximately 77kt of ore has been processed through the Lafiguรฉ processing plant, with all circuits operating in line with expectations. The first gold pour included gold from both the gravity and CIL circuits, and yielded approximately 380 ounces of gold. The Lafiguรฉ mine is expected to achieve commercial production and ramp up to its nameplate capacity of 4.0Mtpa in Q3-2024.
Figure 1: First gold pour at the Lafiguรฉ mine

Figure 2: Paul Day, General Manager at Lafiguรฉ with the first gold bar poured at the mine

ABOUT THE LAFIGUร MINE
The Lafiguรฉ mine is located towards the northern end of the Birimian aged Oumรฉ-Fetekro greenstone belt, in north-central Cรดte dโIvoire, approximately 500km from Abidjan by road. The Lafiguรฉ deposit is located in the northeast part of the Fetekro exploration permit, adjacent to existing infrastructure, including sealed paved roads and high voltage grid power. Endeavour has an 80% ownership stake in the Lafiguรฉ mine (with 10% owned by the Ivorian Government and 10% owned by SODEMI, a state-owned mining company) and a 100% ownership stake in the remainder of the Fetekro exploration licence.
Endeavour began exploration on the Fetekro property in March 2017, following a strategic assessment of its exploration tenements which identified the project as a top priority target. To date, only a limited portion of the Fetekro property has been explored, as the priority has been the delineation of the Lafiguรฉ deposit. A maiden Mineral Resource Estimate for the Lafiguรฉ deposit was published on 29 October 2018 and subsequently updated on 3 September 2019, 18 August 2020 and 15 May 2022. A Preliminary Economic Assessment (โPEAโ) was published on 18 August 2020 and a Preliminary Feasibility Study (โPFSโ) was completed with the effective date of 31 December 2020.
Construction of the Lafiguรฉ project in Cรดte d'Ivoire was launched in Q4-2022, following the completion of a Definitive Feasibility Study (โDFSโ) which confirmed Lafiguรฉโs potential to be a cornerstone asset for Endeavour. The 2022 DFS contemplates a 12.8 year LOM with average annual production of 203koz at a low AISC of $871/oz, with an initial capital cost of $448 million. The project DFS displayed robust economics at an $1,800/oz gold price assumption including an after-tax NPV5% of $870m and an after-tax IRR of 33%. For FY-2024, Lafiguรฉ is expected to produce between 90-110koz at an AISC of between $900-975/oz.
As at 31 December 2023, Proven and Probable reserves totalled 49.8Mt at 1.69 g/t containing 2.7Moz of gold and Measured and Indicated resources (inclusive of reserves) totalled 46.2Mt at 2.04 g/t containing 3.0Moz of gold.
Given the strong exploration potential, Endeavour is targeting the discovery of 1.2 โ 1.8Moz of Indicated resources across the Lafiguรฉ mining permit and the wider Fetekro exploration permit area over the 2021 to 2025 period at a discovery cost of $14/oz. To date 0.6Moz, or 50% of the lower end of the target, has been discovered.
QUALIFIED PERSONS
Mark Morcombe, COO of Endeavour Mining plc., a Fellow of the Australasian Institute of Mining and Metallurgy, is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and approved the technical information in this news release.
CONTACT INFORMATION
| Jack Garman Vice President, Investor Relations +44 203 011 2723 jack.garman@endeavourmining.com | Brunswick Group LLP in London Carole Cable, Partner +44 207 404 5959 ccable@brunswickgroup.com |
ABOUT ENDEAVOUR MINING PLC
Endeavour Mining is one of the worldโs senior gold producers and the largest in West Africa, with operating assets across Senegal, Cote dโIvoire and Burkina Faso and a strong portfolio of advanced development projects and exploration assets in the highly prospective Birimian Greenstone Belt across West Africa.
A member of the World Gold Council, Endeavour is committed to the principles of responsible mining and delivering sustainable value to its employees, stakeholders and the communities where it operates. Endeavour is listed on the London and Toronto Stock Exchanges, under the symbol EDV.
For more information, please visit www.endeavourmining.com.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION
This news release contains "forward-looking statements" within the meaning of applicable securities laws.ย All statements, other than statements of historical fact, are "forward-looking statements".ย Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "expected", "budgeted", "forecasts", and "anticipates".
Forward-looking statements, while based on management's best estimates and assumptions, are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the successful integration of acquisitions; risks related to international operations; risks related to general economic conditions and credit availability, actual results of current exploration activities, unanticipated reclamation expenses; changes in project parameters as plans continue to be refined; fluctuations in prices of metals including gold; fluctuations in foreign currency exchange rates, increases in market prices of mining consumables, possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; delays in the completion of development or construction activities, changes in national and local government regulation of mining operations, tax rules and regulations, and political and economic developments in countries in which Endeavour operates. Although Endeavour has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Please refer to Endeavour's most recent Annual Information Form filed under its profile at www.sedarplus.ca for further information respecting the risks affecting Endeavour and its business.
Attachment